Williamstown Fire District Moving to Acquire New OPM for Station Project

By Stephen DravisiBerkshires Staff
Print Story | Email Story
WILLIAMSTOWN, Mass. — More than two years after choosing an owner's project manager for its new station project, the Fire District is set to move forward with a new OPM.
 
Prudential Committee Chair David Moresi mentioned the move during his report to the annual Fire District meeting on Tuesday at Williamstown Elementary School.
 
"We are very pleased with the most recent [construction cost] estimates projected, as well as what we consider to be a significant cost savings by soliciting for a new OPM," Moresi said during his address to the meeting.
 
After the half-hour meeting concluded, Moresi confirmed that the protracted negotiations with Colliers International on a final contract for management services were a sign that things might not work out with the firm.
 
"As I've said from Day 1, it's our goal to do this project in a fiscally responsible way," Moresi said. "We felt [the negotiations] were not heading in the direction of our best interest."
 
The good news is that the five-member Prudential Committee could select a new OPM as soon as Wednesday.
 
Moresi said the district's Building Committee received four responses from its Request for Qualifications, vetted those proposals and voted to recommend the Prudential Committee enter negotiations with Skanska Construction, which has a regional office in Boston.
 
"They're a known entity in the area," Moresi said of Skanska. "They've been involved in a lot of quality projects."
 
Skanska was recently selected as OPM for the Wahconah Park project and oversaw the construction of the new Taconic High School in Pittsfield.
 
The Fire District's project was a focus throughout Tuesday's annual meeting.
 
Moresi opened his remarks by quipping that it had been a "pretty quiet" year for the district, before "reminding" himself that, in fact, it was an eventful 12 months indeed.
 
"We received overwhelming town voter approval for our new station," he said. "It was truly a historic year for the district, and the town made it clear it wants the district to continue meeting the needs of the town for many years to come."
 
Building Committee Chair K. Elaine Neely told the meeting that her panel remains hard at work at achieving its three goals: "a facility that provides for the operating needs of the district for 50 years," meets the town's net-zero carbon emissions goal and does it all "at the lowest possible cost."
 
The meeting members breezed through the 12-article meeting warrant with hardly a question and no dissenting votes as it approved the district's operating budget and one-time expenditures for fiscal year 2024.
 
Prior to the meeting, the district held its annual election. Twenty-eight voters cast ballots in the two uncontested races. John Notsley won another three years on the Prudential Committee by a vote of 28-0, and Paul Harsch was returned as district moderator for three years by a vote of 23-0 with five blank ballots.
 
"Congratulations to Mr. Notsley and Mr. Harsch," Harsch joked before moving on to the main business of the evening.
 
In addition to hearing reports from Moresi and Neely, the meeting heard from the district's recently appointed treasurer, Billie Jo Sawyer, who reported that the district's free cash for FY22 has been certified by the commonwealth and its audit report once again came back clean.
 
Jeffrey Thomas, the chair of a public advisory panel he created with Notsley in 2019 for the district, addressed the small crowd to encourage the Fire District to continue spreading the word about its benefit to residents.
 
"There isn't sufficient awareness in this community for what the Fire District does and all the sacrifices volunteers make to keep our community safe," Thomas said. "[Awareness has] improved, and the turnout at the special district meeting was proof of that. But don't rest on your laurels. Don't let up in getting the word out about what you do.
 
"People have short memories. People come in and out of town. Far too many of us are aware of you only when we need you. That's important to change, especially when the property tax bills come in in a few years."
 
Moresi's remarks indicated that higher awareness of the district may be paying off in other ways, beyond the vote on the building.
 
"The district has witnessed positive improvements, seeing our numbers grow," Moresi said, noting that more call-volunteer firefighters were recruited both from town residents and the student population at Williams College. "As Chief [Craig] Pedercini put it recently, 'It is great to show up at a scene and see more personnel at the scene.'
 
"I am confident, with the coming of a new station, this upward trend will continue."

Tags: annual meeting,   fire district,   fiscal 2024,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Developer Working Through Delay in Opening Williamstown Apartments

By Stephen DravisiBerkshires.com Sports
 
WILLIAMSTOWN, Mass. -- A delay in obtaining the certificate of occupancy for a 54-unit apartment building on Water Street forced some tenants to postpone their moves this week.
 
The "River Lofts" apartments, the third and final planned phase of development at the Cable Mills property, is funded in part by $480,000 in town contributions to the developer.
 
On Friday morning, iBerkshires.com heard from would-be occupants that they had to change their plans at the last minute while the four-story building awaited final sign-off from the town's building inspector.
 
"We are very close but there are a few small punch list items that need to be finalized," Town Manager Robert Menicocci wrote in a midday Friday email. "Our building inspector is working closely with them each day to help them get their c/o. We are hopeful that it can happen in the next day or so."
 
Developer David Traggorth of Hanover, Mass., firm Causeway Development said that such delays are not uncommon and are taken into account in the initial leases of new developments like River Lofts.
 
"As is typical with new construction, the final inspection process involves several approvals, and timing can shift," Traggorth wrote in reply to an email seeking information. "Given this reality, resident leases anticipate potential construction-related delays and address changes to occupancy dates and rent adjustments while an apartment is unavailable.
 
"We’re completing the final inspection and certificate of occupancy process at River Lofts, and a handful of residents have had to adjust their move-in dates. We understand that changing an expected moving date is disruptive and our leasing and marketing team is in touch with each affected resident, working through individual needs on a case-by-case basis."