The School Building Committee opted to go with the post sign, but asked for changes to the font and graphics.
NORTH ADAMS, Mass. — The Greylock School Project has passed one of two local permitting authorities in preparation for bidding documents to be released Nov. 17.
The Conservation Commission gave the OK for the $65 million project on Tuesday.
"We're targeting a completion date for the documentation on Nov. 17," Jesse Saylor of TSKP Studio told the School Building Committee meeting just before the Conservation Commission. "The real reason that's later than we had anticipated is because of the local review meetings ... We have a Conservation Commission meeting, public hearing today, Oct. 21, at 6 p.m., that's what we're going to right after this meeting, and that will be our first time meeting with the Conservation Commission. ...
"We anticipate meeting with the Planning Board at a public hearing on Monday, Nov. 10. If we're approved to proceed at that meeting, will be ready to go to bid. And so we've set the bid date one week later, leaving a week if there are any amendments that are required to the documentation."
Saylor and Chelsea Christenson, a civil engineer with Nitsch Engineering, presented the plans to the commission.
"Our goal of the project is to bring nature to the students through the design of the school, also the building itself is a good environmental steward," said Saylor. The building systems are all electric. No fossil fuels are used to heat or cool the building. Energy models anticipate that the building will be highly energy-efficient thanks to its highly insulated walls and roof and also due to geothermal wells that will harvest the relative warmth of the earth in the winter and its coolness in the summer to offset human cooling loads."
The site itself "retains some natural resources worthy of protection," he said, including an intermittent stream that runs into a pipe on the southern edge and, to the north, there's a "more significant" wetlands area.
The stream will not be affected and the wetlands are part of the school drainage will continue to be fed that way. The project also is not expected to affect Well No. 2, a backup for the city's water system.
"The project will also conserve mature tree growth at the north edge of the site and at the south edge of the site, which creates a natural buffer to residential residential neighborhoods to the north and south," Saylor continued.
Con Com Chair Andrew Kawczakasked the city's Public Services Commissioner Timothy Lescarbeau, who was in attendance, if the plan met the wellhead protection requirements.
"The well is in a non-conforming zone to begin with, because it's close to the roads and you know the school, the old school," he said. "The area is much better now than it was considering GreylockWorks was an aluminum anodizing plant that always made me cringe. Now it's retail and rental space, residential, so I don't see any impact from this."
Christenson walked through the details for water drainage and catchment, noting "we did get a letter from DEP Water Resources supporting the project."
In response to questions, she and Saylor elaborated that the turtle pond is a manmade educational component and not part of the water management system.
"A lot of design and research has gone into this pond to make these turtles survive," Christenson said. "I know our landscape architects have done a lot of research on what they need and hibernation and all sorts of things. So it's been fascinating listening to it."
The turtle pond was a feature of the open courtyard in the old school that is being replicated in the new school. Saylor said it will be lined without about 3 feet depth of sand, though there are conversations about the depth because of the age of the children in prekindergarten-through-Grade 2 school.
Before the commission meeting, the School Building Committee narrowed down its choices on the main sign. The members had not liked the previous iterations, so TKSP came back with options incorporating their feedback.
"There's a attempt in both of these signs to kind of match up with the building in a little bit of an abstract way," said Saylor.
They were offered a modification of the post sign with straight rather than peaked top (Option 1) and a simpler sign using the vertical fiber cement siding planned for the school with a flat top (Option 3). Members liked the graphic on the post sign and the sided option but there were concerns it looked too much like a bench for hanging out. Several stated concerns on the font and the ability to read the lettering; Superintendent Timothy Callahan reminded them the signs would be about 8 feet long, which would be reflected in the letter.
"I want something that has a little bit more whimsy, that's a little bit more exciting, because, like, we're making this for them, like we want them to see the sign and get excited," said member Andrew Rosenburg, pitching for the post sign. "It's a nice time, but 3. That's I feel like it kind of goes towards more adult sensibilities."
The members voted for Option 1, the post sign, but asked for more work on the font and graphic.
The committee also voted to hire Energy Tax Savers Inc., a consulting firm specializing in green energy grants, to work on its federal geothermal financing.
Tim Alix of Collier's International, the owner's project manager, said it's been recommended by other districts and the Massachusetts School Building Authority to have a consultant because the applications will be completed after the system in operational.
"By having somebody work with us and assist us, we'll be requesting that the contractor document the costs and breakdowns in such a way that we have all that information available to us, and this consultant would then work with the district on assembling that application and submitting those those documents," he said.
Collier's sought three proposals and Energy Tax Savers was the lowest at $15,900 compared to the other two about $50,000 with alternative add-ons.
"I think that that would be the outfit to go with, the prices which is more reasonable, and we have experience of working with them, and things have gone well," Alix said.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
North Adams Updated on Schools, Council President Honored With 'Distinction'
By Tammy Daniels iBerkshires Staff
Superintendent Timothy Callahan gives a presentation on the school system at Tuesday's City Council meeting.
NORTH ADAMS, Mass. — The City Council got an update on what's up in the school system and its president was inducted into the mayor's Women's Leadership Hall of Fame.
Mayor Jennifer Macksey, as the city's first woman mayor, established the Hall of Fame in 2022, during March, Women's History Month, to recognize local women who have had a positive impact on the city. Past inductees have included the council's first woman president Fran Buckley, Gov. Jane Swift and boxing pioneer Gail Grandchamp.
She described President Ashley Shade as a colleague and a friend and a former student.
"Ashley is known not just for her leadership, but for her compassion, her ability to listen, to understand and to stand up for those whose voices are often gone unheard," the mayor said. "She has been a tireless advocate for the LGBTQ plus community and marginalized communities at both the local and national level here in North Adams."
Elected in 2021, Shade is the first openly transgender person to hold the role of council president in Massachusetts. She also leads the first-ever woman majority council in the city's history.
The McCann Technical School graduate also has served on boards and commissions, "always working to make our city more inclusive, equitable and welcoming," said the mayor. "Ashley not leads not only with strength, but with a heart, and our community is a much stronger place because of it."
Shade, wearing her signature pink suit, was presented with a plaque from the mayor designating her a "woman of distinction."
The City Council got an update on what's up in the school system and its president was inducted into the mayor's Women's Leadership Hall of Fame. click for more
The Massachusetts Museum of Contemporary Art Commission welcomed bread-baking appliance designers Brod & Taylor to the campus on Monday. click for more
He explained his plans to the License Commission on Tuesday as he applied for an all-alcohol license for Zio Roberto Ristorante and Taverna, which is expected to open in late May.
click for more
Qwanell Bradley scored 33 points, and Adan Wicks added 29 as the Hoosac Valley boys basketball team won a Division 5 State Championship on Sunday. click for more