Pittsfield Road Work and Construction Updates: May 11-15
- May 11-15: Raising structures on Scalise Dr., Meleca Ave., Darlene Ave. & Kenwood St. & Brunswick Street
-
May 12-15: Milling of:
- Beacon Avenue
- Bradford Street (between Francis Avenue and Center Street)
- Crane Avenue (Unkament Park Drive to about 567 Crane Ave)
- Fairfield Street
- Jones Avenue (north side)
- Churchill Street (From Cascade Street to about 669 Churchill Street)
East Street Project:
- Overhead utility work will continue to transfer existing cables from the north side of East Street to the new poles on the south side of the street between Woodlawn Avenue and the Merrill Road/East Street intersection. During the transfers, traffic will have to be stopped at intervals of 10 minutes. Please seek alternate routes if possible.
- Structure and underground utility work continues. Please proceed cautiously through this area and seek alternate routes if possible.
- Eversource continues their underground utility work on Fenn Street between North Street and Allen Street. This work is expected to continue over the next several weeks. The westbound lane on Fenn Street between Allen Street and North Street remains closed.
Sidewalk Repairs:
- Sidewalk replacement will occur at Appleton Avenue between East Street to Dawes Avenue to replace the asphalt sections along the east side of the street. This work will take place over the next several weeks.