MSBA Moves Taconic High School Project To Design Phase

By Andy McKeeveriBerkshires Staff
Print Story | Email Story
The state approved the plan to build a new school.
PITTSFIELD, Mass. — The Massachusetts School Building Authority agreed Wednesday to move to the design phase for a brand new Taconic High School.
 
The Board of Directors voted in favor of the moving the project to the schematic design phase when architects will design the final product. 
 
"Listening to the needs of a community and developing projects accordingly are priorities at the MSBA, and the Taconic High School project is a case study in that sentiment," said Treasurer Steven Grossman said in a statement.
 
"Thanks to our collaborative work with local officials, we are working to build a safe and modern educational facility that will provide students with a top-notch learning environment."
 
The project is expected to cost in the $115,700,000 range, with the final numbers being fleshed out in the coming months. 
 
"Production and approval of a schematic design will help us to determine the final budget for the potential project," MSBA Executive Director Jack McCarthy said.
 
Locally, the city would borrow that amount and receive about 80 percent reimbursements for a majority of the items. In total, the city is expect to pay about $40 million with the state covering the rest.
 
"We then begin discussions with the City Council. I am guardedly optimistic for their support, too," Mayor Daniel Bianchi said. "I think a new career, vocational high school fits in with everything else we are trying to do. We've got the Berkshire Innovation Center, which is going to help small businesses grow ... 
 
"But, it is really going to help direct the way our applied materials companies and our life sciences companies grow in the future."
 
The mayor calls the project part of the "master plan" for business development — with the school feeding to Berkshire Community College and then to the local businesses. 
 
A new 247,770 square-foot school built to accommodate 920 students was chosen as the preferred option by the School Building Needs Commission. The commission opted for new construction over renovating the current building or a mixture of renovation and new construction.
 
The current building will be occupied throughout the two-year construction. The new building will be located across the driveway to the north, where ball fields are currently located.
 
After construction, the students will move into the new building and the current structure will be torn down.
 
Architects Drumney Rosane & Anderson Architects Inc. and consultants Skanska USA has led the city through the feasibility study to get to this point. 

Tags: MSBA,   Taconic High,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield Woman Dies After Being Rescued From Structure Fire

By Brittany PolitoiBerkshires Staff
PITTSFIELD, Mass. — The woman who was rescued when her home caught fire on Monday has died. 
 
The Berkshire District Attorney's Office confirmed on Tuesday that Susan Steenstrup, 67, died after she was pulled from the blaze at 1 Marlboro Drive. The cause of death has not been confirmed.
 
Steenstrup was found on the second-floor by firefighters who responded to the blaze at about 6:45 p.m. She was taken by County Ambulance to Berkshire Medical Center. 
 
The two-story, 1930s home is coned off and shows signs of the emergency response such as a broken front window where crews entered to rescue Steenstrup. The fire was reported to have spread from the kitchen and a cause has not yet been determined.
 
Steenstrup was the only occupant at the time. The home had been in her family since at least the 1960s. 
View Full Story

More Pittsfield Stories