Pittsfield Votes Down $74 Million Wastewater Upgrades

By Andy McKeeveriBerkshires Staff
Print Story | Email Story
PITTSFIELD, Mass. — The City Council rejected a $74 million capital request to renovate the wastewater treatment center late Tuesday night.
 
Shortly before midnight, the request from Mayor Linda Tyer to borrow for upgrades to the plant fell one vote short of the supermajority needed. Councilors Christopher Connell, Melissa Mazzeo, Kevin Morandi, and Donna Todd Rivers all voted down the project.
 
"I cannot move forward and vote on this, say yes, until all of the questions are answered," Mazzeo said.
 
The council only discussed it briefly at the end of Tuesday's five-hour meeting. The vote had been put off multiple times, with Connell using a charter objection two weeks earlier to thwart a vote.
 
The rejection could very likely make the city miss the next deadline as part of an administrative order issued by the U.S. Environmental Protection Agency, which has warned the city that it is prepared to impose fines for not lowering the levels of phosphorous and aluminum in the water coming out of the plant. The project proposed by the consultants, Kleinfelder, also called for a nitrogen optimization process.
 
"Further delay also will result in increased costs of the upgrades and in the ongoing discharge of higher levels of pollutant to the Housatonic River for an even longer period of time. In light of the history of this matter and the importance of the upgrades to the protection of human health and the environment, please be advised that EPA is prepared to take further enforcement as necessary to ensure compliance with the requirements of the permit should the city fail to meet its obligation to begin construction by August 1, 2018," reads the letter penned by Karen McGuire, acting director of the office of environmental stewardship.
 
The issue dates back to a 2008 National Pollutant Discharge Elimination System permit restricting the flow of contaminants into the Housatonic River. The city had fought that in court but ultimately lost. Since then, the city put forth money to design a plant that would meet specifications laid out by the EPA.
 
The design came back to the City Council early this year and the administration sought to receive the borrowing authority for construction. 
 
The City Council had many concerns over that design and debated over multiple lengthy meetings. But ultimately, not enough councilors were convinced to move forward. 
 
At this point, it isn't clear what the vote will mean. But it is likely to come back to the council in the future, in one way or the other.
 
For more information, read our prior stories on the topic below.
 
image description

Vote Delayed On Pittsfield's $74 Million Wastewater...

The administration is seeking authority to borrow the $74 million in an effort to comply with an EPA administrative order, which calls for significantly decreasing the amount of phosphorus, and aluminum treatment, released into the Housatonic River. The plan developed in consultation with Kleinfelder also calls for a nitrogen optimization process.

image description

Pittsfield Finance Panel Is No on $74M Wastewater...

The City Council's finance subcommittee is recommending that the city hold off on borrowing $74 million to make major repairs to the wastewater system.

image description

Pittsfield Council Wants More Details on $74M...

The City Council doesn't want to rush into making a $74 million decision. Mayor Linda Tyer had put forth a petition calling for the borrowing of $74 million for a massive project with the wastewater system. The city is under an administrative order from the Environmental Protection Agency holding the system to higher standards of phosphorus, aluminum treatment, and nitrogen removal. The project has been in design for about a year, coming after years of ultimately losing appeals in federal cou

image description

$74 Million Wastewater Plant Upgrades Heads to City...

The mayor is asking for the authority to borrow $74 million for a major upgrade of the city's wastewater treatment center. The expense has been a long time coming, starting with the city seeking to renew its National Pollutant Discharge Elimination System permit in 2005. The Environmental Protection Agency oversees those permits in an effort to keep waterways clean and had issued a permit in 2008 requiring significantly higher standards of phosphorus, aluminum treatment, and nitrogen removal.

 


Tags: EPA,   municipal borrowing,   wastewater,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield ZBA Member Recognized for 40 Years of Service

By Brittany PolitoiBerkshires Staff

Albert Ingegni III tells the council about how his father-in-law, former Mayor Remo Del Gallo who died at age 94 in 2020, enjoyed his many years serving the city and told Ingegni to do the same. 

PITTSFIELD, Mass. — It's not every day that a citizen is recognized for decades of service to a local board — except for Tuesday.

Albert Ingegni III was applauded for four decades of service on the Zoning Board of Appeals during City Council. Mayor Peter Marchetti presented him with a certificate of thanks for his commitment to the community.

"It's not every day that you get to stand before the City Council in honor of a Pittsfield citizen who has dedicated 40 years of his life serving on a board or commission," he said.

"As we say that, I know that there are many people that want to serve on boards and commissions and this office will take any resume that there is and evaluate each person but tonight, we're here to honor Albert Ingegni."

The honoree is currently chair of the ZBA, which handles applicants who are appealing a decision or asking for a variance.

Ingegni said he was thinking on the ride over about his late father-in-law, former Mayor Remo Del Gallo, who told him to "enjoy every moment of it because it goes really quickly."

"He was right," he said. "Thank you all."

The council accepted $18,000 from the state Department of Conservation and Recreation and a  $310,060 from the U.S. Department of Transportation's Safe Streets and Roads for All program.