Second-floor view of under-construction NARH elevator tower
North Adams – A North Adams Regional Hospital multi-phase makeover is progressing on schedule and a modernized critical care unit and new lobby area could be open by year’s end.
“We expect the critical care unit to be open by the end of the year,†said NARH Community Relations Director Paul Hopkins during a May 4 interview and site tour. The entire project may be completed during August 2006.
Critical Changes
“The critical care unit is independent of other project components. The unit will stay in approximately the same area but will be three times the size it is today,†Hopkins said.
The completed unit will cover the full length of the hospital’s northern wing and plans include glass-fronted private patient rooms all within sight of a nurse’s station, a family waiting space and a private consultation room.
Patients are receiving care in rooms near the construction site and their comfort is a top priority, Hopkins said. Officials and employees of the project’s architectural firm DiGiorgio Associates Inc. and general contractor Monitor Builders Inc. are well-versed with hospital projects, he said.
“They understand that a hospital operates 24 hours day,†he said, and noted that work was suspended on at least two occasions to accommodate surgeries.
Weekly meetings with housekeeping department staff, infection control personnel, and information technology employees maintain communication about each construction step and employee strategies. “These meetings are important,†Hopkins said. “For example, we keep housekeeping informed about the next steps so that they can keep the construction where it should be.â€
An interior ceiling-to-floor wall was erected to protect patients and hospital staff from much of the construction dust and noise, and specially-designed adhesive mats are scattered along the construction area. Dust from the workers’ boots adheres to the mats; as one travels from just beyond the work zone to a door leading away from the site, the blue-hued mats show a consistent decrease in tracked dust particles. Ventilation tubing is in place as well.
If lobby construction continues unimpeded, the area could open in September, Hopkins said. Structural steel is in place and concrete slab work is expected to begin next week. Overhead arched enclosures are being erected and construction of an elevator tower is underway. The elevator will serve all hospital levels except the basement. The lobby is expected to host a new gift shop as well.Privacy and Comfort for Patients
Surgical unit construction plans include a 10,200-square-foot addition that will host a full range of services at one location. Once completed, the unit will house four state-of-the-art operating rooms, private recovery rooms, an update family waiting area, and chapel space.
“Surgical services is more than doubling its space,†Hopkins said. “Everything is centralized. Everything will happen here, no more being wheeled through hallways. This will be much more private and comfortable.â€
Maternity unit construction is expected to begin once the surgical unit is completed, he said. The unit size will increase by about 3,500-square-feet and new features include five private rooms and two two-bed semi-private rooms. Whirlpool tubs and private bathrooms will deliver added comfort to maternity unit guests, Hopkins said. “This area will feel more like a hotel than a hospital."
An Emergency Department overhaul is expected to result in 17 private examination rooms, inclusion of an x-ray suite equipped with digital x-ray technology, and “telemedicine†stroke services between hospital doctors and Massachusetts General Hospital neurologists.
Bigger and Better
Overall, the project will add about 19,000-square-feet to the hospital front and include about 30,000-square-feet of interior renovations.
“With the renovations, the whole hospital is about 170,000-square-feet and about 50,000 square feet of that will be new,†Hopkins said.
Some improvements are already in use. A new magnetic resonance imaging machine is serving patients and doctors and new floors and wall-coverings were recently installed at the hospital dining room.
The about $23 million project is being funded in part by a $12 million CARE Campaign revenue effort. A private solicitation raised about $10 million toward the construction; a public appeal is now underway to raise $2 million that will establish a NARH endowment fund, Hopkins said. About $13 million of the construction costs are being funded via bonds issued by the hospital last fall.
Fiscal Foresight and Tough Choices
Hopkins said he is optimistic that news of recent administrative-level hospital job cuts will not adversely affect the public fundraising effort. The job cuts were necessary because of an ever-evolving health care services delivery system. Hospitals are providing less in-patient care and many more out-patient services, including day surgeries, MRI exams, and endoscopy procedures, and resources must be shifted accordingly, he said. Hospitals across the country are facing very tight financial constraints and are struggling to remain viable while implementing necessary changes. The NARH construction project was designed to modernize and improve the hospital and the care delivered; ironically, job cuts reflect the need for fiscal foresight as the facility moves into the future of healthcare.
