North Adams School Project Awards $51M Bid

By Tammy Daniels iBerkshires Staff
Print Story | Email Story
NORTH ADAMS, Mass. — The School Building Committee has awarded the Greylock School project to Fontaine Bros. Inc. of Springfield. 
 
Mayor Jennifer Macksey said she could "breathe a little better" with a bid contract that comes in nearly $2 million under budget.
 
The committee approved a bid of $50,498,544 on Thursday night that includes two alternates — the rebuild of the Appalachian Trail kiosk and the relocation and reconstruction of the baseball field. 
 
"I will say, all in all, for us to have overall the number of bidders that we had interested in our project, and especially to receive the GC bids that we did, the team Colliers and TSKP certainly did a good job attracting people to us," she said. "But this project ... really shows the testament of the good work that Colliers and TSKP and all of you have been doing throughout this process."
 
Fontaine had the low bid between Brait Builders of Marshfield and J&J Contractors Inc. of North Billerica.
 
The project had been bid out at $52,250,000 with three alternates: moving the ballfield, the kiosk and vertical geothermal wells. 
 
Committee members asked Timothy Alix of Collier's International, the owner's project manager, about his impressions of the bidders. He was most familiar with Fontaine, having worked with the company on a half-dozen school projects and noted it was the contractor on the Mountain View Elementary School in Easthampton that the Massachusetts School Building Authority has held up as an example school. He also had some of his colleagues call on projects that he had not personally worked on. 
 
"They're a quality firm. They do a good job. The changes are reasonable and fair," he said. "If they have an issue, they'll work with you, and with an open dialog, I have only good things to say about that."
 
He has not worked with J&J but it came through the prequalification process with no red flags and Brait he'd worked with as well, and considered it the type to push to keep things moving on a project. As to the subbidders, Colliers has worked with many of them and they, too, went through the prequalification process.  
 
The geothermal heating system, being pushed by the state, is expected to be partially funded by the federal government. Initial estimates for a vertical system came in almost double the $2.4 million earmarked in federal funding from the Inflation Reduction Act. 
 
A year ago, the building committee switched to a horizontal system that will be 20 to 30 feet under the new parking lot at an estimated at $1.5 million. The vertical system was kept as an alternate in bidding at about an extra $226,000.
 
"We did include an alternate for a vertical system to kind of check, because the horizontal system was something that we haven't done before," said Jesse Saylor of TSKP Studio, the project designer. "It's a little bit newer technology for geothermal, and we weren't sure we were going to encounter bidders and a favorable pricing, even though our research was showing that it should be less expensive for this site."
 
He said the difference was in the drilling technology; rather than drilling down, the drilling will be horizontal and not disturb the surface. 
 
Committee members Benjamin Lamb and David Moresi questioned the efficacy of the horizontal system, asking if that had been followed up on.
 
"We want the system to last a really long time, we want it to be able to accommodate the full buildings operations. Is there an efficiency issue from one to another?" asked Lamb.
 
Moresi asked if Saylor had worked on any similar projects and if it had been vetted. 
 
"From our perspective, the systems are providing equivalent performance to North Adams and have similar longevity," Saylor said, adding they have been used extensively in Canada. 
 
"We were more concerned about the number of bidders that you'd have, because there's a pretty large market of vertical well drillers at this point in the state, but there aren't as many horizontal drillers," he said. 
 
Moresi wasn't convinced, saying there had been a lot of issues with bigger projects in the area that have implemented new technologies. 
 
"I mean, there's another project recently, and I asked the OPM to maybe make some phone calls and do a little due diligence," he said. "I really feel that things like this need to be vetted, because the last thing the school wants to deal with his issues."
 
Saylor said he could reach out to Williams College, which is also putting in a geothermal system for the new art museum and ran into the same problems with the aquifer that Greylock had. 
 
The vote for the bid approval included a statement for more research into the horizontal system and a recognition that a rebid of the electrical required a change order. 
 
The vote was unanimous and followed by applause, with Moresi abstaining because of his relationship to subbidder Adams Plumbing and Heating. 
 
Alix said some process issues with the bidding, including the rebid of the electric, pushed out the deadline slightly. Work is expected to start at the end of the month with completion in July 2027. 

Tags: bidding,   Greylock School Project,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Urban Legends and Cryptids Come Alive as North Adams Prepares for Mohawk Theater Haunted House

By Breanna SteeleiBerkshires Staff

NORTH ADAMS, Mass. — A spooky and scary night at the Mohawk Theater is approaching fast after local officials decorated it for their annual haunted house.

For the third year in a row the police department, fire department, City Hall, Northern Berkshire EMS, nbCC, Drury High School, American Legion, and 18 Degrees spent hundreds of hours the past few weeks setting up at the former theater.

This year's theme is Urban Legends and Cryptids, with an emphasis on local lore and giving participating groups room to create their own scenes.

Business Manager for the Department of Public Safety Meghan DeLuca showed iBerkshires the setup and what they have been working on.

When you first enter you'll notice the Hoosac Tunnel welcoming you with a train lit up and smoking. The posters on the wall were made by Drury High's digital marketing and media class will give you a sneak peak of what you may encounter when you enter the tunnel.

All of the departments chose a different theme for their space; MCLA welcomes you in detention, the American Legion is putting a twist on Red Riding Hood and the Three Little Pigs, Drury is hosting aliens and another cryptid.

"We're all in here trying to curate the whole entire space because obviously, this is an undertaking. This building is not open to the public currently. I grew up in North Adams my whole entire life until we had the opportunity three years ago to come in here, and we were trying to find a space that was going to work for the haunted house. I'd never been in here, so I think that a lot of the allure is that this is a place that you're not expecting to be able to come into," she said.

DeLuca said planning begins around April, with organizers choosing a theme, confirming which groups will participate, collecting set ideas, and determining what materials are needed. Then setup begins around mid-August, as donated materials arrive and the team builds and adjusts the layout.

View Full Story

More North Adams Stories