PITTSFIELD, Mass. — The airport is expected to be shut down for 85 days this spring for the reconstruction of the main runway.
The City Council's Finance Subcommittee voted affirmatively on the borrowing to repave both of the airport's runways. The total project will cost $6.9 million, which is 95 percent paid for by the Federal Aviation Administration. The city's cost will be $349,735.
"We are required to authorize the entire project amount and that is reduced by any grants that come in to support the project," Director of Finance Matthew Kerwood said.
Airport Commission Chairman Tom Sakshaug said the airport will be completely shut down on April 30. The main runway will be paved. The smaller runway will be done right after and will be shut down for an additional 55 days.
Sakshaug said the Airport Commission had a number of possibilities but ultimately decided to do the paving all at once.
The project has been a long time coming. At one point it had been included in the massive airport extension project but got pulled from that scope. In fiscal 2016, the City Council approved $3.5 million for the paving. But, then prices were estimated to come in higher. In fiscal 2017, the City Council authorized another $2.6 million.
"It was clear that the original $3.5 [million] plus the $2.6 [million] were not enough," Kerwood said.
Kerwood said since then the engineering has been completed and the bids for construction came in at $6.9 million and the two authorizations were at $6.1 million. The subcommittee approved combining both of those authorizations and then increasing the total.
The finance director added that in the future, administrators will wait until having a final price with the FAA before asking for an authorization — thus avoiding revisiting the authorization multiple times.
Meanwhile, the airport is also set to host two solar arrays. With Oak Leaf Energy Partners, the committee agreed to a 30-year lease, 20 in the initial term and followed by two five-year extensions. The agreement would bring between of $3.1 million and $6.8 million to the airport in lease payments and $6.5 million to the city for tax payments.
Consultant Beth Greenblatt said the agreement is in place, but the actual total will depend on when the state approves the tax incentives. Greenblatt said the state's Solar Massachusetts Renewable Target program — which replaced the SREX tax incentives — is based more on timing that it is revenue. She said there are various blocks.
Once a block is filled up, the next block provides lower incentives. Greenblatt has agreements in place with Oak Leaf for three different blocks, depending on where it falls in the program.
"It is less of a technical issue but more of a timing issue to when the project qualifies under the smart program," Greenblatt said.
Assessor Paula King said, "We're not really estimating. We are just giving you the different scenarios ... these are hard numbers but it depends on what block we enter into."
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Zebra Mussels Found in Pittsfield's Onota Lake
By Brittany PolitoiBerkshires Staff
PITTSFIELD, Mass. — The city will treat one acre of Onota Lake for zebra mussels.
On Wednesday, during a special virtual meeting, the Conservation Commission approved a series of three treatments with EarthTec QZ. During dive monitoring in August, a live adult zebra mussel was found near the boat ramp.
Parks, Open Space, and Natural Resources Manager James McGrath said it will begin in the next 7-10 days, and that this treatment is nearly identical to that in the fall of 2024, as approved by the ConCom and other entities.
EarthTec QZ, an EPA-registered liquid molluscicide, will be applied to a 1-acre section from a boat with GPS guidance, about 14 days apart. There will be signs and notices of treatments to alert the public.
Karen Murray, of the Lake Onota Preservation Association, explained that the area is from the rocky point north of the boat launch to the boat launch, and a little south of the fishing pier.
"Again, does that mean we have live zebra mussels? We don't know, but it's pretty strong evidence of a potential problem," she said.
Pittsfield and LOPA embarked on an early detection process at Onota Lake in the fall of 2023; the state Department of Conservation and Recreation had found the area near the boat launch positive for zebra mussel eDNA.
On Wednesday, during a special virtual meeting, the Conservation Commission approved a series of three treatments with EarthTec QZ. During dive monitoring in August, a live adult zebra mussel was found near the boat ramp.
click for more
Independent congressional candidate Nadia Milleron says she has found a formula to address the financial pressures leaving many Americans struggling to pay their bills. click for more
The unveiling on Thursday, marks the close of Let It Shine's 2026 outdoor public art season and the third year of its emerging artist program, said Mill Town Foundation Program Director Andy Wrba.
click for more