National Grid Meets With Local Officials Over Power Outages

By Tammy DanielsiBerkshires Staff
Print Story | Email Story
Steps Taken by National Grid

• Retained a consultant to analyze lightning protection
• Investigating the quality and stability of all breakers
• Evaluating the infrastructure at the Adams facility, most specifically as it relates to downtime
• Replaced a large transformer
• Control center upgrades are being put in place that are designed to reduce downtime
• Looking at ways to improve communication at the inception of, and throughout, an interruption

Above, a transformer at the Adams substation at the power outage on July 8. Several power interruptions have occurred over the last few months, raising concerns from public officials. Some 18,000 people were out of power during two of the events and schools were closed because of a transformer fire in May.

NORTH ADAMS, Mass. — Mayor Richard Alcombright said he was reassured about the area's electrical service after a meeting this week with National Grid officials.

"They understand that we weren't happy," he said Wednesday. "I think the overall tenor is she reassured us they were aware of our concerns."

The meeting with Marcy Reed, president of National Grid in Massachusetts, came after several power outages that affected large parts of North County.

The transformer fire at the Adams substation in May was followed by incidents two days in a row July.

Alcombright said Williamstown Town Manager Peter Fohlin, Adams Town Administrator Jonathan Butler, Florida Town Administrator Christine Dobbert, public safety officials and representatives from Massachusetts College of Liberal Arts met with Reed and her senior staff.


"There seemed to be some sense in the community that the Adams substation was outdated and old," said Alcombright, but National Grid officials said their equipment was as good as any in the state.

"We constantly invest in our infrastructure to offer customers the safest, most reliable electric service possible," said Reed in a statement. "National Grid knows communities depend on the power we provide, and we take outages like these very seriously: We've repaired and replaced equipment in our Adams substation and our system is now operating normally."

The utility was continuing to test the equipment and breakers at the substation, the group was told.

The mayor said local officials thought the National Grid team as "extremely accessible and responsive."

There was more listening than talking, he said, adding that the having the regional president there demonstrated North County's concerns were being addressed.

"We don't live in a perfect world and we understand that," he said.

Equipment Failure Knocks Out Power to North County
NORTH ADAMS - 07-09-2014 - The power came back a lot quicker on Wednesday. Navarro said a separate equipment failure required switching over to a...
Transformer Fire Knocks Out Power Again in North...
NORTH COUNTY - 07-08-2014 - Power was lost around 11:30 a.m. Tuesday and then came on again around 1:30 only to go back out a few minutes later.
Power Outage Disrupts North Berkshire, Closes Schools
ADAMS - 05-09-2014 - A National Grid transformer station caught fire behind the Holland Co. in Adams.

 


Tags: National Grid,   power outage,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

North Adams Winter Parking Ban in Effect

Staff reportsiBerkshires
NORTH ADAMS, Mass. — The weather's been nice so far this fall but the winds of winter are ahead. And North Adams is getting ready. 
 
The fall decorations have been pulled from Main Street, the Christmas trees are installed, and the annual overnight parking ban has gone into effect.
 
As of Sunday, Nov. 1, overnight parking on city streets is prohibited between the hours of 1 and 6 a.m. This is to allow plows to clear the streets during snowstorms. 
 
"We understand that residents may need time to make alternative parking arrangements," said Mayor Jennifer Macksey in a city alert. "Therefore, we will provide a brief grace period during the first few weeks of November. During this time, vehicles parked overnight will receive courtesy reminders rather than tickets."
 
But don't wait too long to find alternative parking: Ticket enforcement is anticipated to begin in mid-November.
 
But, if the city gets snow or conditions requiring plowing and sanding, enforcement could start earlier.
 
"Our goal is to give residents adequate time to adjust while ensuring our streets remain safe and accessible for everyone," said the mayor.
 
View Full Story

More North Adams Stories