Taconic High School Educational Program

Tax Impacts of the Bonding

Taconic High School Today
Built in 1969, the aging building suffers from a number of issues. ...    view more
MSBA Process
The Massachusetts School Building Authority has a delineated process for research, funding and construction of public schools. Once a locally......    view more
Design
THE DESIGN   Working with the MSBA, the project is based on serving 920 students. That accounts for the 750 or so currently attending the......    view more
Auditorium
The design features a gymnasium and auditorium that will be smaller than the current ones. The current gym is much bigger than the state's......    view more
Site Plan
The front of the proposed new school is oriented south, opposite the current school, which will allow it to be built while students are still attending......    view more
First Floor
Shops and common areas would be located on the ground floor. A subcommittee was formed to inventory the current equipment and furniture and as much of......    view more
Second Floor
The clustering feature, which the School Building Needs Commission added back into the plan, is designed to create "academies." The......    view more
Third Floor
The third floor space will mirror the second floor in clustering classrooms. ...    view more
Front & Back
The building would be built around security protocols, eliminating the multiple areas of egress and funneling visitors through the main......    view more
Academics
The project is built around an educational plan the School Committee approved early in the project. McCandless said the idea is to......    view more
Future Expansion
The city was very clear a few years ago that we want two high schools. Superintendent Jason McCandless Should......    view more
Taconic High School Today
Built in 1969, the aging building suffers from a number of issues. view more
Top Stories
Ribbon Cut On New $120.8 Million Taconic High...
Taconic senior Alexandria Carmon went to numerous vocational competitions against schools throughout the state. And it made her jealous. The health technologies program at Taconic had great...   [1 Comment]
Volunteers Build Dugouts At Taconic High...
Most of those who worked on the new Taconic High School live in the area. They coach youth sports or they're volunteer firemen in their communities. As the final pieces come together - with the...   [2 Comments]
Construction Wrapping Up at New Taconic High...
For all intents and purposes, the new Taconic High School building is done. A temporary certificate of occupancy has been granted and administrative staff has been working out of the new $120.8...   [2 Comments]
Final Public Tours Of Taconic High School...
Residents will get one final chance to walk the halls of the current Taconic High School before it meets the wrecking ball. Superintendent Jason McCandless said on Saturday, June 30 and Sunday,...
Taconic Construction: Final Month Before...
In one month, a certification of occupancy will be issued and staff will be allowed into the new $120.8 million to start setting up their offices. But before then, more than 100 tradesmen remain...
Taconic Construction Hits Home Stretch, Plans...
Gilbane Construction is scheduled to finish the new Taconic High School on June 29. From there, a moving company will be contracted to bring all of the equipment being kept at the current school...
Taconic High School Construction: Fixtures and...
Tiling, fixtures, flooring, more tiling, painting, and ceilings. That's what's getting the biggest focus at the new Taconic High School building. The mechanical systems are mostly complete and...   [1 Comment]
Pittsfield Eyes Repairs To Taconic Track,...
A small working group has been getting cost estimates for every thing they'd like to do and determined to focus priority on those particular upgrades. Broken down, it is estimated that repairing the...   [3 Comments]
Taconic High Construction: Focus on Interior...
Nearly all of the mechanical and exterior work is complete and the focus at the new Taconic High School is transitioning to painting and finishing. The $120.8 new school has been under...
Taconic Principal Plotting Use, Scheduling of...
On Valentine Road more than 100 tradesmen have been on and off the site of the new Taconic getting the structure ready. And inside the current building across the road, Principal John Vosburgh has...   [1 Comment]
Taconic Construction: Progress Aided by Mild...
A mild autumn has helped move along outside work at the new Taconic High School. As December sets in, concrete is still being poured. That mild weather has allowed workers to put sidewalks all...   [1 Comment]
Taconic Contruction: 58 Percent Complete;...
Construction managers expect to complete $4 million worth of construction per month to keep on schedule with the building of the new Taconic High School.
Taconic Construction: Mechanical Systems,...
There is just one more school year left for the current Taconic High School. Across the driveway, workers have been constructing a new $120.8 million school. On a daily basis, an average of 150...

View All
9/11 Division: Holden 1,...
That means the Pittsfield Americans make their first road...
Pittsfield Nationals Hold Off...
Monday’s sectional final Pittsfield Little League National...
Simon Mele Lift Pittsfield...
Simon Mele turned Friday’s final of the Donald Gleason...
Hunt, Burris Lead Team to...
Todd Hunt and Tom Burris each scored 17 points to lead...
Wendling Pitches Pittsfield...
Chase Wendling struck out nine in a four-inning win, and...
Paronto, Roccabruna Pitch...
Paronto went 2-for-4 at the plate and scored twice, but it...
Pittsfield AL Win Pitchers...
Konnor Dugan was dominant. Cam Hillard was clutch. And the...
Williamstown in Cal Ripken...
Williamstown’s 9-and-under Cal Ripken Baseball All-Stars...
3rd Annual ‘Grill & Spill’...
More than 50 skateboarders from states all over New England...
Donald Gleason District 1...
Cam Blake hit a three-run triple in the top of the third...
Williamstown 4th of July 2019
Williamstown's Independence Day activities included a...
Pittsfield 4th of July Parade...
The annual Pittsfield Fourth of July Parade brought...
North Adams Opens Splash Park
The splash park is the centerpiece of a Noel Field...
2019 City Champs R.I. Baker
R.I. Baker won 2 of 3 games to win the 2019 NBIYB City...
Berkshire Force 12U Team Wins...
Mia Arpante struck out five and allowed just one hit to go...
2019 Berkshire County All...
The final action of the 2019 high school softball season...
9/11 Division: Holden 1,...
That means the Pittsfield Americans make their first road...
Pittsfield Nationals Hold Off...
Monday’s sectional final Pittsfield Little League National...
Simon Mele Lift Pittsfield...
Simon Mele turned Friday’s final of the Donald Gleason...
Hunt, Burris Lead Team to...
Todd Hunt and Tom Burris each scored 17 points to lead...
Wendling Pitches Pittsfield...
Chase Wendling struck out nine in a four-inning win, and...
| Home | A & E | Business | Community News | Dining | Real Estate | Schools | Sports & Outdoors | Berkshires Weather | Weddings
Advertise | Recommend This Page | Help Contact Us | Privacy Policy| User Agreement
iBerkshires.com is owned and operated by: Boxcar Media 102 Main Street, North Adams, MA 01247 -- T. 413-663-3384 F.413-664-4251
© 2000 Boxcar Media LLC - All rights reserved