image description
The auditorium remain uncompleted, forcing Mount Greylock officials to find locations for school productions.

Mount Greylock School Building Committee Presses Contractor on Auditorium

By Stephen DravisiBerkshires Staff
Print Story | Email Story
WILLIAMSTOWN, Mass. — School officials and the School Building Committee on Tuesday continued to express their frustration with the pace of completion of the Mount Greylock Regional school building project.
 
At the latest meeting of the School Building Committee, the panel pressed Turner Construction Vice President Carl Stewart III for a date when the general contractor finally will finish work on the school's auditorium.
 
"What's your best guess?" co-Chairman Mark Schiek asked Stewart point blank.
 
"I'm not going to give one," Stewart said. "Believe me, Williamstown is a nice town, but we want to be done as much as you want us to be done."
 
The middle-high school opened in September with all parts of the building, including the new three-story academic wing, open under a temporary certificate of occupancy. That TCO did not cover the auditorium, one of two public areas — along with the gymnasium — that were preserved and renovated from the original 1950 school.
 
Four months into the school year, the auditorium is still unavailable, a condition that sent the school's fall concert off campus to Williams College's Chapin Hall and forced the annual residency of Shakespeare & Company to hold rehearsals in the cafeteria.
 
"We have the spring musical coming up, and we're going to be holding auditions and rehearsals in the cafeteria," Principal Mary MacDonald told the committee. "We have a concert this January, and we have plans in place to do that in the cafeteria. We have debates each fall in the eighth grade, and we'll go back to Griffin Hall [at Williams].
 
"I haven't been able to find space at Williams for the musical in March. I don't know if I have to, but I have to make that decision now."
 
Schiek took the lead on pressing the district's case with the New York City-based multinational contractor with offices in Albany.
 
"We're affecting programming now," Schiek said in a meeting viewable on the district's YouTube site. "So we need to know when the turnover will be."
 
Stewart said the systems that need to aligned are complex and that Turner is moving as quickly as it can to get the building ready for commissioning.
 
"As an example, we put the house lighting in," Stewart said. "They're having problems programming it. The electricians needed to get back up to it, so we needed a special lift. These buildings nowadays are much more complicated than they used to be, and the commissioning process is tough."
 
Mount Greylock Superintendent Kimberley Grady told the committee the district aims to incorporate the auditorium into a full certificate of occupancy for the entire middle-high school, rather than open spaces under a series of TCOs, in part because the latter option would impact the start date for warranties on equipment. Opening everything under a full COO, when available, is in the district's best interest, she said.
 
"We're going through commissioning of systems in the auditorium," Stewart said. "As soon as those meet programmatic needs and the needs of the town [inspector], we'll turn them over to you.
 
"We know you want them, and we're working hard to get things done."
 
Grady told the SBC that, "per discussions with our [legal] counsel]," the district is holding back payments to all subcontractors on the project at the moment.
 
"We'll discuss which ones have final pay, which ones that have retainage that we can release final pay," Grady said.
 
In April, the school committee decided to retain an attorney with the Boston firm Strang, Scott, Giroux and Young to represent the district in regard to the building project.
 
Schiek ended Tuesday's discussion with a plea to the general contractor.
 
"All we can say is, 'Get it done,' " Schiek said, looking directly at Stewart. "What else can you say at this point? Get it done."
 
Another point of contention at Tuesday's hour-long meeting was a $50,940 change order, paid from Turner's contingency, to redo the entry from Cold Spring Road (Route 7) over Indigenous Peoples Day weekend in October, about a month after the school opened.
 
The committee needed to approve the expenditure, which was approved on an emergency basis to make the changes to the turn radius and the width of the two egress lanes from the campus.
 
Grady explained that the entrance was a problem for both school buses and fire trucks, noting that the Williamstown Fire Department ran tests during the night after the school opened and determined that the radius was insufficient.
 
"On a day like this with perfect conditions, they could make the turn, but as soon as we add any snow, they wouldn't," Grady said.
 
Committee member Al Terranova was perplexed by the need to make the change after the work appeared to be completed.
 
"How does this happen?" Terranova asked. "How do we not know what the radius of a turn in a driveway should be? We know how big a bus is. We know how big a fire engine is. How does this happen?"
 
Grady asked Jason Springer of architect Perkins Eastman to field Terranova's query.
 
"Coming to the project late, I had the same questions when this came up," Springer said. "It's a difference between what we planned on paper and the real world experience of the fire department coming onto the site with their vehicles. … On paper, the emergency vehicle radiuses worked.
 
"This wouldn't be the first time that something worked great on paper and not as well in practice."
 
During the vote to approve payment for redoing the entryway, Terranova paused to think about his decision before ultimately voting as part of a unanimous decision of the eight committee members present to pay the bill.

Tags: MGRHS school project,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Mount Greylock School Committee Votes Slight Increase to Proposed Assessments

By Stephen DravisiBerkshires Staff
WILLIAMSTOWN, Mass. — The Mount Greylock Regional School Committee on Thursday voted unanimously to slightly increase the assessment to the district's member towns from the figures in the draft budget presented by the administration.
 
The School Committee opted to lower the use of Mount Greylock's reserve account by $70,000 and, instead, increase by that amount the share of the fiscal year 2025 operating budget shared proportionally by Lanesborough and Williamstown taxpayers.
 
The budget prepared by the administration and presented to the School Committee at its annual public hearing on Thursday included $665,000 from the district's Excess and Deficiency account, the equivalent of a municipal free cash balance, an accrual of lower-than-anticipated expenses and higher-than-anticipated revenue in any given year.
 
That represented a 90 percent jump from the $350,000 allocated from E&D for fiscal year 2024, which ends on June 30. And, coupled with more robust use of the district's tuition revenue account (7 percent more in FY25) and School Choice revenue (3 percent more), the draw down on E&D is seen as a stopgap measure to mitigate a spike in FY25 expenses and an unsustainable budgeting strategy long term, administrators say.
 
The budget passed by the School Committee on Thursday continues to rely more heavily on reserves than in years past, but to a lesser extent than originally proposed.
 
Specifically, the budget the panel approved includes a total assessment to Williamstown of $13,775,336 (including capital and operating costs) and a total assessment to Lanesborough of $6,425,373.
 
As a percentage increase from the FY24 assessments, that translates to a 3.90 percent increase to Williamstown and a 3.38 percent increase to Lanesborough.
 
View Full Story

More Williamstown Stories