image description
A diagram used to explain the new phasing plan. Area C, the last area planned for completion, is depicted in blue.

Mount Greylock Confident of Keeping Timeline, Planning for the Worst

By Stephen DravisiBerkshires Staff
Print Story | Email Story

Turner Construction's Mike Giso addresses the Mount Greylock Transition Committee and School Building Committee on Tuesday.
 
WILLIAMSTOWN, Mass. — The construction manager for the $64 million addition/renovation project at Mount Greylock Regional School expressed confidence Tuesday that the building will be ready in time for the start of the 2018-19 academic year.
 
The elected and appointed residents who serve as committee members in the district still want to start planning ahead for what happens if it is not.
 
Mike Giso of Turner Construction addressed a joint meeting of the school district's Transition Committee and the Mount Greylock School Building Committee to explain the revised phasing plan for the building project.
 
As discussed by the School Building Committee this winter, that plan changed from the original target of moving classes into a three-story academic wing over the upcoming April vacation. The new timeline has all operations moving into the new and renovated spaces this summer.
 
But it is an admittedly tight timeline.
 
As laid out Tuesday by Giso, the last section of the building slated for completion is what is being called Area C, the new school's central core that ties together the academic wing, cafeteria and renovated spaces like the auditorium and gym and which includes the new library.
 
That space, at the center of the new school, is scheduled to be finished "early August," Giso said.
 
Everything else, except for the school's renovated auditorium, should be wrapped up by the end of July. The auditorium likely will be the last element to be completed because it backs up on the 1960 school building that is slated to be abated and demolished immediately after the conclusion of the current academic year.
 
"We have a high level of confidence," Giso said of the building's availability for the start of school this fall. "The fact that we're finishing a lot of these areas months before we have to have the certificate of occupancy in hand obviously helps with that … even though you could suggest we're pushing the envelope [in Area C]."
 
School Building Committee member Hugh Daley said he has confidence in the revised phasing plan but, joking that he is a pessimist by nature, encouraged the district to consider its "Plan B" if Area C falls behind schedule.
 
"We have a trigger point in there," Daley said. "At some point in about May or early June, you guys are going to have to make a decision on pulling down the back building. You have to have a timeline, and if you haven't hit dates by a certain point, you guys have to say, 'Don't touch that building.' "
 
Interim Superintendent Kimberley Grady told the committee that the district has just two options: have a new building or delay demolition of the old one.
 
"Typically, when you miss a mark, you have the opportunity to bus kids to an abandoned building," Grady said. "The only one in the area is [Adams Memorial Middle School], but their boiler system is decommissioned, so it's not an option. The other option would be bringing in trailers … If we needed that number of trailers, we'd need to know we need that now [in order to order enough]."
 
In the end, the School Building Committee voted unanimously to recommend that the Transition Committee approve a contract revision that reflects the new phasing plan for the project after the district has consulted with its attorney to make sure the contract amendment preserves the district's rights as an owner.
 
But first, it heard from a Williamstown resident and parent in the district, Chris Kapiloff, who also is the chief executive officer of a glass company that is a subcontractor on school projects around the commonwealth. Kapiloff, who said he has worked with both the district's owner's project manager, Dore & Whittier, and its architect, Boston's Perkins Eastman, was less sanguine about Turner's revised timeline.
 
"I've literally worked in hundreds of buildings like this," Kapiloff said. "Honestly, I would give you guys a coin flip at best of finishing on time. You're admittedly razor thin on your schedule. If anything goes wrong — if a piece of equipment breaks, if there's a sprinkler system without the right pressure, I can give you dozens of things that have happened that are outside of everyone's control — especially when your schedule only give you one shot at the end to get everything right …"
 
"I have no idea what's led you guys to this point, but if it can be four months late, it can be five months late. It's not hard to imagine [the timeline] moving into October."
 
School Building Committee and Transition Committee member Carolyn Greene clarified that the building project is "not four or five months late." Rather, the phasing of the project has shifted; the overall end date for the project, in December 2018, has not changed.
 
Giso told the committees his firm has "never not delivered."
 
"[Turner Vice President and General Manager] Carl Stewart made it clear when he was here last week that this is not going to be the first," Giso said.

Tags: MGRHS school project,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

National Grid Hosts Customer Assistance Events In The Berkshires

WALTHAM, Mass. — National Grid will hold a series of in-person Customer Assistance Events this December. 
 
As colder weather sets in, these events are designed to help customers manage winter energy bills and explore cost-saving programs.
 
In Berkshire County:
  • Dec. 4 – Town Library, Williamstown, 4:00pm – 8:00pm, 1095 Main Street, Williamstown
  • Dec. 5 – National Grid Great Barrington Office, 11:00am – 2:00pm, 927 South Main Street, Great Barrington
  • Dec. 5 – Sheffield Bushnell-Sage Library, 5:00pm – 8:00pm, 97 Main Street, Sheffield
Many of these events will continue to take place at local senior centers, making it convenient for older residents to access personalized assistance. Attendees at any location will have direct access to National Grid Customer Service Specialists, who can provide personalized guidance on payment options and energy solutions to meet each household's needs.
 
"As December begins, customers still have opportunities to find support and manage energy costs," said Bill Malee, chief customer officer, National Grid. "We're proud to host many of these events at local senior centers, ensuring customers have easy access to the support they need. Our in-person events are a great way for customers to connect with our team, learn about flexible payment options, and discover energy-saving programs that can help make a real difference this season."
 
Customers attending in-person events will have the opportunity to meet with representatives from National Grid, who will be on-site to assist with billing issues and provide information on:
  • Enrolling in National Grid's new Payment Assistance Bundle
  • Enrolling in Budget Billing
  • Enrolling in the Energy Discount Rate (for qualifying customers)
  • Scheduling home energy assessments and sharing information on other energy efficiency opportunities for homes or businesses 
These events are part of National Grid's broader commitment to affordability and reliability. Customers can also access support by calling 1-800-233-5325.
 
National Grid customers can now sign up for a new Payment Assistance Bundle. The bundle combines three solutions to make it easier for managing energy costs and paying down past due amounts over a 12-month period.
  • Deferred Payment Agreement: Spread out past-due balance into future monthly payments.
  • Automatic Monthly Payments: Automatically deduct payments from your bank account each month and avoid missing due dates.
  • Budget Plan: Break down annual energy costs into balanced monthly payments, making it easier to budget and plan expenses.
Customers interested in enrolling in the Payment Assistance Bundle can do so online by visiting ngrid.com/hereforyou, at an in-person event, or by calling 1-800-233-5325.
View Full Story

More Williamstown Stories