Pittsfield Prepping For New School Costs Estimates

By Andy McKeeveriBerkshires Staff
Print Story | Email Story
Paul Kneedler says the city should expect to pay a third of the estimated $118 million to build a new school.
PITTSFIELD, Mass.  — Architects say within a few months the city will know how much it will have to pay to build a new school.
 
Ballpark figures puts the cost to taxpayers somewhere in the $40 million range with the state picking up the tab for about 80 million.
 
Paul Kneedler, a consultant with Skanska, the firm working on the project, told the School Building Commission on Monday that state will pay about two-thirds of the total cost.
 
That number is more accurate than the previously estimated 80 percent reimbursement for the $118 million proposal because there are a number of things the state won't cover.
 
"You are probably looking at 64 to 67, 68 percent," of the total cost, Kneedler told the commissioners.
 
For example, the city will have to pay to remove the asbestos floor tiles, will need to do utility work on Valentine Road and will need attorneys and permitting — all of which will receive no reimbursement from the state.
 
Further work on the site but not in the building is capped at 8 percent, with the city footing the remainder. 
 
"I don't know if there is a job in Massachusetts that hasn't gone over that 8 percent," Kneedler said.
 
And, the state also caps its reimbursement at $287 per square foot. Taconic's current plans are estimated to cost $372 per square foot.
 
Kneedler said Plymouth South High School is in the phase of signing contracts for the work and of the $107 million project, taxpayers are expected to take on some $60 million. That town started with a 53 percent reimbursement rate but only 80 percent of the costs were eligible for it.
 
"In reality, they are getting an effective reimbursement rate of 42.9 percent when you compare it to the total project cost," he said. 
 
The town of Haverhill matches closer to Pittsfield, though, with a similar starting reimbursement rate of 79 percent. Eighty-two percent of that project was eligible for reimbursement, leaving the town to pay about 45 percent of the total cost.
 
Kneedler said once the schematic design phase is completed, the Massachusetts School Building Authority will look through all aspects to determine what it will and will not pay for. From there, the city and the state will have to reach agreements on contracts.
 
According to Carl Franceschi of Drummey Rosane Anderson architects, the firms are hoping to have a scope of work and budget by spring 2015. Then the firm will spend a year detailing the specifications for a 2016 bid. Eventually the building will be constructed in 2016 and 2017 for an opening in later summer of 2018.
 
"We can still meet the original schedule," Franceschi said.
 
The commissioners had hoped to move to the next step in the process already but had to delay for two months because the state hadn't responded to their first filings. Fransceschi said the firm received comments on its submission of an educational plan and a space program and, with Mayor Daniel Bianchi and Superintendent Jason McCandless, traveled to Boston last week to answer questions the MSBA had.
 
"MSBA wants to make sure we get the program down before we jump into designing the building," Franceschi said of the educational plan.
 
The MSBA wanted more clarification on those two aspects because the comprehensive high school plan isn't a replication of what is currently happening at the school, Franceschi said, and includes more flexibility.
 
The MSBA reduced the size of the proposed building by 5,000 square feet — a reduction in one classroom, a science lab and shrinking the size of a couple other rooms. That dropped to estimated cost to $118 million.

Tags: new business,   MSBA,   school building,   school building committee,   Taconic High,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

15 People Displaced in Pittsfield Home Fires

Staff Reports

PITTSFIELD, Mass. — Fifteen people were displaced after 2-alarm home fires this weekend on Springside Avenue and Elaine Drive. 

On Friday evening, the Fire Department responded to a structure fire at 209 Springside Ave., which took a four-hour battle to extinguish and resulted in a partial roof collapse. The next day, on Saturday evening, crews knocked down a fire at 121 Elaine Drive in about an hour. 

The garage and part of the single-family home on Elaine Drive were gutted to the frame, along with a vehicle parked in the driveway. On Springside Avenue, the top level and porch of the multifamily were burned through.  

A GoFundMe has been started for the family of the Elaine Drive home, which includes several young children.  The fundraiser, with a $5,500 goal, explains they lost their home and all of their belongings. (iBerkshires.com does not confirm or endorse fundraisers; they are provided as information only.)

There were no civilian or firefighter injuries, and both incidents are under investigation.  One dog was rescued on Springside Avenue. 

On Oct. 10, around 6:15 p.m., PFD responded to the Springside Avenue home for a reported structure fire and saw a 2 1/2-story wood frame multifamily with a heavy blaze showing from the second-floor front porch, extending out. 

The building suffered a partial roof collapse, which prolonged extinguishment. The fire was brought under control after about four hours.

“An aggressive offensive attack was mounted by first arriving crews stretching hose lines into the building as well as primary searches that proved negative. Ladders were placed around the structure to provide access as well as escape if needed. An off-duty Fire Captain had also been on scene early in the incident to help evacuate the structure and rescue a dog,” PFD wrote in a press release. 

View Full Story

More Pittsfield Stories