“We must show fiscal responsibility at administrative levels and beyond,†Hopkins said. “Where we have the opportunity to eliminate jobs, we have to do it. We have to be as careful as we can. Our hope is that the community will see that our staffing changes are meant to be fiscally responsible.â€
Susan Bush may be reached at 802-823-9367 or by e-mail at suebush123@adelphia.net.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Lanesborough Town Meeting to Vote Budget, Bylaws & Vehicle Purchases
By Breanna SteeleiBerkshires Staff
LANESBOROUGH, Mass. — Tuesday's annual town meeting includes a $14 million operating budget, new short-term rentals, accessory dwelling units and sign bylaws, and free cash article appropriations.
Voters will gather at Lanesborough Elementary School on June 9 at 6 p.m. to decide on 20 warrant articles.
The fiscal 2027 budget is up a little over 10 percent. Some of the main increases are the Mount Greylock Regional School District and McCann Technical School: the McCann assessment is up more than 30 percent based on factors including enrollment and the school renovation project, and Mount Greylock's is up 11 percent.
Article 11 is for the town to vote to approve from free cash the sum of $16,298.48 for the McCann Technical School roof and window replacement project so as not to impact the budget. Article 3 is appropriate $7,586,284 for Mount Greylock Regional School assessment.
Another notable increase was in life and health insurance, showing an increase of about 26 percent.
Ambulance Director Jen Weber is planning 24-hour coverage, which means more staff and a hike in her budget. One of the articles asks the town to appropriate $234,100 to operate the Ambulance Enterprise Fund for salaries and expenses.
Many town departments are looking for new vehicles. The Fire Department is looking to replace its outdated 1996 fire engine. There are two articles related to the truck at a total of $813,366. Article 12 would transfer $225,000 from free cash into the Fire Truck Stabilization Fund; Article 13 would transfer $605,000 from the fund and authorize the borrowing of $208,366.08.
The total includes a $100,000 contingency cost to cover any additional costs if a 2026 model-year chassis cannot be secured before new emissions standards go into effect in 2027.
The board at its last meeting moved the $225,000 transfer to come before the borrowing article, changing the stabilization number. If the $225,000 is not voted on, then they will amend the next article's number on the floor, subtracting the $225,000. This shows the borrowing number significantly lower.
Article 17 asks for the transfer of $80,000 from free cash to replace a police cruiser.
Police Chief Rob Derksen's aim is to replace one vehicle every other year, meaning the oldest vehicle gets replaced about every 10 years.
He stressed that if delayed this year, the town may have to double up in a future year to get back on schedule, and that paying later usually costs more. The article will ask for $80,000 from free cash, the vehicles used to be funded by the BHRD.
Lastly, the Highway Department is looking to replace a 2014 International dump truck that will be a total of $330,000 and will take two to three years to receive.
Money will be used from last year's approval of $250,000 from free cash for the replacement of a 2012 highway front-end loader that was underspent $49,261. Town meeting is being asked to approve a transfer of $53,274.85 from free cash and the use of $227,464 from funds from the Sale of Town Real Estate to fund the balance.
Other free cash proposals include $1,200 to purchase software to support tracking and ongoing maintenance schedules of town-owned vehicles; $42,000 for the replacement of the Highway Department's storage shed roof, $200,000 to reduce the tax levy.
Cassidy Flynn scattered five hits in a complete-game effort in the circle as Lenox upset top-seeded Hoosac Valley, 3-2, in the quarter-finals of the Division 5 State Tournament. click for more
Brayden Durant struck out seven and walked one in a complete-game effort on the mound Saturday to pitch the Drury baseball team to a 6-0 win over Keefe Tech in the quarter-finals of the Division 5 State Tournament at Joe Wolfe Field. click for more
Jason Codey struck out 13, walked two and allowed just an infield single as the Generals earned a 7-1 win over Wahconah to claim their third straight regional title. click for more
Gracelyn Wright struck out eight, and Genevieve Lagess went 3-for-5 with four runs batted in as the Hurricanes beat Monson, 17-3, to claim their first Western Mass title in four years. click for more
For the boys, Ward Bianchi helped lead the way with a win in the shot put and a second place in the javelin as the Mounties finished 16 points ahead of runner-up Pittsfield (pending the results of the pole vault, which were unavailable at 11 p.m. Friday night). click for more