image description
Adams will be selecting a designer to bring one element of the Greylock Glen project, a multi-use center, to reality.

Greylock Glen Resort Outdoor Center Receives 13 Design Bids

By Jack GuerinoiBerkshires Staff
Print Story | Email Story
ADAMS, Mass. — Thirteen may be the lucky number for the town of Adams. 
 
The town, the designated developer of the Greylock Glen, has received 13 proposals from architectural firms interested in designing the "Greylock Glen Resort Outdoor Center."
 
"It's an excellent response," Town Administrator Tony Mazzucco said. "It is for the design of the outdoor center so you'd expect many bidders but 13 gives us a great number of design options and price ranges to choose from."  
 
The town's been working for decades to get something on 56 acres of the 1,000-acre glen, which lies at the foot of the Mount Greylock State Reservation in Adams. Since being named the developer nearly a decade ago, extensive design has been done for trails through the pristine landscape and preliminary road and infrastructure work has been completed in the last few years. A lodge, conference center and ampitheatre is planned along with a primitive campground. 
 
But it's been difficult to get the estimated $50 million project off the ground. Only one application of interest was received for the campground project in December from local artist and entrepreneur Ralph Brill. And the last time the outdoor center and lodging was put out to bid five years ago, not a single developer was interested
 
This time was different, with the town only requesting design services for just the $5 million, 11,000 square-foot multi-use center. Thirteen bids were received in early February from firms in Massachusetts, Vermont and Connecticut.
 
Arcade, of Pittsfield, was the only bidder from Berkshire County. Also submitting bids were Austin Design Inc. of Colrain; C & H Architects of Amherst; Bargmann Hendrie & Archetype Inc., DHK Inc., Oudens Ello Architecture, Touloukian Touloukian Inc. and Design Lab Architects, all of Boston; Maryann Thompson Architects of Watertown; LDA Architecture & Interiors of Cambridge; Charles Rose Architects Inc. of Somerville; Centerbrook Architects & Planners of Centerbrook, Conn., and William Maclay Architects of Waitsfield, Vt.
 
"We have design funds in hand and the construction funds are earmarked in a state bond bill, so were very excited to be progressing," Mazzucco said. "These are exciting times."
 
The proposed building will contain a welcome area, exhibit space, a media room, four classrooms and a concession area. The town is asking the building be net zero, so the selected designer is expected to have experience in green building technologies and energy efficiency.
 
The center will have a public focus but may also be the location of a future Massachusetts College of Liberal Arts' field station for its Environmental Studies program
 
Also, there is an interest in housing a Nordic ski center to be run by a private operator.
 
The chosen firm will not only work with the town during the design process but is expected to be involved in the public review process, and work with the town to secure construction funding for the proposed facility.
 
With initial trail work begun last summer, and bids in hand for at least two of the proposed elements, the long-awaited Greylock Glen development finally appears to be picking up speed.

Tags: Greylock Glen,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Greylock Glen Outdoor Center 90% Complete

By Tammy DanielsiBerkshires Staff
ADAMS, Mass. — The Greylock Glen Outdoor Center is about 90 percent finished with an anticipated completion date in August. 
 
Matthew Sturz of owner's project manager Colliers International updated the Selectmen on the project's progress via Zoom on Wednesday. 
 
"We'll work with the town to determine exactly the logistics of that," he said in response to questions about the opening. "I think that there's certainly interest in getting the facility open as soon as it can open. But we do need to conclude the construction activities ... it's not federally advisable to have construction activity going on with the public."
 
The completion will depend on getting a certificate of occupancy for the 10,000-square foot facility.
 
The  $8.3 million project is running eight months behind the expected schedule, Sturz said, largely because of permitting with the state Department of Environmental Protection that required an extensive environmental review of endangered species, working with National Grid to determine how solar will be integrated into the project, and the need for a water system for both potable water and fire suppression. 
 
"Transformers and all manner of electrical switchgear is being significantly impacted by supply chain issues throughout the construction industry," said Sturz. "So coordinating those items up front took a little bit longer than anticipated."
 
A 350,000-gallon water tank is being constructed on the grounds to provide water with completion expected by July or August. 
 
View Full Story

More Adams Stories