ADAMS, Mass. — Thirteen may be the lucky number for the town of Adams.
The town, the designated developer of the Greylock Glen, has received 13 proposals from architectural firms interested in designing the "Greylock Glen Resort Outdoor Center."
"It's an excellent response," Town Administrator Tony Mazzucco said. "It is for the design of the outdoor center so you'd expect many bidders but 13 gives us a great number of design options and price ranges to choose from."
The town's been working for decades to get something on 56 acres of the 1,000-acre glen, which lies at the foot of the Mount Greylock State Reservation in Adams. Since being named the developer nearly a decade ago, extensive design has been done for trails through the pristine landscape and preliminary road and infrastructure work has been completed in the last few years. A lodge, conference center and ampitheatre is planned along with a primitive campground.
But it's been difficult to get the estimated $50 million project off the ground. Only one application of interest was received for the campground project in December from local artist and entrepreneur Ralph Brill. And the last time the outdoor center and lodging was put out to bid five years ago, not a single developer was interested.
This time was different, with the town only requesting design services for just the $5 million, 11,000 square-foot multi-use center. Thirteen bids were received in early February from firms in Massachusetts, Vermont and Connecticut.
Arcade, of Pittsfield, was the only bidder from Berkshire County. Also submitting bids were Austin Design Inc. of Colrain; C & H Architects of Amherst; Bargmann Hendrie & Archetype Inc., DHK Inc., Oudens Ello Architecture, Touloukian Touloukian Inc. and Design Lab Architects, all of Boston; Maryann Thompson Architects of Watertown; LDA Architecture & Interiors of Cambridge; Charles Rose Architects Inc. of Somerville; Centerbrook Architects & Planners of Centerbrook, Conn., and William Maclay Architects of Waitsfield, Vt.
"We have design funds in hand and the construction funds are earmarked in a state bond bill, so were very excited to be progressing," Mazzucco said. "These are exciting times."
The proposed building will contain a welcome area, exhibit space, a media room, four classrooms and a concession area. The town is asking the building be net zero, so the selected designer is expected to have experience in green building technologies and energy efficiency.
The center will have a public focus but may also be the location of a future Massachusetts College of Liberal Arts' field station for its Environmental Studies program
Also, there is an interest in housing a Nordic ski center to be run by a private operator.
The chosen firm will not only work with the town during the design process but is expected to be involved in the public review process, and work with the town to secure construction funding for the proposed facility.
With initial trail work begun last summer, and bids in hand for at least two of the proposed elements, the long-awaited Greylock Glen development finally appears to be picking up speed.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Greylock Glen Outdoor Center 90% Complete
By Tammy DanielsiBerkshires Staff
ADAMS, Mass. — The Greylock Glen Outdoor Center is about 90 percent finished with an anticipated completion date in August.
Matthew Sturz of owner's project manager Colliers International updated the Selectmen on the project's progress via Zoom on Wednesday.
"We'll work with the town to determine exactly the logistics of that," he said in response to questions about the opening. "I think that there's certainly interest in getting the facility open as soon as it can open. But we do need to conclude the construction activities ... it's not federally advisable to have construction activity going on with the public."
The completion will depend on getting a certificate of occupancy for the 10,000-square foot facility.
The $8.3 million project is running eight months behind the expected schedule, Sturz said, largely because of permitting with the state Department of Environmental Protection that required an extensive environmental review of endangered species, working with National Grid to determine how solar will be integrated into the project, and the need for a water system for both potable water and fire suppression.
"Transformers and all manner of electrical switchgear is being significantly impacted by supply chain issues throughout the construction industry," said Sturz. "So coordinating those items up front took a little bit longer than anticipated."
A 350,000-gallon water tank is being constructed on the grounds to provide water with completion expected by July or August.
Michael Wynn, who was selected in January to run the center, submitted a level operating budget of $57,500 but said he could pull funding from different lines to ensure there was money for advertising this fall.
click for more
The Selectmen on Wednesday night voted to award the bid to Mackin Construction Co. Inc. of Greenfield, which plans to invest $11 million to build out 20 or more one- and two-bedroom apartments in the three-story classroom wing that parallels Columbia Street.
click for more
The Selectmen two weeks ago had requested the utility appear before the board after receiving numerous complaints over flickering lights, including in Town Hall.
click for more
Taylor Garabedian scored a team-high 22 points and grabbed five rebounds, and Abby Scialabba scored 16 points for the ‘Canes, who got 16 points, nine rebounds and four assists from Ashlyn Lesure. click for more
On Saturday afternoon at Lowell’s Tsongas Center, the Hurricanes will take aim at Division 5 State Championships in girls and boys basketball. click for more