Most of the work has been completed, it is just landscaping, signage, and fencing mostly left.
PITTSFIELD, Mass. — The multi-year North Street reconstruction is poised to be completed in November.
Work on the final phase of the streetscape project commenced in August 2015 and is on pace to conclude by the end of November. The section of the city's main thoroughfare has been under construction from Madison Avenue and Columbus Avenue for the last phase this summer. That is the final piece in a decade-long rehabilitation of North Street.
"Much of the streetscape work has been completed at this point and we are on schedule to finish on time. The project should be completed by the end of November," said Ryan Grennan, GIS coordinator with the city's Engineering Department.
"At this point, markings and fencing are almost complete. Trees and landscaping are currently being planted. Most street signs still need to be installed (this will most likely happen in November). Inspections and punch list items will also take place in November."
The final phase of the project is funded through a state MassWorks grant to the tune of $4.5 million. The engineering firm Fuss and O'Neill designed all four phases of the project focusing on traffic and pedestrian safety, improving traffic functions and sprucing up the overall appearance. The work includes bump outs at crosswalks, new lighting, flash beacons at unsignalized crosswalks, new sidewalks, bicycle lanes, and road resurfacing.
North Street has been seemingly under construction for years as the reconstruction project was divided into phases. The efforts were first cited in a 2005 master plan for the city. The work first began in 2009 with the renovation of Park Square, which included eliminating the rotary for $3.4 million and extended to Housatonic Street, for $1.8 million, in conjunction with the redevelopment of the Colonial Theater.
Another $6 million moved the project down for another mile or so on South Street from Housatonic with the intersection and signals being revamped for $1.5 million.
In 2012, the work expanded the other way, heading North on North Street. That expansion of the reconstruction cost $3.8 million and was done in conjunction with the redevelopment of the Beacon Cinema.
New planters were chosen to spruce up the sidewalks.
After that, Phase 3 jumped to the other end of North Street to the area around Berkshire Medical Center and ending at Madison Avenue. That cost was $2 million. Now the final phase links the two ends of the project. J.H. Maximillian had the contracts for all phases of the work.
Meanwhile, the city renovated Sottile and Persip parks, pocket parks on either side of Columbus Avenue as well as used a state grant to renovate the McKay Street parking garage.
The goal of the streetscape project was to attract private investment. On and surrounding North Street a number of those projects have taken place over the years as well.
Not only had the Beacon and Colonial Theater became anchors to the commercial area but Main Street Hospitality renovated the former Besse-Clark building on North Street into a boutique hotel. Allegrone Construction renovated the Howard Building at the intersection of First and Fenn Street into commercial and market-rate housing.
Allegrone is currently finishing renovating the Onota Building on North Street, with the temporary sidewalk being removed last week and windows now installed, with the same purpose. A few years ago, Scarafoni Associates renovated the former Notre Dame School into apartments.
Inevitably, the construction during each phase caused traffic disruption and access to downtown businesses — especially during the third phase in which a deeper road reconstruction was needed than in other sections. The city used display signs to tell shoppers that the stores were, in fact, open and helped direct customers to the entrances. But, with construction during the sections were widespread and eliminated parking and some access.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
Housing Secretary Edward Augustus cuts the ribbon at The First on Thursday with housing officials and Mayor Peter Marchetti, state Sen. Paul Mark and state Rep. Tricia Farley-Bouvier.
PITTSFIELD, Mass. — The holidays are here and several community members are celebrating it with the opening of two affordable housing initiatives.
"This is a day to celebrate," Hearthway CEO Eileen Peltier said during the ribbon-cutting on Thursday.
The celebration was for nearly 40 supportive permanent housing units; nine at "The First" located within the Zion Lutheran Church, and 28 on West Housatonic Street. A ceremony was held in the new Housing Resource Center on First Street, which was funded by the American Rescue Plan Act.
The apartments will be leased out by Hearthway, with ServiceNet as a partner.
The First Street location has nine studio apartments that are about 300 square feet and has a large community center. The West Housatonic Street location will have 28 studio units that range between 300 to 350 square feet. All units can be adapted to be ADA accessible.
The West Housatonic location is still under construction with the hope to have it completed by the middle of January, said Chris Wilett, Hearthway development associate.
Prior to the ribbon-cutting, public officials and community resource personnel were able to tour the two new permanent supported housing projects — West Housatonic Apartments and The First Street Apartments and Housing Resource Center.
click for more
Kyzer and Cali are both poodles. Kyzer is the male and is 7 years old, and a little bigger than his sister Cali, who is a miniature of Kyzer and 8 years old.
click for more