Taconic High School Educational Program

Tax Impacts of the Bonding

Taconic High School Today
Built in 1969, the aging building suffers from a number of issues. ...    view more
MSBA Process
The Massachusetts School Building Authority has a delineated process for research, funding and construction of public schools. Once a locally......    view more
Design
THE DESIGN   Working with the MSBA, the project is based on serving 920 students. That accounts for the 750 or so currently attending the......    view more
Auditorium
The design features a gymnasium and auditorium that will be smaller than the current ones. The current gym is much bigger than the state's......    view more
Site Plan
The front of the proposed new school is oriented south, opposite the current school, which will allow it to be built while students are still attending......    view more
First Floor
Shops and common areas would be located on the ground floor. A subcommittee was formed to inventory the current equipment and furniture and as much of......    view more
Second Floor
The clustering feature, which the School Building Needs Commission added back into the plan, is designed to create "academies." The......    view more
Third Floor
The third floor space will mirror the second floor in clustering classrooms. ...    view more
Front & Back
The building would be built around security protocols, eliminating the multiple areas of egress and funneling visitors through the main......    view more
Academics
The project is built around an educational plan the School Committee approved early in the project. McCandless said the idea is to......    view more
Future Expansion
The city was very clear a few years ago that we want two high schools. Superintendent Jason McCandless Should......    view more
Taconic High School Today
Built in 1969, the aging building suffers from a number of issues. view more
Top Stories
Volunteers Build Dugouts At Taconic High...
Most of those who worked on the new Taconic High School live in the area. They coach youth sports or they're volunteer firemen in their communities. As the final pieces come together - with the...   [2 Comments]
Construction Wrapping Up at New Taconic High...
For all intents and purposes, the new Taconic High School building is done. A temporary certificate of occupancy has been granted and administrative staff has been working out of the new $120.8...   [2 Comments]
Final Public Tours Of Taconic High School...
Residents will get one final chance to walk the halls of the current Taconic High School before it meets the wrecking ball. Superintendent Jason McCandless said on Saturday, June 30 and Sunday,...
Taconic Construction: Final Month Before...
In one month, a certification of occupancy will be issued and staff will be allowed into the new $120.8 million to start setting up their offices. But before then, more than 100 tradesmen remain...
Taconic Construction Hits Home Stretch, Plans...
Gilbane Construction is scheduled to finish the new Taconic High School on June 29. From there, a moving company will be contracted to bring all of the equipment being kept at the current school...
Taconic High School Construction: Fixtures and...
Tiling, fixtures, flooring, more tiling, painting, and ceilings. That's what's getting the biggest focus at the new Taconic High School building. The mechanical systems are mostly complete and...   [1 Comment]
Pittsfield Eyes Repairs To Taconic Track,...
A small working group has been getting cost estimates for every thing they'd like to do and determined to focus priority on those particular upgrades. Broken down, it is estimated that repairing the...   [3 Comments]
Taconic High Construction: Focus on Interior...
Nearly all of the mechanical and exterior work is complete and the focus at the new Taconic High School is transitioning to painting and finishing. The $120.8 new school has been under...
Taconic Principal Plotting Use, Scheduling of...
On Valentine Road more than 100 tradesmen have been on and off the site of the new Taconic getting the structure ready. And inside the current building across the road, Principal John Vosburgh has...   [1 Comment]
Taconic Construction: Progress Aided by Mild...
A mild autumn has helped move along outside work at the new Taconic High School. As December sets in, concrete is still being poured. That mild weather has allowed workers to put sidewalks all...   [1 Comment]
Taconic Contruction: 58 Percent Complete;...
Construction managers expect to complete $4 million worth of construction per month to keep on schedule with the building of the new Taconic High School.
Taconic Construction: Mechanical Systems,...
There is just one more school year left for the current Taconic High School. Across the driveway, workers have been constructing a new $120.8 million school. On a daily basis, an average of 150...
Taconic Construction: Project On Budget
The Taconic High School construction budget is trending on target, according to Thomas Meyer of the project managers Skanska USA. Construction on the $120.8 million high school is 43 percent...
Taconic Construction: Halfway Point In Sight
Construction on the new Taconic High School is quickly approaching the halfway point. By the end of the month, the $120.8 million project should be right at the 50 percent completion mark.
Taconic Construction: Walls Going Up, Power...
The wrap around the construction site is expected to be fully removed soon. The work has ramped up in recent week with the onset of nicer weather. On Thursday there were close to 150 workers on...   [4 Comments]
Pittsfield Seeking Consistency In Financing...
PITTSFIELD, Mass. - The needed cash flow to pay to build the new Taconic High School hits a peak in the coming months. The Finance Department is closely monitoring the funding of the project,...
Taconic Construction: Exterior Precast To...
There are over 100 people on site at the building of the new Taconic High School and that is expected to ramp up even more over the coming months. Construction on the $120.8 million building has...
Final Steel Beam Placed On New Taconic High...
The $120.8 million Taconic High School construction project hit another milestone Friday when workers placed the final steel beam on the structure. In a topping off ceremony, a construction...   [3 Comments]
Superstructure of New Taconic High Nearly...
The superstructure of the new Taconic High School is nearly completed. The city will hold a topping off ceremony next Friday, a tradition in construction projects to celebrate the final beam of...
Taconic High Construction: Precast Concrete...
The first precast concrete beam for the vocational shops at the new Taconic High School was placed on Tuesday. Construction has been ongoing since March. It began with site work by J.H....

