image description
The front of Town Hall has been covered with scaffolding as repairs continue on the roof and dormers.

Adams Selectmen Approve Additional Funds For Town Hall

By Jack GuerinoiBerkshires Staff
Print Story | Email Story
ADAMS, Mass. — The Board of Selectmen approved a $60,000 reserve fund transfer on Wednesday to address unforeseen additions to the Town Hall roof repair project.
 
Town Administrator Jay Green requested the funds to cover additional structural and masonry work atop building.
 
"With any project, once they get into it they have found other issues and concerns with the roof structure," Green said. "It is mostly structural, dormers, some of the scrapping on the gutters to hold them up as well as the four chimneys they need masonry work."
 
The roof has not been maintained since the building's original renovation into town offices. The project was bid last year but did not start until this spring. Officials did not want to start the project during the winter.  
 
Green said it will cost nearly $32,800 to make some of these critical structural repairs to the former American Legion post home. He said the additional amount would be for the chimney work, which is estimated to cost between $15,000 and 20,000. 
 
Although this work does not have to be done now, he said, it would be prudent to complete it while the scaffolding is still in place.
 
"In order to do all of that work they need the scaffolding and scaffolding has a very high mobilization cost," Green said. "It is approximately $850 a week to rent all of that."
 
Selectman Joseph Nowak said he was happy to put more money toward Town Hall but wished a more comprehensive overview of the 1907 building had been done because it was apparent that the building's issues go deeper than just the roof.
 
"When I look at the extent of this I am a lot more concerned about a lot of these other things," Nowak said. "This looks to be more of a Band-Aid approach and I think more needs to be done if we want to do this right."
 
Community Development Director Donna Cesan agreed but noted the original project only encompassed the roof and that this was from a past administration. She said she felt a more comprehensive approach would have been better.
 
She did add that she thought the company, Titan Roofing, was doing a great job.
 
"I have been very pleased with their work and their workmanship so I think we are getting our money's worth," Cesan said. "I think we are doing right by this building." 
 
The $60,000 transfer would bring the town's stabilization account down to $75,000 and although the Selectmen approved the transfer it left them unnerved
 
"That will put us below $100,000," Nowak said. "That just puts us one calamity away."
 
The Finance Committee now have to approve the transfer. 

Tags: town hall,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Greylock Glen Outdoor Center 90% Complete

By Tammy DanielsiBerkshires Staff
ADAMS, Mass. — The Greylock Glen Outdoor Center is about 90 percent finished with an anticipated completion date in August. 
 
Matthew Sturz of owner's project manager Colliers International updated the Selectmen on the project's progress via Zoom on Wednesday. 
 
"We'll work with the town to determine exactly the logistics of that," he said in response to questions about the opening. "I think that there's certainly interest in getting the facility open as soon as it can open. But we do need to conclude the construction activities ... it's not federally advisable to have construction activity going on with the public."
 
The completion will depend on getting a certificate of occupancy for the 10,000-square foot facility.
 
The  $8.3 million project is running eight months behind the expected schedule, Sturz said, largely because of permitting with the state Department of Environmental Protection that required an extensive environmental review of endangered species, working with National Grid to determine how solar will be integrated into the project, and the need for a water system for both potable water and fire suppression. 
 
"Transformers and all manner of electrical switchgear is being significantly impacted by supply chain issues throughout the construction industry," said Sturz. "So coordinating those items up front took a little bit longer than anticipated."
 
A 350,000-gallon water tank is being constructed on the grounds to provide water with completion expected by July or August. 
 
View Full Story

More Adams Stories