image description

Pittsfield Commission Refuses Support For Yola Esther Project

By Joe DurwiniBerkshires Correspondent
Print Story | Email Story

PITTSFIELD, Mass. — The Commission on Disabilities voted Thursday to deny a variance sought by the Yola Esther Development, expressing frustration about the lack of compliance seen in the controversial development project that includes Giovina, Kara and Karen drives.

The state's Architectural Access Board (AAB), which must approve the variance for curb cuts sought by Yola Esther, has asked for the local commission's input in the form of a written letter either expressing support or lack of support.

"Since they've disregarded our input from the beginning, I'm of the opinion that we should not support the variance," stated commission Chairwoman June Hailer.

Hailer, along with City Engineer Matthew Billeter, had previously raised concerns about the project's compliance with agreed upon terms in October, speaking in opposition of the return of a bond credit to the developers, which was nonetheless approved by the city's Community Development Board.

According to them, the project has completely failed to meet federal ADA requirements, and overall upgrades to the three streets off Williams and Leona will cost as much as $200,000 to the city if they ultimately were to become accepted city streets.

"This situation is particularly egregious," said Billeter. "We were ignored. Since then, we've been bullied by the developer. I'm not going to be bullied."

Billeter on Thursday expressed disappointment in the Community Development Board's 7-1 vote to approve the letter of credit despite the recommendation of his office. "Politics gets involved and sometimes the right thing doesn't get done."

If this variance is approved, the city will be "left with basically useless sidewalks," Billeter added, "It's hard to walk on them, let alone navigate a wheelchair."

"I don't like the attitude [from them]," offered Commissioner Pat Sheely.

Hailer said there will also issues with the variance paperwork not being submitted on time. "They're not meeting required deadlines ... there's a whole bunch of stuff going on here."

The commission voted unanimously for a motion to send a letter stating it is not in support of the request to the AAB, which will make the final determination on this issue.


Tags: ADA,   commission on disabilities,   housing development,   sidewalks,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Flooding Leads Pittsfield ConCom to Bel Air Dam Deconstruction Site

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — The Bel Air Dam project team toured the site on Monday with the Conservation Commission to review conditions following a flooding incident

Work has been on hold for two weeks after melting snow and a release of water from Pontoosuc Lake led to water overtopping of the almost 200-year-old, abandoned dam. The project team says deconstruction is still on track to end in December. 

"They have plenty of time to finish the work, so they don't expect that they're going to need extra time, but we're all waiting," reported Robert Lowell, the Department of Conservation and Recreation's deputy chief engineer. 

"… it's unfortunate, but the high-water conditions in the spring, we did have in the contract that the site might flood, so there was supposed to be a contingency for it, and we're now dealing with the complications of that." 

DCR's Office of Dam Safety is leading the $20 million removal of the classified "high hazard" dam, funded by American Rescue Plan Act dollars. It has been an area of concern for more than a decade. 

The dam on Pontoosuc Brook dates to 1832 and was used for nearly a hundred years to power a long-gone woolen mill. It's being targeted for removal, using American Rescue Plan Act funds, because the stacked stone structure poses a significant danger to homes and businesses downstream. Excavation of sediment began last fall by contractor SumCo Eco-Contracting of Wakefield. 

Earlier this month, community members noticed flooding at the site bordering Wahconah Street; water levels were down by the next week. Conservation commissioners called for the site visit with concerns about the effects of the water release and how it is being remedied.  

The group got a look at the large project area near the dam and asked questions. Chair James Conant explained that community members wanted to know the cause of the flooding. 

Jane Winn, former executive director of the Berkshire Environmental Action Team, said this was specifically brought up at the Conservation Commission hearing to ensure this sort of thing didn't happen. 

View Full Story

More Pittsfield Stories