View All
Volleyball: Pittsfield vs...
The Pittsfield volleyball team Thursday won the first city...
Walk A Mile In Her Shoes 2018
Hundreds of men put on their best high heels and wedges to...
B Soccer: Wahconah vs Hoosac...
Huban scores twice as Wahconah boys defeat Hoosac Valley...
Golf: Monument Mountain vs...
The Monument Mountain golf team used a complete team effort...
Football: Palmer vs McCann...
McCann Tech win over Palmer 21-7
Football: Taconic vs Wahconah
Tim Clayton threw for 169 yards and three touchdowns, and...
BSoccer: P.V.C.S. vs McCann...
Cam Belmer scored six goals Thursday to lead the Pioneer...
Football: E. Longmeadow vs...
E. Longmeadow win over Pittsfield 27-6 Friday night at BCC.
Volleyball: Mount Greylock vs...
Geyer, who chose to use only seniors in the third set,...
G Soccer: Science and...
The Blue Devils got four goals from Jacqueline Moulton en...
Volleyball: Taconic vs...
The Wahconah volleyball team Monday rallied from 1-0 and...
Football: Mount Greylock vs...
The Hoosac Valley football team came from behind and edged...
Golf: Westfield Tech vs...
McCann Tech's top four players each scored 51 or below...
Golf: Mount Greylock vs...
Derek Alibozek Friday got off to a fast start and avoided a...
Football: Easthampton vs...
Taconic tops Easthampton 74-0 on Friday night at BCC.
B Soccer: Hoosac Valley vs...
The Drury boys soccer team started the season off with a...
Volleyball: Pittsfield vs...
The Pittsfield volleyball team Thursday won the first city...
Walk A Mile In Her Shoes 2018
Hundreds of men put on their best high heels and wedges to...
B Soccer: Wahconah vs Hoosac...
Huban scores twice as Wahconah boys defeat Hoosac Valley...
Golf: Monument Mountain vs...
The Monument Mountain golf team used a complete team effort...
Football: Palmer vs McCann...
McCann Tech win over Palmer 21-7
| Home | A & E | Business | Community News | Dining | Real Estate | Schools | Sports & Outdoors | Berkshires Weather | Weddings
Advertise | Recommend This Page | Help Contact Us | Privacy Policy| User Agreement
iBerkshires.com is owned and operated by: Boxcar Media 102 Main Street, North Adams, MA 01247 -- T. 413-663-3384 F.413-664-4251
© 2000 Boxcar Media LLC - All rights reserved