MassDOT Secretary Stephanie Pollack said the state prefers projects that not just replace failing infrastructure, but serve meaningful roles in the community.
LANESBOROUGH, Mass. — Some 150 households in the Narragansett Avenue neighborhood depend on one single bridge to get in and out. It's their only access.
And as they commute over it, often they're slowing down and veering lanes to avoid the anglers who have plopped down a chair in the lane.
The narrow road didn't have much for parking, and that is where many with kayaks and canoes would park to get into Pontoosuc Lake.
Anyone who was walking or bicycling had to share what was left of the roadway.
As of next year, all of that will be taken fixed. Workers are able halfway through what turned into a four-year project to replace the Narragansett Avenue causeway bridge. Last summer, a temporary bridge was installed and this summer Maxymillian is building the new one.
"It is approximately a $7 million project. It is supposed to be finished by November of 2019. But that includes ripping out the old bridge. So hopefully, we can open the new one. This, as early as next summer, will be a totally functional bridge and then they take the temporary bridge out," Town Manager Paul Sieloff said.
Sieloff said the bridge was in poor condition but there was no way for the town to handle the construction costs itself. The state Department of Transportation took responsibility for the entire project. On Tuesday, MassDOT Secretary Stephanie Pollack stopped by the see the progress firsthand.
"This is one of the billions of dollars of projects the Baker-Polito administration is doing across the state. What we always look for are transportation projects that are important for the roads and bridges, but also important for the communities," Pollack said. "Here we have a situation, we had a very old bridge in tough shape, there are 150 houses on the other side where if anything happened to the bridge they'd really be isolated, and we also had an opportunity to widen out the bridge.
"We know people like to fish off the bridge. We know there is a lot more biking activity."
The new bridge will sit on an arch, replacing what was two pipes underneath the bridge. It will feature a sidewalk and a bicycle lane. The town is gearing up for another project once the bridge is completed to build four to six parking spaces right next to the popular fishing spot.
"A lot of people going fishing here. They'd bring chairs and be in the middle of the road. You had to be really careful. Now there is a place people can come and sit. There is a sidewalk. It is going to be safe for everybody," said Mass DOT District 1 Director Francesca Hemming.
That the bridge sat on pipes gave Pollack a bit of a chuckle, but it isn't the oddest bridge she's seen in Western Massachusetts.
"You have bridges that are much more interesting. This one was built on pipes. Last year, I saw one that was built on trees by the Conservation Corps in the 1930s. In eastern Mass, they are more standardized," Pollack said.
The process to get a shovel in the ground was a challenge. The town needed to secure some 18 different easements from property owners who owned property MassDOT needed either access to or to permanently take land. The town paid out some $50,000 to reach those agreements. And there, there was a secondary challenge, five pieces of land around the bridge were in protected by Article 97, which places a restriction for conservation and requires a two-thirds vote of the Legislature to remove it.
Then state Rep. Gailanne Cariddi tried to usher that bill through. But, time was short as the legislative session was coming to an end. Ultimately, there was a legal question from the secretary of state's office about it being "navigable water" and it needed approval from that office. That ultimately led to the bill not making it to a vote before the end of the session. It was carried over into 2017, when Cariddi re-filed it months before she died.
Meanwhile, MassDOT had enough to award the bid and build the temporary bridge. That piece of legislation sat on Beacon Hill for a period of time without a representative pushing it along. Construction managers on site Tuesday said the work hadn't gone perfectly smooth either but the project remains on schedule for reopening next year.
Pollack said Article 97 restrictions are something MassDOT runs into often. The restriction is in the state's constitution, so there is little MassDOT can do to avoid the legal requirements. But, Pollack said the department's permitting staff is able to help towns navigate that process.
"We don't have a lot of ability to change the rules. One of the things we are able to do as a state agency is that we have full-time permitting staff. We were able to devote some of that staff to get through the Article 97 process. We have to do it a lot whereas a community, it might be once every few years, or they haven't done it before," Pollack said. "We can't change the processes but we can help with the processes."
The bridge isn't terribly large but the replacement poses a significant financial challenge to the town.
"It is a challenge because we only get about $225,000 in Chapter 90 and you're looking at millions of dollars. We have to look for a special appropriation from the state or federal money to get these bridge projects done because they are so large and expensive," Sieloff said.
Pollack said that was something she heard since her first day as secretary. And she said MassDOT has placed a priority on repairing the state's bridges.
"Previously we were focused on our bridges but one of the things that I heard from the very first time I became secretary and came out to the Berkshires was that some of these town-owned bridges are a real problem, in bad shape, and the communities didn't have the resources to tackle them by themselves," she said.
The entire project is still on schedule to be completed next November.
