The culvert carrying Miller Brook into Tophet Brook along Jordan Street has collapsed. The cost to fix it has ballooned to $3.9 million.

Adams Moves Forward With Long-Delayed Miller Brook Culvert Replacement

By Sabrina DammsiBerkshires Staff
Print Story | Email Story
This image documented by the town shows how the paving was collapsing. Residents at 17-31 Jordan have been forced to find alternate parking for several years.
ADAMS, Mass. — After years of delays, funding uncertainty and temporary repairs, the town is moving forward with work on the Miller Brook culvert behind 17-31 Jordan St., with construction expected to begin in the spring.
 
The deteriorating Miller Brook culvert has been a longstanding headache for the town and nearby residents, resulting in years of parking challenges and repairs. The culvert carries Miller Brook into Tophet Brook under what had the parking lot for the apartment building. According to the town's 2021 annual report, the Miller Brook culvert collapsed in 2020. 
 
"I think it's in significantly worse condition now, where the concrete blocks have actually folded in," Town Administrator Nicholas Caccamo said.
 
At the time of the initial collapse, the town had applied for government funding to address the damage, while the Department of Public Works implemented measures, including constructing a cage to prevent large debris from clogging the system.
 
In 2025, the project faced further uncertainty as the town awaited approval from the Federal Emergency Management Agency for additional funding and a contract extension.
 
The project's estimated cost had increased from $2.2 million to $3.9 million, prompting the town to request a budget amendment, an extension of the project timeline and approval of its final design to proceed with bidding.
 
Although the town had previously secured $1.7 million in federal funding, with a $572,000 local contribution, officials reported difficulty obtaining responses from the Federal Emergency Management Agency regarding the requested approvals.
 
"This has been a long time coming for the town. My understanding it's been years. There were potential funding gaps that have been closed, and the town's worked closely through state agencies as a conduit to federal agencies to ensure that the gap funding and the contract length has been extended," Caccamo said. 
 
In July, the town issued an invitation for bids, which received eight bids that was ultimately awarded to A.J. Virgilio Construction for a total price of $1.9 million. 
 
The $1.9 million project includes removing or filling the existing 272-foot deteriorated culvert and portions of the existing channel, installing new concrete culverts, improving drainage infrastructure, and reconstructing the driveway and parking lot.
 
"The culvert has to be ordered by A.J. Virgilio. So those pieces have to be manufactured by a concrete company, and then they're going to be shipped on site and installed, so it'll be a pretty interesting project," Caccamo said. 
 
Additional work includes improvements to the adjacent diversion channel, installation of fencing, guardrails, bollards and gates, and landscaping.
 
Prior to the collapse, residents in that area used to park on the culvert. Once the work is complete, that parking will be restored allowing residents to resume off-street parking and eliminating the need for the temporary on-street parking arrangements that have caused neighborhood tensions.

Tags: culvert,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Adams to Appoint Interim Director for Greylock Glen

By Sabrina DammsiBerkshires Staff
ADAMS, Mass. — The town will have to find a new director for the Greylock Glen Outdoor Center following the departure of Daniel Doyle last week. 
 
The Selectmen appointed Doyle as executive director in August 2025. However, on Saturday, he announced his departure from the position in a post on his personal Facebook page.
 
Doyle had submitted his two weeks' notice to Town Administrator Nicholas Caccamo, with his last day in the position being Friday, Nov. 13.
 
"Presently, my office is focused on finding an immediate solution that keeps the lights on, and the doors open for the public at the Outdoor Center," Caccamo said on Monday.
 
Caccamo said he will seek ratification the appointment of Inspectional Services Administrative Assistance Wendy Robert as part-time interim director, with responsibilities limited to coordinating volunteer schedules, handling private event rental inquiries, processing invoice payments, and overseeing ongoing maintenance. The appointment will be made at Wednesday's meeting of the Selectmen, at which Doyle's letter of resignation will also be accepted. 
 
In his post, Doyle said he is grateful for the good times he had at the Glen and is more optimistic than ever that there is a path to it becoming what so many have hoped it would be. 
 
"It may not be the easiest or most obvious path, yet it's there if you're willing to bushwack a bit. I won't be holed up in the nurse's station but I'll be paying attention and lending a hand where I can. Keep the fire burning and the wheels turning … and keep in touch," he said. 
 
View Full Story

More Adams Stories