Pittsfield Prepping For New School Costs Estimates

By Andy McKeeveriBerkshires Staff
Print Story | Email Story
Paul Kneedler says the city should expect to pay a third of the estimated $118 million to build a new school.
PITTSFIELD, Mass.  — Architects say within a few months the city will know how much it will have to pay to build a new school.
 
Ballpark figures puts the cost to taxpayers somewhere in the $40 million range with the state picking up the tab for about 80 million.
 
Paul Kneedler, a consultant with Skanska, the firm working on the project, told the School Building Commission on Monday that state will pay about two-thirds of the total cost.
 
That number is more accurate than the previously estimated 80 percent reimbursement for the $118 million proposal because there are a number of things the state won't cover.
 
"You are probably looking at 64 to 67, 68 percent," of the total cost, Kneedler told the commissioners.
 
For example, the city will have to pay to remove the asbestos floor tiles, will need to do utility work on Valentine Road and will need attorneys and permitting — all of which will receive no reimbursement from the state.
 
Further work on the site but not in the building is capped at 8 percent, with the city footing the remainder. 
 
"I don't know if there is a job in Massachusetts that hasn't gone over that 8 percent," Kneedler said.
 
And, the state also caps its reimbursement at $287 per square foot. Taconic's current plans are estimated to cost $372 per square foot.
 
Kneedler said Plymouth South High School is in the phase of signing contracts for the work and of the $107 million project, taxpayers are expected to take on some $60 million. That town started with a 53 percent reimbursement rate but only 80 percent of the costs were eligible for it.
 
"In reality, they are getting an effective reimbursement rate of 42.9 percent when you compare it to the total project cost," he said. 
 
The town of Haverhill matches closer to Pittsfield, though, with a similar starting reimbursement rate of 79 percent. Eighty-two percent of that project was eligible for reimbursement, leaving the town to pay about 45 percent of the total cost.
 
Kneedler said once the schematic design phase is completed, the Massachusetts School Building Authority will look through all aspects to determine what it will and will not pay for. From there, the city and the state will have to reach agreements on contracts.
 
According to Carl Franceschi of Drummey Rosane Anderson architects, the firms are hoping to have a scope of work and budget by spring 2015. Then the firm will spend a year detailing the specifications for a 2016 bid. Eventually the building will be constructed in 2016 and 2017 for an opening in later summer of 2018.
 
"We can still meet the original schedule," Franceschi said.
 
The commissioners had hoped to move to the next step in the process already but had to delay for two months because the state hadn't responded to their first filings. Fransceschi said the firm received comments on its submission of an educational plan and a space program and, with Mayor Daniel Bianchi and Superintendent Jason McCandless, traveled to Boston last week to answer questions the MSBA had.
 
"MSBA wants to make sure we get the program down before we jump into designing the building," Franceschi said of the educational plan.
 
The MSBA wanted more clarification on those two aspects because the comprehensive high school plan isn't a replication of what is currently happening at the school, Franceschi said, and includes more flexibility.
 
The MSBA reduced the size of the proposed building by 5,000 square feet — a reduction in one classroom, a science lab and shrinking the size of a couple other rooms. That dropped to estimated cost to $118 million.

Tags: new business,   MSBA,   school building,   school building committee,   Taconic High,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

PEDA Site 9 Preparation, Member Retirement

By Breanna SteeleiBerkshires Staff

PITTSFIELD, Mass. — The redevelopment of Site 9 for mixed-use in the William Stanley Business Park is set to take off. 

Edward Weagle, principal geologist at Roux Associates, gave an update on the yearlong work to the Pittsfield Economic Development Authority last week.

"It's been a real pleasure for me to work on a project like this," he said. "This is kind of like a project of a career of a lifetime for me, and I'm very pleased to see that we're just at the finish line right now. My understanding is that all the documents are in front of the commissioner, waiting for her to sign off."

Mill Town Capital is planning to develop a mixed-use building that includes housing on the site. Roux, headquartered in Islandia, N.Y., was hired assist with obtaining grant financing, regulatory permitting, and regulatory approvals to aid in preparing the 16.5-acre site for redevelopment. Approximately 25,000 cubic yards of concrete slabs, foundations, and pavements were removed from the former GE site. 

Once the documents are signed off, PEDA can begin the work of transferring 4.7 acres to Mill Town. Weagle said the closing on this project will make it easier to work on the other parcels and that he's looking forward to working on Sites 7 and 8.

PEDA received a $500,000 Site Readiness Program grant last year from MassDevelopment for Sites 7 and Site 8. The approximately 3-acre sites are across Woodlawn Avenue from Site 9 and border Kellogg Street. 

In other news, the state Department of Transportation has rented the east side of the parking lot for CDL (Commercial Driver's License) training. This is an annual lease that began in September and will bring in $37,200 in revenue.

Lastly, the meeting concluded with congratulations to Maurice "Mick" Callahan Jr. on his retirement.

Callahan is a former chair and a founding member of PEDA, dating back to when the board was established in the 1990s. He has also served on a number of civic and community boards and has volunteered for many organizations in the Berkshires. He is the president of M. Callahan Inc. 

"The one thing that's been a common denominator back is that you've always put others before yourself. You've served others well. You've been a mentor to two generations of Denmarks, and I'm sure many generations of other families and people within this city," said board Chair Jonathan Denmark. "We can never say thank you enough, but thank you for your services, for the creation of this board, your service to the city of Pittsfield, and to all the communities that you've represented and enjoy retirement." 

"It wasn't always easy to be in the position that you were in Mick, but you handled it with so much grace, always respecting this community, bringing pride to our community," member Linda Clairmont said. "I could not have accomplished many of the things I did, especially here for this business part, without you all of the Economic Development discussions that we had really informed my thinking, and I'm so grateful."

Callahan left the team with a message as this was his final meeting, but said he is always reachable if needed.

"I also have to say that a lot of great people sat around this table and other tables before the current board, and the time that I had with Pam [Green] and Mike [Filpi] sticking around, the leadership of this mayor [board member Linda Tyer], and it really, it was always great synergy," he said.

"So don't be afraid to embrace change. And you know, you got a business model. It's been around long time. Shake it up. Take a good look at it, figure out where it needs to go, and you're lucky to have leadership that you have here."

View Full Story

More Pittsfield Stories