NORTH ADAMS, Mass. — The Shamrock Hangar renovation project, although moving along, will be completed later than expected.
Peter Enzien of Stantec, the engineering firm overseeing the airport improvement projects, told the Airport Commission Tuesday that instead of completing the Shamrock Hangar by December 4, as agreed upon, the project will be pushed out towards the end of the month.
"They are hoping by the end of this week to have the windows in and do some of the electrical work," Enzien said.
"The ultimate goal here is to get the space wrapped up by Christmas to a point where there may be a few miscellaneous things that need to be addressed but the space is mostly complete."
The city purchased the hangar this summer and through Non-Primary Entitlement Funds from the Federal Aviation Authority, the city is renovating the space.
Enzien said the project is being held up by materials that have not yet arrived such as the windows. He said much of the plumbing is complete and the interior walls have been framed.
Enzien said while removing old sheetrock, they found that a portion of the lower wall was rotting but they were able to correct the issue.
"The bottom portion of the wall was rotted right out about 8 inches from the floor so water coming in from the outside over the years had caused a lot of the wood to rot," he said.
Enzien said although the hangar is anticipated to be largely complete by Christmas, the hangar door installation will likely be complete sometime in the early new year because the contractor must work in tandem with the door manufacturers.
Chairman Jeff Naughton asked that the contractor submit an official request for an extension.
Enzien said not much work has been done on the administrative building project, which is also planned to be renovated, however, the gate improvements are mostly complete.
Enzien said gate eight and gate ten have been motorized and although both gates seem to be functioning, there is a slight issue with the remote-control operation of gate ten. The remote should be able to operate within a 500-foot radius of the gate.
"They don’t know if it is the plantings that are causing a line of sight issue, but I spoke with Berkshire Fence and they are looking at other options," he said. "Hopefully in the next week or so we will have a solution and then we can close out the project."
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
North Adams Airport Commissioners Get Update on Hangar Project
By Jack GuerinoiBerkshires Staff
NORTH ADAMS, Mass. — The Airport Commission received an update on a new hangar construction project that is expected to go out to bid in March.
Peter Enzien of Stantec, the airport's engineer, reported Tuesday that preliminary work is progressing on the proposed six-unit hangar project. Enzien said survey work is complete, noting the site is a simple, flat plot of land.
"It is a big, wide-open, flat area, so it did not take them long," he said.
Enzien said he is waiting on the results of some soil borings, noting that a potentially high clay composition could cause some hiccups.
"The soil here is not good; there is a lot of clay here. We are hopeful we can do a conventional foundation system," he said. "It is a fairly light building. It is just a pre-engineered metal building."
Enzien said although the design process has begun, he will be able to change plans if the soil results come back unfavorably.
The proposed 147-foot hangar, which will be funded through state and federal funds, will run along the east side of the Shamrock Hangar from east to west. Enzien noted that although the plot looks flat, some grading will still have to take place.
The nonprofit organization on Tuesday celebrated its more than 60 volunteers who spent more than 8,500 hours last year feeding the community.
click for more
The college's search firm WittKieffer has already received 14 completed applications with another 15 expressing interest, said Trustees President Buffy Lord, and had more than 80 responses in the five days since the posting went up.
click for more
Wendy Penner can be found pretty much everywhere: leading local initiatives to address climate change and sustainability, championing public health approaches for substance abuse, and motivating citizens to defend their rights and the rights of others. click for more
Pupils at Brayton Elementary got to taste test a new side dish as chef Kyle Zegel passed out cups cider-glazed carrots on Friday for the children to try. click for more
Clarksburg's partners in the North Berkshire School Union agreed to take a look at the assessment structure for the union's administration and the union agreement. click for more