Adams, Cheshire Anticipate Paving Schedule for Ashuwillticook Trail

Staff Reports
01:46AM / Tuesday, December 03, 2019
Print | Email
ADAMS, Mass. — Officials in Adams and Cheshire are expecting an update this month on the schedule for repaving 11.2 miles of the Ashuwillticook Rail Trail.
 
The nearly 20-year-old portion of the trail runs from the Pittsfield/Lanesborough line to the Adams Visitor Center and was constructed in two phases completed in 2001 and 2004, respectively. A 1.2-mile extension that goes from Hoosac Street to Lime Street in Adams was completed in 2017 and is not part of this update. 
 
This will be the first total resurfacing of the popular bike and walking path since its initial completion. The project will be done in two phases with the first from April to July and the second immediately after and ending in October in 2020. Which half gets done in which phase is still undecided. 
 
Cheshire is hoping to be included in the first phase, Town Administrator Edmund St. John IV told the Cheshire Board of Selectmen recently. He feels starting in the summer would have a deleterious impact on the town financially.
 
"There's not really a good time to do this as it's going to have a major impact on everything. I did say to the folks at DOT ... if it's July to October it's a busy season for us because we have the lake that goes along a lot of it. A lot of users go along the lake, businesses on the lake, restaurant, Whitney's Farm. There's a lot of impact that would happen during the summer if that portion of the rail trail was closed," he said. "Obviously my concern is how this is going to affect Cheshire but there's also the realization that this is going to impact Adams as well."
 
St. John met with the the state Departments of Transportation and of Conservation and Recreation regarding the $3.4 million repaving. 
 
Selectmen Jason Levesque thought the earlier snowmelt along the trail in Cheshire might be a factor in which half gets closed for resurfacing first.
 
In Adams, Town Administrator Jay Green thinks it's likely the town will get the summer phase of the resurfacing project. 
 
"Phase two is going to come from Church Street (in Cheshire) north and end at the Visitors Center. That work, as of now, is anticipated to take place from [July to October] of 2020. That may very well change but as of right now that is what Mass DOT anticipates," he told the Adams Board of Selectmen last month. "The contract has been awarded to Maxymillian. We anticipate to schedule a meeting sometime in December and we hope to have more information at that time."
 
Funding for the project is from the Transportation Improvement Program for the Berkshire Metropolitan Planning Commission. It has been in the planning stages for about four years and is currently going through the permitting process and will be before the Adams Conservation Commission on Thursday. 

Tags: Ashuwillticook Rail Trail,   MassDOT,   paving,   

6 Comments
MORE STORIES:
| Home | A & E | Business | Community News | Dining | Real Estate | Schools | Sports & Outdoors | Berkshires Weather | Weddings |
Advertise | Recommend This Page | Help Contact Us
iBerkshires.com is owned and operated by: Boxcar Media 102 Main Street, North Adams, MA 01247 -- T. 413-663-3384 F.413-664-4251
© 2012 Boxcar Media LLC - All rights reserved

Privacy Policy| User Agreement