image description
The Airport Commission was updated about the progress of multiple ongoing improvement projects.

North Adams Hangar Project To Be Extended

By Jack GuerinoiBerkshires Staff
Print Story | Email Story
NORTH ADAMS, Mass. — The Shamrock Hangar renovation project, although moving along, will be completed later than expected.
 
Peter Enzien of Stantec, the engineering firm overseeing the airport improvement projects, told the Airport Commission Tuesday that instead of completing the Shamrock Hangar by December 4, as agreed upon, the project will be pushed out towards the end of the month.
 
"They are hoping by the end of this week to have the windows in and do some of the electrical work," Enzien said.
 
"The ultimate goal here is to get the space wrapped up by Christmas to a point where there may be a few miscellaneous things that need to be addressed but the space is mostly complete."
 
The city purchased the hangar this summer and through Non-Primary Entitlement Funds from the Federal Aviation Authority, the city is renovating the space.
 
Enzien said the project is being held up by materials that have not yet arrived such as the windows. He said much of the plumbing is complete and the interior walls have been framed.
 
Enzien said while removing old sheetrock, they found that a portion of the lower wall was rotting but they were able to correct the issue.
 
"The bottom portion of the wall was rotted right out about 8 inches from the floor so water coming in from the outside over the years had caused a lot of the wood to rot," he said. 
 
Enzien said although the hangar is anticipated to be largely complete by Christmas, the hangar door installation will likely be complete sometime in the early new year because the contractor must work in tandem with the door manufacturers. 
 
Chairman Jeff Naughton asked that the contractor submit an official request for an extension.
 
Enzien said not much work has been done on the administrative building project, which is also planned to be renovated, however, the gate improvements are mostly complete.
 
Enzien said gate eight and gate ten have been motorized and although both gates seem to be functioning, there is a slight issue with the remote-control operation of gate ten. The remote should be able to operate within a 500-foot radius of the gate.
 
"They don’t know if it is the plantings that are causing a line of sight issue, but I spoke with Berkshire Fence and they are looking at other options," he said. "Hopefully in the next week or so we will have a solution and then we can close out the project." 

Tags: airport commission,   harriman west,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

North Adams Airport Commissioners Get Update on Hangar Project

By Jack GuerinoiBerkshires Staff
NORTH ADAMS, Mass. — The Airport Commission received an update on a new hangar construction project that is expected to go out to bid in March.
 
Peter Enzien of Stantec, the airport's engineer, reported Tuesday that preliminary work is progressing on the proposed six-unit hangar project. Enzien said survey work is complete, noting the site is a simple, flat plot of land.
 
"It is a big, wide-open, flat area, so it did not take them long," he said.
 
Enzien said he is waiting on the results of some soil borings, noting that a potentially high clay composition could cause some hiccups.
 
"The soil here is not good; there is a lot of clay here. We are hopeful we can do a conventional foundation system," he said. "It is a fairly light building. It is just a pre-engineered metal building."
 
Enzien said although the design process has begun, he will be able to change plans if the soil results come back unfavorably.
 
The proposed 147-foot hangar, which will be funded through state and federal funds, will run along the east side of the Shamrock Hangar from east to west. Enzien noted that although the plot looks flat, some grading will still have to take place.
 
View Full Story

More North Adams Stories