NORTH ADAMS, Mass. — The Airport Commission received an update on a new hangar construction project that is expected to go out to bid in March.
Peter Enzien of Stantec, the airport's engineer, reported Tuesday that preliminary work is progressing on the proposed six-unit hangar project. Enzien said survey work is complete, noting the site is a simple, flat plot of land.
"It is a big, wide-open, flat area, so it did not take them long," he said.
Enzien said he is waiting on the results of some soil borings, noting that a potentially high clay composition could cause some hiccups.
"The soil here is not good; there is a lot of clay here. We are hopeful we can do a conventional foundation system," he said. "It is a fairly light building. It is just a pre-engineered metal building."
Enzien said although the design process has begun, he will be able to change plans if the soil results come back unfavorably.
The proposed 147-foot hangar, which will be funded through state and federal funds, will run along the east side of the Shamrock Hangar from east to west. Enzien noted that although the plot looks flat, some grading will still have to take place.
Stantec must submit plans to state and federal agencies by the first week of February. After addressing notes, the project can go out to bid in March. Bids will likely be opened May 1.
Enzien added that the project could include a new roof on the city-owned Shamrock Hangar. He said the roof work will be included as an alternative in the bid.
"We will see how the bids come in. If it is reasonable, the FAA might fund 95 percent of it," he said. "If they don't, MassDOT offered to pick up 80 percent of it. The airport would pick up the remaining 20 percent."
The commission also mentioned they could consider selling the Shamrock Hangar. City Councilor and Airport Commission liaison Andrew Fitch asked if it was possible to move the property if the city is not using it.
"If we have buildings that we are not using, the Shamrock Building perhaps — if we don't have plans to develop plans to use a building, maybe we consider offloading it in a constructive way," Fitch said. "Not saying that it has to be offloaded, but something to think about if we are never going to use that space."
Enzien said it is possible to sell the property, but a few steps need to take place first. Although the city owns the property, it was purchased with federal money. This means the lounge area must remain open to the public. Enzien noted the city could reimburse the federal money to clear that restriction.
"Then you could do whatever you want," he said.
The reimbursement would not be a simple exchange of cash; instead, the amount would be marked against future airport improvement grant funds, lessening the potential grant amount available for future projects.
Fitch, who continued to speak during public comment, also suggested the airport consider updating its signage.
"I don't think our sign is very impressive, exciting, or representative of the businesses here," Fitch said. "We do have a high-end arts community around here if we want to do something interesting."
He showed a picture of the Bennington Airport sign, which appeared to be made of old airplane parts. The commission agreed, and Enzien noted the current sign was repurposed from a doctor's office building.
"We thought a sign is better than no sign, and it was always meant to be temporary," he said.
Fitch suggested the commission could tap the Massachusetts Cultural Council for a potential grant.
Finally, the commission tabled a discussion on kitchen equipment donated by Williams College to support the restaurant space in the Administration Building until Commissioner James Haskins could be present. Chairman Dean Bullett said they would need to act on the donation at the next meeting, as the college is preparing to move the equipment for upcoming renovations.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
North Adams Council OKs Funds for Ashland Street Project Easements
By Tammy Daniels iBerkshires Staff
NORTH ADAMS, Mass. — The City Council on Tuesday approved an appropriation of $256,635 from the Land Sales Account for easements and takings related to the Ashland Street project.
A second roll call vote approved the easements and takings during a meeting lasting nearly three hours.
"This is a construction project that has been in the works for probably, like eight years, coming down the pipe in conjunction with MassDOT," said Mayor Jennifer Macksey. "And what we are asking tonight is permission for appropriation for us to pay for some permanent and some temporary easements to complete this work."
The mayor noted the use of "eminent domain" in the legal language but assured the council and audience that no one's home or driveway were being taken.
The temporary construction easements will terminate after six years; the permanent roadway easements will give the city rights to access those areas for purposes of repair or public construction.
The takings are the city's contribution to the $11.4 million Complete Streets project, being funded by the state Department of Transportation through the 2026 Transportation Improvement Program. The account has $463,000, leaving a balance of $207,000 after the appropriation.
The City Council on Tuesday approved an appropriation of $256,635 from the Land Sales Account for easements and takings related to the Ashland Street project. click for more
Driscoll was getting a lesson in fly fishing from Brian Gilbert of Hilltown Anglers after a speaking to outdoor recreation stakeholders at Berkshire East in Charlemont.
click for more