Pittsfield Council Asked To Contribute More Toward Clapp Park Project

By Andy McKeeveriBerkshires Staff
Print Story | Email Story
PITTSFIELD, Mass. — After bids came in too high twice, the City Council is being asked to up the city's contribution toward the renovation of Clapp Park.
 
The city had received a $400,000 state grant to undertake a massive restoration of the West Housatonic Street park. That was matched by city funds for bathrooms, the community preservation act funding, $180,000 donation from the Rotary Club, and a $5,000 donation from Carr Hardware.
 
But, it is not enough. Parks and Open Spaces Manager Jim McGrath said the project is about $150,000 underfunded after the most recent bids were opened. The project has to be done by the end of June or else the city will lose its starting funding for it. The project had already been scaled back once in a cost-cutting measure and the decision has been made to ask the City Council to cover the difference.
 
"This allows the whole project to move forward comprehensively and the way it was designed," McGrath said.
 
The focus on the park started with the formation of a Buddy Pellerin Field Committee. That group organized an effort to rename the baseball field, which is home for the Pittsfield High Generals, after the former coach. From there, they've began raising money and making improvements to the field. The group has a multi-year vision to completely transform the field.
 
The Rotary Club then joined in. In celebration of its 100th year, the group voted to donate $180,000 to build a splash pad at Clapp Park. The city brought those funding sources together and applied, and received, the state grant. The City Council would later approve another $150,000 to be used to renovate the bathrooms at the park.
 
"That was a critical part of the project," McGrath said of the restrooms.
 
McGrath said he wasn't sure why the bids on the project came in over budget twice. The design put to bid was already scaled back from the original vision and McGrath said it seems that bids have been coming in higher than expected more frequently now.
 
"I don't know what the reasoning is all I know is we have a project we are trying to execute and we don't have enough funding," McGrath said.
 
The City Council is now being asked to increase the capital authorization by $325,000 and then rescind the $150,000 eyed specifically for the bathrooms. The bathrooms aren't being removed from the project but rather the funds for the entire project are being consolidated into one authorization.
 
That move will give the $150,000 or so needed to complete the project plus a little extra for contingency should an issue be discovered during construction.
 
"Any time you start scratching into the ground and working on the subsurface, there are always unknowns," McGrath said, later adding,"if we don't need all of that money, we won't use all of that money."
 
The city had hoped to have the project's contract awarded already and the timeline is getting tighter. McGrath said the deadline for the state funds is June 30. 
 
"We risk losing the $400,000 reimbursement," McGrath said.
 
The timeline now is to get the contract awarded and work started in early May. The work on the baseball field would be done last, allowing for the high school team to finish the season on the field.
 
"We can get this project in in the course of two months," McGrath said.
 
Mountain View Landscape was the sole bidder on the project this time with a price of $672,750. That price, however, is just for the base work, McGrath said. He said the city will also be purchasing the playground equipment, splash pad parts, player benches, and other materials for the work on their own. Nor does that price include a buffer should there be problems.
 
McGrath said he isn't happy that the department is in the position to have to ask the council for more money but he believes the councilors will see the value in the project.
 
"I have confidence that the council likes the project and will back the project," he said.
 
The City Council will field the request at its meeting Tuesday evening.
 
Ongoing Coverage:
 
image description

Pittsfield Finalizes Plans For Clapp Park Renovations

A final design for more than a half million dollars worth of improvements to Clapp Park was finalized Monday. The Parks Commission gave its stamp of approval on the design crafted by Berkshire Design Group. The design, however, isn't entirely what parks officials had been hoping for when first crafted.

 
image description

Pittsfield's Clapp Park Renovation Getting Scaled Back

Parks and Open Space Manager James McGrath told the Parks Commission on Tuesday that the design currently crafted is estimated to go over the $675,000 budget for the project. He is now working with Berkshire Design on scaling the concept back slightly to make the numbers work

 
image description

After Winning State Grant, Pittsfield Starts to...

The new splash pad at Clapp Park is eyed to be located where the basketball court currently sits. The basketball court is eyed to move to the rear of the property. A new parking lot, and curbcut onto Route 20, will be built next to the splash bad. The bullpen will be moved. The playground will be renovated. The backstop will be moved back and the track will be repaired.

image description

State Awards $400K For Major Renovation of Clapp Park

The state is investing $400,000 to renovate Clapp Park. Gov. Charlie Baker announced on Friday some $6.3 million worth of grants statewide for park improvement projects. Pittsfield received the maximum amount through the Executive Office of Energy and Environmental Affairs project for a massive renovation to the West Housatonic Street Park.

 
image description

Carr Hardware Delivers Check For Pittsfield Splash Pad...

