WILLIAMSTOWN, Mass. — Williams College is ramping up its pending construction projects with a phased approach that follows state and federal guidelines for reducing the spread of the novel coronavirus.
 
Working with the town's Board of Health, the college has implemented a new health and safety plan that will allow work by the college's contracted vendors to start in a multi-phase process that begins on Monday, according to a news release from the school on Friday afternoon.
 
"Above all, our primary objective is to keep the Williamstown community, Williams College campus community, and our job sites safe while assisting in stopping the spread of the COVID-19 virus," said Rita Coppola-Wallace, executive director of design and construction at Williams.
 
The new protocols require social distancing of 6 feet or more from other workers, stringent hygiene practices and increased hygiene facilities at the job site. Those found in violation of the protocols could be subject to removal from the campus.
 
The rules will be enforced by one of the college's new full-time COVID-19 officers, who each will be responsible for one of four zones on campus. In Phase 1, each of the zones will have between five and nine projects, including work ranging from elevator repair to doors and trim painting.
 
"Officers will certify via daily reports that all contractors and subcontractors on campus are in full compliance with the college's safety protocols and measures as well as associated local, state, and federal guidelines and directives," the news release read.
 
The plan announced on Friday does not include two of the college's higher profile projects, the unified science center and the renovation of Fort Hoosac on South Street. Those projects already resumed after a suspension in late March.
 
Those larger projects have site-specific COVID-19 compliance officers and their own safety protocols developed with the projects' construction managers.
 
As for the smaller projects, they will be phased in beginning on the first of the month for the next four months, "or until Governor Baker lifts the mandated protocols for construction workers," the college said. And the school will reduce its annual and renewal construction projects by half in order to promote safety during the pandemic.
 
""In conjunction with this plan, the implementation of shared resources will improve likelihood of compliance, reduce vendor frustration, minimize redundancy, and increase understanding of the steps necessary to minimize COVID-19 risks on active projects," Coppola-Wallace said.
 
As for the rest of Williams' operations, the college continues to have its personnel work from home as it evaluates its options for fall semester.
 
"We don't have summer classes on campus," Williams President Maud Mandel said Friday morning in a virtual town hall hosted by 1Berkshire. "We're not holding our traditional research programs and other orientation programs and things that we would have done on campus.
 
"So right now, we're in a very heavy scenario planning for the fall. We're really pursuing both options. On the one hand, we're doing all the work necessary to think about what it would be to open safely and to think about the myriad questions involved in a residential college. … And, simultaneously, we're thinking about how to build a remote educational program that we could be proud of."

Tags: COVID-19,   Williams College,   


More Coronavirus Updates

Keep up to date on the latest COVID-19 news:


If you would like to contribute information on this article, contact us at info@iberkshires.com.

Williams College Receives Anonymous $25M Gift to Support Projects

Staff Reports
WILLIAMSTOWN, Mass. — Williams College has received a $25 million gift commitment in support of three major initiatives currently underway on campus: constructing a new museum building, developing a comprehensive plan for athletics and wellbeing facilities, and endowing the All-Grant financial aid program. 
 
The donors, who wish to remain anonymous, say the gift reflects their desire to not only support Williams but also President Maud S. Mandel's strategic vision and plan for the college. 
 
"This remarkably generous commitment sustains our momentum for WCMA, will be a catalyst for financial aid, and is foundational for athletics and wellness. It will allow us to build upon areas of excellence that have long defined the college," Mandel said. "I could not be more appreciative of this extraordinary investment in Williams."
 
Of the donors' total gift, $10 million will help fund the first freestanding, purpose-built home for the Williams College Museum of Art (WCMA), a primary teaching resource for the college across all disciplines and home to more than 15,000 works. 
 
Each year, roughly 30 academic departments teach with WCMA's collection in as many as 130 different courses. 
 
The new building, designed by the internationally recognized firm SO-IL and slated to open in 2027, will provide dedicated areas for teaching and learning, greater access to the collection and space for everything from formal programs to impromptu gatherings. The college plans to fund at least $100 million of the total project cost with gifts.
 
Another $10 million will support planning for and early investments in a comprehensive approach to renewing the college's athletics and wellbeing facilities. 
 
View Full Story

More Williamstown Stories