The School Building Needs Commission met in the new high school for the first time.
PITTSFIELD, Mass. — An oil spill has led to contractors to dip more into the contingency fund for the new Taconic High School.
Jim Moran, project manager with Skanska USA, said a slab under the boiler room was removed during the demolition of the original school, unveiling an oil spill contaminating the soil. The land there had to be remediated and rain had poured in requiring treatment.
"The good news is that the project remains on budget. But we had some challenges over the winter and spring, unforeseeable conditions that cost money that we didn't anticipate," Moran said.
"The big one we just finished up Friday when we unearthed the slab for the boiler room, there was an oil spill underneath it. That had to be remediated."
Moran said the clean up is costing an unanticipated $50,000. It becomes the second contamination issue the construction project has unearthed. When workers began digging for the site of the new school, a significant amount of old construction material was found buried in the ground. That cost an estimated $500,000 additional cost to remediate.
The project had included about a $2.5 million in its budget for contingency to handle such issues as that. But that is getting chipped away as time goes on. Moran said another $50,000 may have to come out of contingency as well because of prices for furniture, fixtures, and equipment for the horticulture building and the auto shop.
Moran said $50,000 was estimated for those fixtures but not all of the items were included in the bidders. That is requiring the contractors to track down prices and purchases for a number of pieces through state contract. Moran said right now it is estimated that the entire slate of equipment will cost slightly more than $100,000.
"We had a lot of items that were bid on by the contractors," Moran said. "Our consultant has plugged in numbers for what we believe the cost of those missing items are and when you add them all up, it is double the budget."
Moran said Graybar and Carr Hardware both submitted bids — the second time they were put to bid — and Graybar's bid was non-conforming and had to be eliminated. Carr Hardware had bid on only some of the items needed but not all. Moran said the city can accept the Carr Hardware bids but will still need to shop around to find the rest of the material.
"It is going to take a lot of work to individually chase each price," Moran said.
Purchasing Agent Colleen Hunter-Mullett said there is about $500,000 remaining in contingency to cover the additional needs. But, the project still isn't completed.
"I am cautiously optimistic that we will have some left," she said.
Gilane Building Co.'s Dave DeForest said the entire project will be done later this year. The old school has been demolished and all that is left are piles of crushed concrete. Maxymilian, which was subcontracted to grade the site of the former school for future soccer and lacrosse fields and parking lot, has been somewhat hindered by the rain.
DeForest said a space directly across the street has been graded to become a parking lot, likely for teachers. That will allow the teacher spaces now to be used by students who are being asked to park in the former shop lot on the far south end of the property and work can shift to there.
He said the first paving coast is expected Friday, depending on weather. Meanwhile, concrete for the horticulture building is ongoing.
"We are constantly watching the weather for both the concrete pouring and the paving," DeForest said.
The new sports fields won't be ready for use for some time. DeForest said Maxymilian is trying to plant grass as it moves along to capitalize on this growing season. He hopes all of the grass is planted by the end of July. It takes two seasons of growing before they can be used so DeForest estimates that they will be ready in 2020.
Superintendent Jason McCandless, however, isn't so optimistic. He said he's eyeing 2021 as the first season for those fields to ensure the ground can handle the usage.
The horticulture and greenhouse buildings are moving along but were held back a bit because of the rain as well. DeForest said the construction company put off doing concrete work to avoiding having to heat it and instead wait for the weather to break. Meanwhile, the mechanical work is underway and eventually the finishes. He hopes to have that done in June.
Meanwhile, in the current Taconic the company is picking through the last pieces. DeForest said the paint booth for auto body is still be programmed to align with the fire alarm system and he expects that to be done in early May. Meanwhile, there is some work booths to be completed in the electrical shop that again he hopes to be done in May. The security system is being fine tuned and administration will be trained more in depth in the system in May — the staff has some level of training on it but DeForest said there is even more the system can do the staff will learn.
Additionally, a company working for the Massachusetts School Building Authority has to re-test the air conditioning system during the summer. As those pieces move along, DeForest said the group is working through some 5,390 "punchlist" items. He said the group is down to the last 79.
DeForest said none of those pieces had held up any education taking place in those rooms. McCandless added that the only educational hold up was that in the fall the Shakespeare and Co. production of Hamlet was moved to Barrington Stage while workers finished the lighting in the auditorium.
"We've been really pleased with the way this place has served kids and the teachers," McCandless said.
The $120.8 million new school broke ground in 2016 and opened in the fall of 2018 for its first class of students. Next year, the school is expected to have some 900 students attending the school with 400 of them being in vocational programs. McCandless said the demand for the vocational programs, specifically electrical, has been high and the district is ramping up those programs up — including adding new ones next year — quicker than originally anticipated.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Capeless Students Raise $5,619 for Charity
By Breanna SteeleiBerkshires Staff
PITTSFIELD, Mass. — Students at Capeless Elementary School celebrated the season of giving by giving back to organizations that they feel inspired them.
On Monday night, 28 fourth-grade students showed off the projects they did to raise funds for an organization of their choice. They had been given $5 each to start a small business by teachers Jeanna Newton and Lidia White.
Newton created the initiative a dozen years ago after her son did one while in fifth grade at Craneville Elementary School, with teacher Teresa Bills.
"And since it was so powerful to me, I asked her if I could steal the idea, and she said yes. And so the following year, I began, and I've been able to do it every year, except for those two years (during the pandemic)," she said. "And it started off as just sort of a feel-good project, but it has quickly tied into so many of the morals and values that we teach at school anyhow, especially our Portrait of a Graduate program."
Students used the venture capital to sell cookies, run raffles, make jewelry, and more. They chose to donate to charities and organizations like St. Jude Children's Research Hospital, Berkshire Humane Society and Toys for Tots.
"Teaching them that because they have so much and they're so blessed, recognizing that not everybody in the community has as much, maybe not even in the world," said Newton. "Some of our organizations were close to home. Others were bigger hospitals, and most of our organizations had to do with helping the sick or the elderly, soldiers, people in need."
Once they have finished and presented their projects, the students write an essay on what they did and how it makes them feel.
"So the essay was about the project, what they decided to do, how they raised more money," Newton said. "And now that the project is over, this week, we're writing about how they feel about themselves and we've heard everything from I feel good about myself to this has changed me."
Sandra Kisselbrock raised $470 for St. Jude's by selling homemade cookies.
"It made me feel amazing and happy to help children during the holiday season," she said.
Gavin Burke chose to donate to the Soldier On Food Pantry. He shoveled snow to earn money to buy the food.
"Because they helped. They used to fight for our country and used to help protect us from other countries invading our land and stuff," he said.
Desiree Brignoni-Lay chose to donate to Toys for Tots and bought toys with the $123 she raised.
Luke Tekin raised $225 for the Berkshire Humane Society by selling raffle tickets for a basket of instant hot chocolate and homemade ricotta cookies because he wanted to help the animals.
"Because animals over, like I'm pretty sure, over 1,000 animals are abandoned each year, he said. "So I really want that to go down and people to adopt them."
Kyzer and Cali are both poodles. Kyzer is the male and is 7 years old, and a little bigger than his sister Cali, who is a miniature of Kyzer and 8 years old.
click for more
A 700-square-foot outdoor water attraction is planned for the 2.1-acre park at 30 John Street. City officials hope to have it operational by summertime.
click for more