Taconic High School Educational Program

Tax Impacts of the Bonding

Taconic High School Today
Built in 1969, the aging building suffers from a number of issues. ...    view more
MSBA Process
The Massachusetts School Building Authority has a delineated process for research, funding and construction of public schools. Once a locally......    view more
Design
THE DESIGN   Working with the MSBA, the project is based on serving 920 students. That accounts for the 750 or so currently attending the......    view more
Auditorium
The design features a gymnasium and auditorium that will be smaller than the current ones. The current gym is much bigger than the state's......    view more
Site Plan
The front of the proposed new school is oriented south, opposite the current school, which will allow it to be built while students are still attending......    view more
First Floor
Shops and common areas would be located on the ground floor. A subcommittee was formed to inventory the current equipment and furniture and as much of......    view more
Second Floor
The clustering feature, which the School Building Needs Commission added back into the plan, is designed to create "academies." The......    view more
Third Floor
The third floor space will mirror the second floor in clustering classrooms. ...    view more
Front & Back
The building would be built around security protocols, eliminating the multiple areas of egress and funneling visitors through the main......    view more
Academics
The project is built around an educational plan the School Committee approved early in the project. McCandless said the idea is to......    view more
Future Expansion
The city was very clear a few years ago that we want two high schools. Superintendent Jason McCandless Should......    view more
Taconic High School Today
Built in 1969, the aging building suffers from a number of issues. view more
Top Stories
Taconic Principal Plotting Use, Scheduling of...
On Valentine Road more than 100 tradesmen have been on and off the site of the new Taconic getting the structure ready. And inside the current building across the road, Principal John Vosburgh has...   [1 Comment]
Taconic Construction: Progress Aided by Mild...
A mild autumn has helped move along outside work at the new Taconic High School. As December sets in, concrete is still being poured. That mild weather has allowed workers to put sidewalks all...   [1 Comment]
Taconic Contruction: 58 Percent Complete;...
Construction managers expect to complete $4 million worth of construction per month to keep on schedule with the building of the new Taconic High School.
Taconic Construction: Mechanical Systems,...
There is just one more school year left for the current Taconic High School. Across the driveway, workers have been constructing a new $120.8 million school. On a daily basis, an average of 150...
Taconic Construction: Project On Budget
The Taconic High School construction budget is trending on target, according to Thomas Meyer of the project managers Skanska USA. Construction on the $120.8 million high school is 43 percent...
Taconic Construction: Halfway Point In Sight
Construction on the new Taconic High School is quickly approaching the halfway point. By the end of the month, the $120.8 million project should be right at the 50 percent completion mark.
Taconic Construction: Walls Going Up, Power...
The wrap around the construction site is expected to be fully removed soon. The work has ramped up in recent week with the onset of nicer weather. On Thursday there were close to 150 workers on...   [4 Comments]
Pittsfield Seeking Consistency In Financing...
PITTSFIELD, Mass. - The needed cash flow to pay to build the new Taconic High School hits a peak in the coming months. The Finance Department is closely monitoring the funding of the project,...
Taconic Construction: Exterior Precast To...
There are over 100 people on site at the building of the new Taconic High School and that is expected to ramp up even more over the coming months. Construction on the $120.8 million building has...
Final Steel Beam Placed On New Taconic High...
The $120.8 million Taconic High School construction project hit another milestone Friday when workers placed the final steel beam on the structure. In a topping off ceremony, a construction...   [3 Comments]
Superstructure of New Taconic High Nearly...
The superstructure of the new Taconic High School is nearly completed. The city will hold a topping off ceremony next Friday, a tradition in construction projects to celebrate the final beam of...
Taconic High Construction: Precast Concrete...
The first precast concrete beam for the vocational shops at the new Taconic High School was placed on Tuesday. Construction has been ongoing since March. It began with site work by J.H....
Gilbane, City Settle On 'Guaranteed Maximum...
The city and Gilbane Building Company has settled on a guaranteed maximum price for the construction of the new Taconic High School. The price for construction only is $97,757,373, which is equal...
McCandless: Contamination at Taconic Site...
The contaminated material found at Taconic High School is mostly cleaned up, according to Superintendent Jason McCandless. McCandless told the School Committee on Wednesday that about 80 percent...
Contaminated Soil Adds to Cost of Taconic High...
Getting rid of construction debris found in the soil at the site of the new Taconic high School will require construction managers to dip into contingency for the first time. John Benzinger of the...
Taconic High Building Project Site Work...
The site of the new school, directly across the driveway from the current building, is under heavy construction with equipment, material piles and dozens of workers getting the ground ready for...   [1 Comment]
Taconic High Project Site Work Starts Monday
On Monday, the Taconic High School property will start to look like a construction site. Superintendent Jason McCandless said workers from Maxymillian will begin the site work for the new high...   [4 Comments]

View All
MLK Day of Service 2018
Northern Berkshire Community Coalition held its 25th Day of...
G Basketball: Westfield vs...
Westfield at Mount Greylock 43-63. Photos by Sean Pikula
B Basketball: Lenox vs Hoosac...
Izaha Stubbs scored 18 points Thursday to lead the Hoosac...
Williams College's BioEyes
Williams College's Center for Learning in Action is again...
B Basketball: Pittsfield vs...
Toby Foehl scored 20 points, and the Mount Greylock...
Bowling: Berkshire County...
Berkshire County League bowling at Greylock Bowl & Golf on...
Skiing: Multiple teams at...
Depth was key for the Mount Greylock boys Nordic team in an...
Westfield State vs MCLA
FINAL: Westfield State University Women top MCLA Athletics...
Hockey: Mount Everett vs...
Hoby MacWhinnie scored twice and set up a goal Wednesday to...
G Basketball: Mohawk vs...
Grace Paplawski scored 16 points Tuesday to lead the Mohawk...
G Basketball: Mount Everett...
Mount Everett girls basketball coach Scott Rote was happy...
G Basketball: Taconic vs...
Aubrey Lazits scored 14 points and grabbed 15 rebounds, and...
B Basketball: Turners Falls...
The Drury boys basketball team Thursday used its high...
Skiing: Berkshire Nordic...
The Mount Greylock girls Nordic ski team opened the season...
Berkshire Holiday Tournament
Zabion Powell and Michael LaFreniere won individual titles...
G Basketball: Drury vs Hoosac...
MLK Day of Service 2018
Northern Berkshire Community Coalition held its 25th Day of...
G Basketball: Westfield vs...
Westfield at Mount Greylock 43-63. Photos by Sean Pikula
B Basketball: Lenox vs Hoosac...
Izaha Stubbs scored 18 points Thursday to lead the Hoosac...
Williams College's BioEyes
Williams College's Center for Learning in Action is again...
B Basketball: Pittsfield vs...
Toby Foehl scored 20 points, and the Mount Greylock...
| Home | A & E | Business | Community News | Dining | Real Estate | Schools | Sports & Outdoors | Berkshires Weather | Weddings
Advertise | Recommend This Page | Help Contact Us | Privacy Policy| User Agreement
iBerkshires.com is owned and operated by: Boxcar Media 102 Main Street, North Adams, MA 01247 -- T. 413-663-3384 F.413-664-4251
© 2000 Boxcar Media LLC - All rights reserved