On Monday, Carr Hardware did what it said it would do - donate its recent prize winnings toward building a splash pad at Clapp Park. The local company has won the "Indie Award" as small business of the year from the business organization Independent We Stand. The prize includes $5,000 cash, which Carr Hardware opted to go toward a splash pad project in partnership with the city of the Rotary Club.

 
image description

Pittsfield's Clapp Park Could Be Next To See Major...

Clapp Park could see a major upgrade in the coming years. The city has partnered with the Rotary Club and the Buddy Pellerin Field Committee on a state grant to complete a major park renovation.

 
image description

Parks Commissions Approves Improvements To Pellerin...

The first round of improvements to the newly named Buddy Pellerin Field at Clapp Park is set for this summer. The Parks Commission gave the group heading the effort the Okay to order a scoreboard and to continue planning for a number of other additions and changes to the field. The group has already raised $20,000 and has set a goal of a quarter of a million to make four phases worth of improvements to the ballfield.

 
image description

Buddy Pellerin Ballfield Project Raising $250,000 for...

The committee behind the naming of Buddy Pellerin Baseball Field at Clapp Park has set a goal of raising $250,000 in the next three years to improve the ballfield. The Parks Commission in April unanimously approved renaming the Clapp Park ballfield after longtime baseball coach George "Buddy" Pellerin. The committee for the Clapp Park Project had applied for the naming and presented the commission more than 150 letters of support.

image description

Clapp Park Ballfield to Be Named After Coach Pellerin

The baseball field at Clapp Park is being named after former coach Buddy Pellerin. The Parks Commission approved the naming on Tuesday after being overwhelmed by support from former players, family and friends of Pellerin. A large crowd filled the meeting room as Ken Ferris gave a presentation on not just why Pellerin deserved the recognition but also plans to upgrade the field.

 
 

Tags: parks commission,   public parks,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Dalton Man Accused of Kidnapping, Shooting Pittsfield Man

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — A Dalton man was arrested on Thursday evening after allegedly kidnapping and shooting another man.

Nicholas Lighten, 35, was arraigned in Central Berkshire District Court on Friday on multiple charges including kidnapping with a firearm and armed assault with intent to murder. He was booked in Dalton around 11:45 p.m. the previous night.

There was heavy police presence Thursday night in the area of Lighten's East Housatonic Street home before his arrest.

Shortly before 7 p.m., Dalton dispatch received a call from the Pittsfield Police Department requesting that an officer respond to Berkshire Medical Center. Adrian Mclaughlin of Pittsfield claimed that he was shot in the leg by Lighten after an altercation at the defendants home. Mclaughlin drove himself to the hospital and was treated and released with non-life-threatening injuries. 

"We were told that Lighten told Adrian to go down to his basement, where he told Adrian to get down on his knees and pulled out a chain," the police report reads.

"We were told that throughout the struggle with Lighten, Adrian recalls three gunshots."

Dalton PD was advised that Pittsfield had swabbed Mclaughlin for DNA because he reported biting Lighten. A bite mark was later found on Lighten's shoulder. 

Later that night, the victim reportedly was "certain, very certain" that Lighten was his assailant when shown a photo array at the hospital.

According to Dalton Police, an officer was stationed near Lighten's house in an unmarked vehicle and instructed to call over the radio if he left the residence. The Berkshire County Special Response Team was also contacted.

Lighten was under surveillance at his home from about 7:50 p.m. to about 8:40 p.m. when he left the property in a vehicle with Massachusetts plates. Another officer initiated a high-risk motor vehicle stop with the sergeant and response team just past Mill Street on West Housatonic Street, police said, and traffic was stopped on both sides of the road.

Lighten and a passenger were removed from the vehicle and detained. Police reported finding items including a brass knuckle knife, three shell casings wrapped in a rubber glove, and a pair of rubber gloves on him.

The response team entered Lighten's home at 43 East Housatonic before 9:30 p.m. for a protective sweep and cleared the residence before 9:50 p.m., police said. The residence was secured for crime scene investigators.

View Full Story

More Pittsfield Stories