Lanesborough particularly has been making progress on many of its small bridges. Both the Minor Road Bridge and the Putnam Street bridge had been replaced in the last few years. Those were after repairs to the Bridge Street bridge. Sieloff said a number of culverts in town were also replaced.
Sieloff said the town just recently added bridges to the 10-year capital plan. But finding the money to pay for the actual work is challenging.
"Thankfully they are paying for the entire construction cost, there is no hit on the town at all, which would have been catastrophic financially," Sieloff said.
In recent years the state has recognized the need and created a small bridge program, which is a pool of money specifically eyed for small bridges and culverts. That is on top of projects like the Narragansett Avenue bridge. Instead of MassDOT taking over the construction completely, that program provides towns with money to repair their own bridges through a competitive grant process.
"We are trying to invest more in those assets and get our bridges in better shape," Pollack said.
Pollack said she is also looking into ways to make the permitting, design, and construction quicker. Particularly in small towns, many have asked to have essentially "off the shelf" bridge designs. Oftentimes the towns are asked to design a bridge before MassDOT releases construction money. That has posed a challenge for some because engineering costs add up.
Pollack has heard that suggestion too but said crafting such designs is easier said than done. But, she hopes to find some ways to make it easier.
"We have talked about trying to standardize it more but it turns out to be harder than you think because every place is a little bit different. But it is something we will take a look at because the more we can streamline the money we have to put into engineering and design, the more we can put the money into more projects. And ultimately, that's what people want," Pollack said.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Bull Hill Road Well in Lanesborough Moves Forward
By Breanna SteeleiBerkshires Staff
LANESBOROUGH, Mass. — The Planning Board heard a proposal from the Village Fire and Water District about a proposed drinking-water supply well at 40 Bull Hill Road.
Officials with the village and with project developers Tighe and Bond gave the project description at the Planning Board's meeting on Monday.
Since 2020, the district has relied on the Minor Road Well, which they said is lacking a redundant water supply source. The Bull Hill Road project will establish a second groundwater source to meet current and future water demands, according to their site plan review application.
The district had previously discontinued its Bridge Street well because of PFAS contamination. Perfluoroalkyl and polyfluoroalkyl substances are a wide variety of chemicals used in consumer products. Exposure to sufficiently elevated levels may cause developmental effects in infants, impact certain organ functions and the immune system, elevate cancer risk, and cause other health effects.
The project well on Bull Hill Road will be on property the district acquired some time ago. It became a prospect for development around five years ago after the state ordered the district to abandon the Bridge Street well.
The project is on about 1.45 acres of land and will be a source of drinking water for about 2,400 residents.
"There's been a variety of testing completed, as well as a larger well has been drilled at the site, and the larger well, in hopes, would become the production well, as again, the redundant water supply, that's all been permitted so far and tested in accordance with MassDEP drinking water program regulations, and all of the tests came back astonishingly positive," said Joseph Popielarczyk, senior project manager and water/wastewater leader at Tighe and Bond. "So there's lots of water down there, and the water quality is great."
Construction is tentatively expected sometime in 2027 or 2028. He said generator procurement could affect the schedule, with lead times estimated at 40 to 52 weeks. They noted the facility could be built and tested before the backup generator arrived.
The project team described remaining permits and approvals, including MassDEP review and an anticipated Conservation Commission order of conditions. They also said funding was in place, while the timeline remained partly dependent on state review.
Resident Barbara Davis-Hassan asked whether nearby septic systems could threaten the well and whether sewer connections might be possible.
Popielarczyk said the properties were outside the required source water protection's 400-foot Zone One area, and said there is no worry of contamination from nearby septic systems.
Hassan also asked about what the noise level would be. Popielarczyk said that there will be a generator for the well and that it would be outdoors in an enclosure that will minimize sound and would run mainly for periodic testing or during a power outage.
Gabe Thomas carded an even par round of 71 at Stockbridge Golf Club Monday to finish two shots clear of the field and claim the first county individual championship for the McCann Tech golf team. click for more
The Select Board has named longtime Easthampton official John Mason as the new town administrator after interviewing him and one other candidate on Tuesday. click for more
The Cooperative Hoosac Valley football program will resume football related activities on Monday, Sept. 28, after being on “pause” for the past nine days. click for more
Hoosac Valley High School has postponed this weekend’s football games following a reported alleged hazing incident involving a large number of football players, the athletic director announced Friday afternoon. click for more
Cassidy Flynn scattered five hits in a complete-game effort in the circle as Lenox upset top-seeded Hoosac Valley, 3-2, in the quarter-finals of the Division 5 State Tournament. click for more
Brayden Durant struck out seven and walked one in a complete-game effort on the mound Saturday to pitch the Drury baseball team to a 6-0 win over Keefe Tech in the quarter-finals of the Division 5 State Tournament at Joe Wolfe Field. click for more