image description

$74 Million Wastewater Plant Upgrades Heads to City Council

By Andy McKeeveriBerkshires Staff
Print Story | Email Story
PITTSFIELD, Mass. — The mayor is asking for the authority to borrow $74 million for a major upgrade of the city's wastewater treatment center.
 
The expense has been a long time coming, starting with the city seeking to renew its National Pollutant Discharge Elimination System permit in 2005. The U.S. Environmental Protection Agency oversees those permits in an effort to keep waterways clean and had issued a permit in 2008 requiring significantly higher standards of phosphorus, aluminum treatment, and nitrogen removal.
 
"This is a very expensive and very impactful program to remove nitrogen, tertiary treatment for phosphorous, aluminum, and then we have to make other upgrades to our system associated with that in a secondary clarifier and sludge dewatering," Commissioner of Public Services and Utilities David Turocy told the City Council back in March.
 
The new standards were set under the Clean Water Act and the city's system doesn't currently conform. The city fought the standards in court but in 2009, a federal judge ruled in favor of the EPA.
 
"We exhausted all of our appeals and ultimately lost in federal court," Turocy said.
 
The city had then engaged with the engineering firm Klienfelder to design a new system. In March, the City Council authorized $4.9 million in borrowing to complete the design of the new system — adding to $1 million that had already been spent. Now, the design is apparently complete and Mayor Linda Tyer has submitted a petition asking for the authorization to borrow for the construction.
 
And she is hoping the council will act quickly. The EPA had issued a consent order setting timelines calling for the construction documents to be ready for bidding by the start of 2018 with actual construction starting this August.
 
"With that design compete we need to move forward with the construction of this project in accordance with the timeline contained in the EPA administrative order. Therefore, I would ask that you waive rule 27 so that you may discuss and vote on the order at your Jan. 23rd meeting," Tyer wrote in her petition to the City Council.
 
"A vote on the 23rd is required to ensure that the project remains on schedule. Any variation from that schedule could result in fines being levied on the city by the EPA."
 
The majority of the councilors have heard a presentation during a City Council of the Whole meeting in the spring of 2017 about the work when the administration asked for the design funds. At that point, the design was only 30 percent complete. Representatives from Klienfelder are expected to prepare an updated presentation to give on Tuesday.
 
In March, Alan Wells, of Klienfelder, told the council that the company "tried to control the costs as best as we can but it is still a large upgrade." It starts with the construction of a new tertiary treatment process and building.
 
That adds an additional level of treatment at the plant and currently, the primary systems are working fine, but the secondary systems date back to the 1970s and been pieced together over the years.
 
"The secondary clarifies are really the weak link," Wells told the council. "They are really at the end of their useful life."
 
The repairs there are need to ensure the new tertiary treatments work properly, Wells said.
 
Next, the city needs to expand the capacity of the dewatering plant. That plant helps reduce the disposal cost of sludge but with the rest of the systems being upgraded, Wells said the current equipment is too small. He said the plan is to expand the capacity, but not expand the building. And finally, there is technology to "optimize the removal of nitrogen."
 
Wells also said that while the cost is high, it is comparative to similar cities and towns that faced the same type of requirements.
 
"The price tag for this is tremendously high. It is $76 million. It is a tough number but it is what is going to be required of us," Turocy had previously said of the project.
 
Tyer said $50 million of the borrowing will be through the state's Clean Water trust fund, lowering the interest over the course of the bond. The payments on the borrowing would likely be wrapped into increases to the water and sewer bills — and thus through the water and sewer enterprise accounts.
 
The City Council had also already approved spending $8.4 million to replace primary pumps at the wastewater treatment plant.

Tags: municipal borrowing,   wastewater,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Two Men Found Guilty of Marijuana Trafficking

PITTSFIELD, Mass. — On Monday, May 6, Yebin Mai, 32 of Staten Island, NY and Dem Wu, age 52 of Staten Island, NY, were found guilty by jury of their peers in Berkshire Superior Court.
 
Yebin Mai was found guilty of two charges: Marijuana Trafficking in 100 pounds or more but less than 2,000 pounds and Witness Intimidation. Dem Wu was found guilty of Marijuana Trafficking in 100 pounds or more but less than 2,000 pounds.
 
According to a report, on July 30, 2020, State Police responded to a request for assistance from the Eversource Electric Company. The emergency dispatcher stated that two Eversource linemen were attempting to fix an electrical problem when they had a confrontation with individuals at 72 Jackson Road, Savoy. The residence belonged to Bin Huang after he purchased it in 2017 for $200,000 cash.
 
When state troopers arrived, the linemen stated that they responded to a report from a resident at 72 Jackson Road, Savoy claiming that power was fluctuating. When the linemen arrived at the house, they observed severely damaged wires and insulators leading from the roadside poles to the residence. When the Eversource linemen approached the house a man came out to meet them. The man, later identified as Yebin Mai, spoke limited English; therefore, communication between the Eversource linemen and resident became difficult. The linemen tried to explain that they would need to turn the power off to conduct a safety check of the electric meter and surrounding electrical connections. Mai became agitated. He handed the linemen an envelope filled with money later determined to be $600. The linemen attempted to return the envelope multiple times, but Mai would not take it. The linemen decided to leave the property. They called the police and waited for them to arrive, stated a report.
 
A trooper and Eversource supervisor arrived on the road at the end of 72 Jackson Road's driveway. A short time later, Mai drove down the driveway and attempted to leave in a pick-up truck with New York plates. There were two other passengers in the truck, including Dem Wu.
 
The trooper instructed Mai to stop and turn off the truck which he obeyed. All the individuals returned to the residence so the linemen could complete their inspection.
 
In a police report, the following items were observed at and around the house:
  • 4 separate electrical meters in poorly constructed boxes on the side of the house
  • Some melted wires and metal around the meter boxes (believed to be due to an excessive amount of energy being drawn through the wires)
  • Evidence of a small fire around one of the meter boxes
  • A smell of fresh grown marijuana (which grew once power was cut to the house and fans in the residence stopped running)
  • The sound of multiple fans inside the residence with no visible air ventilation system on the outside of the house
  • Windows with curtains drawn and boarded shut
  • A backyard covered in debris from a renovation, green planning pots, and large florescent light fixtures
  • Ring door cameras
  • A small path in the woods that ended in a pile of used potting soil and roots and stalks of freshly harvested marijuana plants

Additionally, Eversource reported that the monthly electric bill for 72 Jackson Road was approximately $10,000 per month, much higher than the average homeowner's bill.

The individuals on the property were questioned and ultimately allowed to leave. On July 31, 2020, Massachusetts State Police, including the State Police Detective Unit assigned to the District Attorney's Office, and a member of the DEA arrived at 72 Jackson Road to execute a search warrant. 
View Full Story

More Pittsfield Stories