More than 600 Participate in Steel Rail Races

iBerkshires.com SportsPrint Story | Email Story
PITTSFIELD, Mass. -- Matthew Ferraro was the first runner across the finish line at the MountainOne Steel Rail Marathon.
 
Ferraro clocked a time of 2 hours, 41 minutes flat on the Ashuwilticook Rail Trail course.
 
He finished a little more than five minutes ahead of runner-up Nick Reid (2:46:15).
 
Simone Veale won the race's women's division in a time of 3:18:42. She beat out Jill Hussain, who covered the course in 3:27:23.
 
The fastest marathoner on Sunday was Stephen Gulley, a hand cyclist, who clocked a time of 2:15:03.
 
The 26.2-mile circuit was covered by 150 finishers ranging in age from 18 (William Hanley in 14th place) to 72 (Ric Nudell, who finished in 6:04:47).
 
The day also featured a half-marathon and an 8-kilometer race.
 
Mark Rabasco won the half-marathon in 1:18:41, edging Vincent Gauthier (1:22:38).
 
Kat Morrissey placed third overall in 1:23:43 and first among women in the half-marathon, which had 213 finishers.
 
Abigail Chaloux was the fastest woman in the 8K, crossing the finish line in 35:52, six seconds ahead of Caroline Kessler; the two women were ninth and 10th, respectively, overall in a field of 171 finishers.
 
Peter Hale had the fastest 8K time, 27:42. Erik Kessler was second in 30:32.
 
More than 600 people registered for Sunday's races, a record for the Berkshire Running Foundation event. Runners from 24 different states signed up to run.
If you would like to contribute information on this article, contact us at info@iberkshires.com.

Flooding Leads Pittsfield ConCom to Bel Air Dam Deconstruction Site

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — The Bel Air Dam project team toured the site on Monday with the Conservation Commission to review conditions following a flooding incident

Work has been on hold for two weeks after melting snow and a release of water from Pontoosuc Lake led to water overtopping of the almost 200-year-old, abandoned dam. The project team says deconstruction is still on track to end in December. 

"They have plenty of time to finish the work, so they don't expect that they're going to need extra time, but we're all waiting," reported Robert Lowell, the Department of Conservation and Recreation's deputy chief engineer. 

"… it's unfortunate, but the high-water conditions in the spring, we did have in the contract that the site might flood, so there was supposed to be a contingency for it, and we're now dealing with the complications of that." 

DCR's Office of Dam Safety is leading the $20 million removal of the classified "high hazard" dam, funded by American Rescue Plan Act dollars. It has been an area of concern for more than a decade. 

The dam on Pontoosuc Brook dates to 1832 and was used for nearly a hundred years to power a long-gone woolen mill. It's being targeted for removal, using American Rescue Plan Act funds, because the stacked stone structure poses a significant danger to homes and businesses downstream. Excavation of sediment began last fall by contractor SumCo Eco-Contracting of Wakefield. 

Earlier this month, community members noticed flooding at the site bordering Wahconah Street; water levels were down by the next week. Conservation commissioners called for the site visit with concerns about the effects of the water release and how it is being remedied.  

The group got a look at the large project area near the dam and asked questions. Chair James Conant explained that community members wanted to know the cause of the flooding. 

Jane Winn, former executive director of the Berkshire Environmental Action Team, said this was specifically brought up at the Conservation Commission hearing to ensure this sort of thing didn't happen. 

View Full Story

More Pittsfield Stories