DALTON, Mass. — The anticipated rise in the water and sewer rates has sparked discussion on whether implementing meters could help mitigate the costs for residents
 
The single-family water rate has been $160 since 2011, however, because of the need to improve the town's water main infrastructure, prices are anticipated to increase. 
 
"The infrastructure in town is aged … we have a bunch of old mains in town that need to be changed out," said Water Superintendent Robert Benlien during a joint meeting with the Select Board. 
 
The district had contracted Tighe and Bond to conduct an asset management study in 2022, where it was recommended that the district increase its water rates by 5 percent a year over five years, he said. 
 
This should raise enough funds to take on the needed infrastructure projects, Benlien said, cautioning that the projections are a few years old so the cost estimates have increased since then. 
 
"The AC mains, which were put in the '60s and '70s, have just about reached the end of their life expectancy. We've had a lot of problems down in Greenridge Park," which had an anticipated $4 million price tag, he said. 
 
The main on Main Street, that goes from the Pittsfield/town line to North Street, and up through woods to the tank, was priced at $7.6 million in 2022, he said. 
 
"There's a bunch of stuff that needs to be started, and start working on water main improvements and right now, we don't have the funding for it, especially with the debt that we already have for the two tanks, and the dam, and the Don Elser Pump Station," Benlien said. 
 
"I think we need to start being proactive and I think this is a good start to get us going in the right direction to have the funding available if we do decide to take debt on or work on saving up some money so we can do the smaller projects."
 
Additionally, the town pays Pittsfield for its share of sewer usage and with upgrades needed at the $74 million upgrade to the wastewater system, rates are expected to rise there as well. 
 
The town sends sewage to the city's treatment plant and is billed by Pittsfield based on the total tonnage Dalton sends into its system, Town Manager Eric Anderson said in a follow up. 
 
The town then divides the bill it receives from Pittsfield between all the town residents and businesses at a flat rate. 
 
According to Town Collector Joseph Dinofrio the current sewer rates are $282.00 twice a year, which is $564.00 annually per unit.
 
Pittsfield has proposed raising its fees for the town to include a charge to contribute towards the capital costs. However, there is not an official agreement with the city yet, everything is still in flux, Anderson said. 
 
"Up to this point, they've borne the capital costs of upgrading the system. Whereas in the past, Dalton has borne its fair share of the capital costs. Whereas up to this point, we really haven't with this project," he said. 
 
It can be assumed that the sewer costs will increase at least one and a half times, because that is going to be the multiplier Dalton residents are going to pay, he said. 
 
However, the city is also looking into taking on an additional bond to upgrade its wastewater treatment infrastructure, primarily to address stricter requirements for removing nutrients from effluent, Anderson said. 
 
The city's Department of Public Works is requesting the City Council authorize borrowing up to $15.2 million; this request was referred to the Finance subcommittee. 
 
Previously, treatment focused only on eliminating biological hazards, but new regulations require capturing more nutrients, making the process more technologically complex and costly, he explained. 
 
It is yet to be determined the financial impact this will have on Dalton, Anderson said.
 
Although overseen by separate governing bodies, water and sewer services are closely intertwined. The water department which is managed by the Fire District and overseen by the Board of Water Commissioners, while sewer services are governed by the town. 
 
With projected increases looming, this is a perfect junction to consider meters, because households would be billed based on its usage instead of a flat free across everyone in town, said Select Board member Anthony Pagliarulo during the joint meeting. 
 
"We're not in a drought condition," he said, adding that the Quabbin Reservoir is at 80 percent capacity, which is its lowest lever since 2017 and "water is a precious resource."
 
If the town were to implement meters, it would use water usage as a proxy for sewer output so sewer charges to residents would be allocated based on water use estimates, Anderson said. 
 
"Ideally, if you're a homeowner, and you want to conserve and you want to use low flow devices, and you make sure you don't have leaks in your system, and your toilet doesn't run…and you don't take hour-long showers, that will affect your costs. So you have a built in incentive to save by having it metered," he said. 
 
In some cases, it is challenging to measure sewer usage based solely on water consumption—particularly for activities like gardening, where water is used but doesn’t enter the sewer system, Anderson said. 
 
"So, it's harder to account for that. There's nothing we can do that's totally fair, and I'll be perfectly willing to admit that. But I think it's more fair by [metering,]" he said. 
 
The downside is the town would have to pay for the meters, which is not cheap, and they have a life expectancy of about 20 to 30 years, depending on the meter, Anderson said. 
 
The question remains, is the amount the town would spend on water meters with the cost of being able to "accurately or more fairly" bill residents. 
 
"If you're really being a high user, theoretically you should pay more, because you cost the town more…that's kind of the way most utilities work," Anderson said. 
 
"Everybody doesn't pay the same electrical rate you pay for what you use. And the goal here is to do something very similar."

Tags: sewer rates,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Another Holmes Road Bridge in Pittsfield Down to One Lane

By Brittany PolitoiBerkshires Staff

The location of the bridge on Holmes Road. 

PITTSFIELD, Mass. — Another bridge on Holmes Road will be reduced to one lane indefinitely beginning next month and closed for the rest of the week. 

It's the third bridge so far in the Berkshires that's been downgraded in the past month: The Briggsville bridge in Clarksburg is set to be replaced by a temporary bridge and the Park Street bridge in Adams has had weight restrictions placed on it.

On Tuesday, Pittsfield announced that the bridge over the Housatonic River, located between Cooper Parkway and Pomeroy Avenue will be reduced to one lane of traffic from Monday, March 2, until further notice.

"Due to a recent inspection by the Massachusetts Department of Transportation," a press release stated, it will be closed in both directions from Wednesday afternoon (Feb. 25) to Sunday, March 1, so that barriers and a signal can be installed. 

Two years ago, a bridge farther down the road over the rail line reopened after a partial closure since 2019 and a full closure of more than 60 days. 

The bridge over the Housatonic is identified as being structurally deficient by the state based on an inspection last October. Built in 1962, the 35-foot steel-and-concrete span has an overall condition of 4, or poor. 

Pittsfield has identified a temporary detour during this work, using Pomeroy Avenue, Marshall Avenue and Cooper Parkway.

On March 2, two-way traffic will be restored in one lane and directed with a temporary signal. 

Pittsfield reported that the state has selected this bridge for repair as part of the Funding for Accelerated Infrastructure Repair program and will take responsibility for design and repair "in an accelerated way." Gov. Maura Healey announced the program last month using funds from the Fair Share Act, and is part of the governor's $8 billion transportation plan.  

iBerkshires has reached out to MassDOT for more information on this project. 

Residents and officials celebrated the reopening of the bridge over the railroad in August 2023. It had been reduced to one lane since 2019 after being found structurally insufficient and in need of a $3.5 million replacement of the overpass structure. This included a new superstructure over the Housatonic Rail line, a restored sidewalk, improved bicycle access, pavement, and traffic barriers.

View Full Story

More Pittsfield Stories