image description
The two-story section of the building has floors in place and is prepped for decking. Roofing work is in sight. The steel for the shop section is still being placed on the eastern portion of the site.

Superstructure of New Taconic High Nearly Complete

By Andy McKeeveriBerkshires Staff
Print Story | Email Story
PITTSFIELD, Mass. — The superstructure of the new Taconic High School is nearly completed.
 
The city will hold a topping off ceremony next Friday, a tradition in construction projects to celebrate the final beam of a structure being placed. The completion of the superstructure is pretty much on schedule, the hope was to complete it by the start of 2017. A total of 10 subcontracting companies are currently on site working on the building now.
 
The construction site is broken into multiple areas with the gymnasium and auditorium on the west side and the shop areas to the east. The western portion has been enclosed and heaters are warming the inside to allow walls and decking for the floors to be placed. The heating had just begun this week and takes a few days to bring the temperature up enough and thaw the ground. The roofing is expected to start soon as well. 
 
Meanwhile, on the eastern side workers are finalizing the steel structure and the cranes lifting the pieces into place will soon be gone. That area will be for the shops, with science classrooms up top, and require less interior work. That is expected to remain uncovered with structural and concrete work continuing.
 
Some of the precast concrete, which will be the exterior appearance, has begun with the building of elevator shafts and some pieces on the northern end of the building, providing a glimpse of the various textures being used for exterior appearance.
 
Utilities are almost in place, with a permanent gas line already there to power the heaters. The electricity is being provided by a generator but electricians are expected to have a permanent line to the site in short order as well — much of that infrastructure work is also completed. 
 
The site is coming into form. The slanted roof from the designs is clear and in place. The balcony for the auditorium is visible from the inside. The open space for the gymnasium is there and the material to build the walls are on site and workers will still be taking that on.
 
The precast concrete to enclose the structure is being poured this week and waiting to be delivered. The plan is to have the entire exterior complete by the end of 2017.
 
The $120.8 million project has been under construction for 10 months now and project leaders say overall it is on time and on budget — though typically construction projects lose some time during the winter and regain it during the spring.
 
The building is scheduled to be completed and open for the school year of 2018-2019. Then the current Taconic will be demolished and playing fields and parking lots will be constructed.
 
iBerkshires has been photographing the project since the start. Below is a slideshow of the construction progress.



Tags: Taconic school project,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Flushing of Pittsfield's Water System to Begin

PITTSFIELD, Mass. — The city of Pittsfield's Department of Public Utilities announces that phase 1 of the flushing of the city's water system will begin Monday, April 22.
 
Water mains throughout the city will be flushed, through hydrants, over the upcoming weeks to remove accumulations of pipeline corrosion products. Mains will be flushed Monday through Friday each week, except holidays, between the hours of 7:30 a.m. and 3 p.m.
 
  • The upcoming flushing for April 22 to May 3 is expected to affect the following areas:
  • Starting at the town line on Dalton Avenue working west through Coltsville including lower Crane Avenue, Meadowview neighborhood, following Cheshire Road north.
  • Hubbard Avenue and Downing Parkway.
  • Starting at the town line on East Street working west through the McIntosh and Parkside neighborhoods.
  • Elm Street neighborhoods west to the intersection of East Street.
  • Starting at the town line on Williams Street, working west including Mountain Drive,
  • Ann Drive, East New Lenox Road, and Holmes Road neighborhoods.
Although flushing may cause localized discolored water and reduced service pressure conditions in and around the immediate area of flushing, appropriate measures will be taken to ensure that proper levels of treatment and disinfections are maintained in the system at all times. If residents experience discolored water, they should let the water run for a short period to clear it prior to use.
 
If discolored water or low-pressure conditions persist, please contact the Water Department at (413) 499-9339.
 
Flushing is an important operating procedure that contributes significantly to the maintenance of the water quality in the water distribution system. 
View Full Story

More Pittsfield Stories