James Scalise presented the plans to the Community Development Board on Tuesday. Cafua will now go in front of the City Council to seek approval.

PITTSFIELD, Mass. — The Community Development Board will not support a proposed Dunkin' Donuts drive-through on Fenn Street.

Cafua Management Co. was denied a positive recommendation from the board on Tuesday after presenting a site plan.

Engineer James Scalise of SK Design presented the plans to tear down the former Plunkett School and replace it with a Dunkin' Donuts franchise and retail space.

However, board members were concerned with traffic and how a drive-through would fit into the city's master plan, which calls for a "walkable" downtown and preservation of historic buildings.

The vote was 3-1 in favor of providing no recommendation — member Alf Barbalunga abstained and member David Hathaway recused himself prior to the discussion.

"I think there is nothing I'd like to see less than a drive-through at that corner," said board member Judith Katz, who was the lone vote against having "no recommendation" because she instead wanted to recommend with strict conditions.

Cafua will now have to go in front of the City Council in hopes to get approval for a special permit. The council can vote in favor of giving the company the special permit without a positive recommendation from the Community Development Board.

Traffic was the biggest concern, but Scalise said two studies and an analysis dating since April 2012 have shown there would be little impact. The drive-through would allow for a backup of 13 vehicles on the property — well above the typical six cars, he said. The business expects to bring a peak of 129 more cars to the area each day.

Other Dunkin' Donuts in the city have backups of 10 cars at their max, Scalise said, and being a new store, waiting times for orders would be decreased thus moving cars in and out quicker.

"We believe this project will lead to an improvement of traffic conditions," he told the board, citing that a loading dock that currently forces tractor-trailers to poke out onto Fenn Street would be eliminated and that drivers will be able to see the intersection and traffic lights better.
 

Related stories:

Former Pittsfield School Fate Still Uncertain

Board Upholds Demoliton Delay for Old Plunkett School

The proposed project would replace the already operating First Street Dunkin' Donuts, which had a long history of causing traffic complaints. That situation cannot be considered by the board when rendering a decision on this proposal though.

While picking through the study, board members felt that a drive-through on Fenn would cause too much congestion at an already busy intersection.

Board member Floriana Fitzgerald pointed to wait times of just short of 30 seconds to take a left in some occasions and worried that drivers would get impatient and thus cause delays.



"I am concerned about the real-life situation of an individual sitting in the car waiting to get out," she said, asking how long would it take for a driver to just drive out and force his or her way into the driving lane.

But Traffic Engineer Paul Furgal said the wait times are consistent with similar projects. Scalise added that both the Fire Department and city engineer have reviewed the plans and had no concerns. The plan would utilize existing curb cuts.

Other than traffic, Scalise said the plan improves water run off by creating more green space — thus reducing impervious surfaces — will feature lighting and sign work consistent with the landscape of the newly renovated Common, would tie water and wastewater into the city's infrastructure but with "significantly" less usage than the current building and would confine trash removal a fenced-in rear corner.

Greg Nolan, of Cafua, said the company has its own landscaping and snow removal contracts so the site would be well maintained.

Overall, the plan would "extend the use of the Common" because pedestrians would walk down to the retail shop and restaurant, the proponents said.

"It is a dead zone now," Scalise said.

Board member Sheila Irvin, however, noted that the city's master plan calls for a de-emphasis on "auto-centric" developments. "This is part of our downtown and our master plan calls for walkability and less vehicles," she said.

Attorney Thomas Hamel, representing Cafua, however, contended that the Fenn Street site is on a major thoroughfare and outside of the downtown "neighborhoods."

Additionally, attorney David Rich, also representing Cafua, said the board members shouldn't be considering the historic aspect of  because that is handled by another committee. Board member Louis Costi responded that the city has lost so many historic building that they have, too.

The Historic Commission has twice delayed demolition permits citing the building's 103-year history.


Tags: demolition,   drive-through,   Dunkin Donuts,   fast-food,   historical building,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Flooding Leads Pittsfield ConCom to Bel Air Dam Deconstruction Site

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — The Bel Air Dam project team toured the site on Monday with the Conservation Commission to review conditions following a flooding incident

Work has been on hold for two weeks after melting snow and a release of water from Pontoosuc Lake led to water overtopping of the almost 200-year-old, abandoned dam. The project team says deconstruction is still on track to end in December. 

"They have plenty of time to finish the work, so they don't expect that they're going to need extra time, but we're all waiting," reported Robert Lowell, the Department of Conservation and Recreation's deputy chief engineer. 

"… it's unfortunate, but the high-water conditions in the spring, we did have in the contract that the site might flood, so there was supposed to be a contingency for it, and we're now dealing with the complications of that." 

DCR's Office of Dam Safety is leading the $20 million removal of the classified "high hazard" dam, funded by American Rescue Plan Act dollars. It has been an area of concern for more than a decade. 

The dam on Pontoosuc Brook dates to 1832 and was used for nearly a hundred years to power a long-gone woolen mill. It's being targeted for removal, using American Rescue Plan Act funds, because the stacked stone structure poses a significant danger to homes and businesses downstream. Excavation of sediment began last fall by contractor SumCo Eco-Contracting of Wakefield. 

Earlier this month, community members noticed flooding at the site bordering Wahconah Street; water levels were down by the next week. Conservation commissioners called for the site visit with concerns about the effects of the water release and how it is being remedied.  

The group got a look at the large project area near the dam and asked questions. Chair James Conant explained that community members wanted to know the cause of the flooding. 

Jane Winn, former executive director of the Berkshire Environmental Action Team, said this was specifically brought up at the Conservation Commission hearing to ensure this sort of thing didn't happen. 

View Full Story

More Pittsfield Stories