Church Street Reconstruction in Lenox Set Through Fall
LENOX, Mass. — The schedule for continued $1.6 million reconstruction on Church Street has been released by the Lenox Chamber of Commerce to keep local businesses apprised of the work.The repairs are part of a $7.5 million reconstruction of downtown roads in the town. Off-street work on the new Curtis Park will begin on Monday, Aug. 31; the travel lanes will remain open.
Frequent updates will be provided as the schedule is subject to change.
Excavation on the schedule means sidewalk removal plus the mid-block crossing on Lower Church during Weeks 8 and 9. The first three weeks will focus on the west side of Church Street. Intersection work at Housatonic and Church streets will be done during Weeks 4 through 7, with half of the intersection closed at a time.
Upper Church Street Southern end |
Upper Church Street Northern end |
|
Sept. 8 (Week 1) | Excavation, electric, Walker Street | Drainage intersection |
Sept. 14 (Week 2) |
Curb, gravel grade, electric | Drainage, excavation |
Sept. 21 (Week 3) |
Curb, gravel, grade, electric | Drainage, excavation |
Sept. 28 (Week 4) | Pavers, excavation, intersection |
Excavation, electrical & electric |
Oct. 5 (Week 5) |
Pavers, intersection gravel, grade | Excavation, electrical, curb, gravel, grade |
Oct. 12 (Week 6) |
Pavers, intersection gravel, grade | Excavation, electrical, curb, gravel, grade |
Oct. 19 (Week 7) |
Pavers, intersection gravel, grade | Excavation, electrical, curb, gravel, grade |
Oct. 26 (Week 8) |
Landscape trees, pavers, intersection | Excavation Street, pavers, crosswalks, curb, landscape, electrical |
Nov. 2 (Week 9) |
Landscape trees, pavers, intersection | Excavation Street, pavers, crosswalks, curb, landscape, electrical |
Nov. 9 (Week 10) |
Mill Road | Curb, gravel, grade electrical, pavers, landscape |
Nov.16 (Week 11) |
Cleanup, pave | Cleanup, landscape, pave, electrical |
Nov. 23 (Week 12) |
Benches, trash receptacles | Bench, trash receptacles, signs, markings |