image description
The Planning Board signed off on a site design for the Conte School project that includes removing the stairs on the west side.
image description
Sniezek points to the new entrance and dropoff points for buses and parents.

Planning Board Signs Off on Conte School Plans

By Tammy DanielsiBerkshires Staff
Print Story | Email Story
Julie Sniezek of Guntlow & Associates explains the site plan for the Conte School project at Monday's Planning Board meeting.

NORTH ADAMS, Mass. — The Planning Board on Monday gave the OK for the proposed site plan for the $30 million Conte School project that includes taking out the stairs in Colegrove Park.

But their removal isn't a done deal yet.

The Historical Commission has asked the city solicitor to weigh in the project, specifically if state funds for the school project can be used at Colegrove if it is no longer an essential part of the school.

The area, once the front entrance to the former Drury High School, had been envisioned as a play area for Conte once it was reconfigured into an elementary school. But that option was rejected because of cost concerns and reluctance of teachers to use the area because of time constraints.

Justyna Carlson, chairman of the Historical Commission, said she wanted City Solicitor John DeRosa's opinion before making a decision. The commission is also concerned that the the state Historical Commission has approved a plan endorsed by the local commission last year that has significantly changed.

"As it stands right now, the first meeting we had a motion that we could not approve until we had further information," Carlson said.

Mayor Richard Alcombright said he expected a decision from DeRosa next week and believes the findings will support the park as being considered part of the whole school project. After the meeting, he said it didn't make much sense to put effort into improving the school and leave deteriorating stairs in front of it.

He did agree that making the park accessible to the school is not a priority since fewer students walk to school, the hill will be used less and the west door won't be an access point. The new entrance to the school will be on the south side.

Retaining Wall Could Hold Up Conte School Costs

North Adams Panel Wants Opinion on Park Alteration

North Adams Board Prioritizes Cuts for School Project

"We were hoping to be able to make Colgrove Park accessible to everybody," said Julie Sniezek of Guntlow & Associates, but the ramp leading from the southwest side of the building to the park is "very far from ADA standards." A new ramp would require handrails and a zig-zag pattern to decrease the incline.

Sniezek said the most affordable option would be to take out the two sets of upper stairs and level the area, while leaving the paved circular area, ramp, wall and vegetation in place. The lower stairs, which are in very bad shape, would also be removed.


"We are not able to financially repair these stairs at this time ... we're working with the Historic Commission at the local and state levels to come up with a balance that is acceptable to both parties," Sniezek said.

In answer to a question, from the audience, Sniezek said the stairs would be completely different aesthetically because they would require being brought up to current code. She did not have a cost figure, although the consultants have said the project is close to the 8 percent of construction costs allowed by the state for site work.

One necessary fix is the retaining wall on the southwest corner of the property, which Sniezek said is in "dangerous condition."

That cost for repairing or replacing the wall has been estimated from $500,000 to as much $700,000, which might lead to cuts in other aspects of the project.

Owner's project manager Mel Overmoyer of Strategic Building Solutions expects to keep the budget on track.

"We have the budget from the MSBA that we're sticking to and that will remain the budget throughout the course of the project," Overmoyer said. "There will be no change in cost."

Kristian Whitsett of Margo Jones Architects said the goal is to "preserve the historic character as much as possible" of the century-old school. He said the most evident change will be the new, energy-efficient double windows.

Whitsett said the project is nearing the end of its design and development phase.

Planner Wayne Wilkinson asked about a wall to the east of the school that appeared to have loose stone; Sneizek said engineers had determined it was safe and needed only minor repairs.

The planners approved the site plan unanimously.


Tags: Conte School,   historical commission,   Planning Board,   school project,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Greylock School Project Moves Into Construction; Geothermal System Approved

By Tammy Daniels iBerkshires Staff
NORTH ADAMS, Mass. — The $65 million Greylock School Project has moved into construction phase, where it will stay for the next 18 months or so. 
 
Work has already started, as abatement of asbestos and lead paint at the old school are underway and trees and playground equipment removed for site preparation by general contractor Fontaine Bros.
 
"They hit the ground running," Jesse Saylor of TSKP Studio told the School Building Committee on Tuesday. "Fontaine's doing a nice job looking ahead and forecasting and ... we expect to get their schedule upcoming, as well as their breakdown of schedule of values, which is important because the [Massachusetts School Building Authority] reimburses the city based on that."
 
Timothy Alix of Collier's International, the owner's project manager, said the school construction will come in about $51 million and change.
 
"Our total budget is $65.3 million. We've processed invoices for roughly $4.4 million of that, we believe that roughly $4.2 [million] would be eligible for reimbursement, and then, based on the city's reimbursement rate, we expect a reimbursement of $3.4 [million]," Alix said. "It's right where we expected. Again, the biggest number here will be this construction line item, and we'll start seeing some invoices coming in as Fontaine builds out their schedule of values."
 
Saylor offered a presentation on the differences between vertical and horizontal geothermal systems, with the committee finally committing to horizontal. The savings are estimated at about $225,000; the project is expected to receive about $2.4 million in federal funds toward the alternative energy option. 
 
Committee members had been wary of the use of geothermal, which is being pushed by the state, but felt better after Tuesday's overview and voted unanimously to go with a horizontal system under the parking lot. 
 
View Full Story

More North Adams Stories