image description
The Pecks Road bridge was abruptly closed on Monday afternoon after a state inspection found dangerous deficiencies.

Rapid Deterioration Fully Closes Pecks Road Bridge

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

Detours have been set because of the closed bridge.

PITTSFIELD, Mass. — Rapid deterioration of the Pecks Road bridge has led to its closure until further notice and a hopefully expedited process to replace the entire structure.

The bridge was fully closed to traffic on Monday following an inspection from the Massachusetts Department of Transportation that found six areas of deterioration. Repair work is slated to begin in August by Rifenburg Contracting Corp. and the city says it continues to work closely with MassDOT on steps ahead.

Work will include demolition and reconstruction of the bridge over Onota Brook that has been reduced to one lane for five years. A detour has been routed from Pecks Road to Onota Street, Vin Herbert Boulevard, and Valentine Road.

"Today, upon a 6-month routine inspection, the state found signs of rapid deterioration and ordered the bridge to be closed," Commissioner of Public Services and Utilities Ricardo Morales wrote in an email.

"We are now moving towards having the bridge replaced in one go, as opposed to splitting the work in phases and maintaining traffic flow. This has some setbacks but overall the project should be completed faster."

The bid was awarded to the contracting company for $1,535,420 with a 10 percent construction administration budget and a 10 percent contingency budget, bringing the total estimated cost to $1,842,504.

Morales reported that the city has multiple authorizations for funding from previous years and a state Small Bridge grant that will cover all of the costs. He said a schedule will be shared once the contractor finishes changing the construction approach.


Pedestrian access is still available until construction begins.

The state found structural deficiencies on the south side of the bridge in 2019 and requested that it be closed. Because of the sudden nature of the request and without indication of these deficiencies from prior inspections, the city requested that a section be opened with a single lane of travel, Morales explained.

This was granted and the city started the "lengthy" design process while travel was reduced to one lane with a temporary signal and a ban on heavy vehicles.

"The design process had a rocky start with pandemic-related delays," Morales reported.

"In 2021, the design was pushed through and by 2022 it was fully designed and submitted to DOT for Chapter 85 approval. Under this review period, the DOT had major changes proposed and it took the city until late 2023 for all to be resubmitted. Approval was granted soon after and the city moved to bid the work and hire a contractor."

During the inspection on July 22, MassDOT found:

  • settlement in the wearing surface along the east curb, full length x 3 feet wide by up to 2" deep (This aligns with bay 17)
  • buckling of beam 18 along with a gap between the deck and the beam forming up to 1/4"
  • beam 17 bottom flange is distorted up to 1/4" full length
  • beam 16 bottom flange is distorted 3/4" full length. (Beam has several holes in the flange and web)
  • beam 14 has holes at the north end and the web is distorted 1-1/4" out of the plane
  • beam 13 web is distorted 5/8" out of the plane

For questions, contact the Engineering Division at 413-499-9327

 


Tags: bridge work,   closure,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield Cleans Downtown Litter, Works on Outreach Program

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — As the city develops a peer support outreach program, workers are clearing the downtown of potentially hazardous litter from the wintertime. 

Over the past three weeks, the Health Department has sent out inspectors to assess sanitary conditions in the downtown, beginning on North Street, moving to First Street, and to the McKay Street parking garage. 

"We've identified a lot of needles, and mostly needle caps and then small drug paraphernalia, and while we're identifying them, we're noting where we're finding them, and we're also picking them up and disposing of them properly," Director of Public Health Andy Cambi said. 

"… We have not found any human waste sanitation issues currently, again, not to say that there isn't any, but I think it also speaks to the fact that we do have a new facility that's open, that's being run, The First, which does offer bathroom facilities, laundry facilities." 

On Monday, he updated the Public Health and Safety subcommittee on the progress of the upcoming peer support outreach program and cleanup efforts in the area it will serve. 

The First housing resource center opened in February in the basement of the Zion Lutheran Church with bathrooms, lounge spaces, lockers, and more. In its early days, it averaged about 50 visitors daily; on Sundays, an average of 70 visitors. 

Cambi said he is in constant communication with ServiceNet, which is operating The First. 

"It has been used heavily, so I think that speaks to the relief of issues that we're seeing in the downtown area in regards to those sanitation issues," he added.

"It's a great resource that's available that is being constantly used, so again, what it was intended for."

When the department comes across human waste, they will connect with Department of Public Works staff to have it cleaned and sanitized.  Workers can make a clear distinction between pet and human waste, Cambi reported. 

View Full Story

More Pittsfield Stories