image description
The glass for the media center has been installed. There is just a little more work needed there.
image description
A mocked up classroom.
image description
image description
A large staircase inside of the main entrance has been started.
image description
image description
Sidewalks have been laid.
image description
image description
The electrical room.
image description
Hallway tiles.
image description
The tiles in the girl's locker room.
image description
image description
image description
The stage in the auditorium.
image description
image description
image description
image description
One of two green roofs. Eventually they will host an array of plants, which will soak up rain water.
image description
image description
image description
image description
The north parking lot was built.
image description

Taconic Construction: Progress Aided by Mild Fall

By Andy McKeeveriBerkshires Staff
Print Story | Email Story

The gym ceiling is being painted.
PITTSFIELD, Mass. — A mild autumn has helped move along outside work at the new Taconic High School.
 
As December sets in, concrete is still being poured. The mild weather has allowed workers to put sidewalks all around the school.
 
A parking lot in the north and roads in and out have all received the first layer of blacktopping. If the weather hadn't been as mild, that outside work would have waited until the spring.
 
Inside, the building is already prepared for the winter. Construction managers had a schedule calling for the building to be buttoned up in November, and heating pumped in to keep the building warm for finishing work throughout. Both of those targets have been hit.
 
By the end of October, the building was 62.8 percent complete and workers have been knocking out around 4 percent of the project per month. The work pace has been hitting the milestones on time, with an expected completion by the end of June. After that, furniture and equipment will be moved in to prepare the classrooms for the school year.
 
In October, the number of workers on site peaked at 178. Now, there are about 162 workers of all trades there. The $120.8 million project has been under construction for about a year and a half. And in many areas now, it is starting to look like a school.
 
The girl's locker room has maybe had the most noticeable change in recent months. Tiles have been placed on the wall throughout and walls have been painted. The locker room is on the second floor. Workers have started on the upper floors and moving down. The boy's locker room is a floor below and hasn't had tiling yet.
 
But on the second floor on the westernmost side of the building, tiling has been installed along the hallway walls, about three-quarters of the way up. Painters, meanwhile, are inside the classrooms putting the first few coats on.
 
The gymnasium's roof is now getting painted as well. The gym floor, however, won't be installed for a while so the wide open space is being used for storing material. 
 
The auditorium's stage has been poured. There is still work to be done near the roof, such as hanging the curtain, so the floor remains dirt and flat. Once that work toward the roof is complete, the ground will be dug down and sloped and concrete poured. The stage too will have a wood floor, which is expected to be installed this spring.
 
Workers have also begun to build a large staircase, which takes visitors from the main entrance to the media center and classrooms on the upper floors. The media center, which may be the most visually appealing part of the exterior with large pieces of glass spanning up a slanted room allowing significant natural light in, has a bit more framing work to go.
 
The easternmost side, which houses the shops on the first floor and classrooms on the upper floors, isn't as far along. But, just a few months ago the classrooms upstairs were merely framed out. Now, walls have gone up and painting has begun. 
 
The building is still being powered by generators but those will soon be replaced with the building's permanent power. 
 
iBerkshires has been following the construction since the beginning. Below is a slideshow from each visit. The slideshow is in chronological order since the start of construction.


Tags: Taconic school project,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Dalton Select Board Argues Over Sidewalk Article

By Sabrina DammsiBerkshires Staff
DALTON, Mass. — A heated discussion concerning sidewalks during Monday night's Select Board meeting resulted in the acting chair calling a recess to cool the situation. 
 
The debate stemmed from the two articles on the town meeting warrant for May 6 at 7 p.m. at Wahconah Regional High School. 
 
One proposes purchasing a sidewalk paver for $64,000 so sidewalks can be paved or repaired for less money, but they will use asphalt rather than concrete. The other would amend the town's bylaws to mandate the use of concrete for all future sidewalks. 
 
The article on concrete sidewalks was added to the warrant through a citizen petition led by resident Todd Logan. 
 
The board was determining whether to recommend the article when member John Boyle took the conversation in a new direction by addressing how the petition was brought about. 
 
"I just have a comment about this whole procedure. I'm very disappointed in the fact that you [Logan] have been working, lobbying various groups and implementing this plan and filed this petition six weeks ago. You never had any respect for the Select Board and …" Boyle said. 
 
Before Boyle could finish his statement, which was directed to Logan, who was in the audience, Chair Joe Diver called point of order via Zoom. 
 
View Full Story

More Pittsfield Stories