John Benzinger from Skanska presented the GMP on Monday.
PITTSFIELD,Mass. — The city and Gilbane Building Co. have settled on a guaranteed maximum price for the construction of the new Taconic High School.
The price for construction only is $97,757,373, which is equal to the project established months ago by the state. Now that the bids for the construction are in, Gilbane and the School Building Needs Commission finalized that construction budget, outlining the cost of each item and subcontracts.
"Tonight was a reaffirmation that that was number. Almost two years ago, the [Massachusetts School Building Authority] said this is the number. The City Council when they voted to send the project forward said, yes, that is the number. What we saw here tonight is all of the math that lets us back into that number, which we didn't have when the MSBA approved it," Superintendent Jason McCandless said.
The entire project is budgeted at $120.7 million. The construction was for $97.7 million and now that the bids for that have arrived, construction manager Gilbane can settle on the final price. However, there is still unknown costs such as furnishing the new school.
"Getting the building built, pretty much those bids are out, filling it up with a mixture of equipment we already have and new equipment and furniture, those bids aren't out," McCandless said
Additionally, the bids for electrical work is under protest. John Benzinger of the consulting firm Skanska said Wayne Griffin Electric Co. is challenging the low bidder. Ferguson Electric Co. bid $9,847,000 for the work while Griffin bid $10,400,000. However, Griffin says Ferguson did not fill out the bid documents correctly by not listing any subcontractors and instead only listing itself as the ones performing the work, according to Benzinger.
The city's legal team is working on the appeal now but Skanska is confident the bid will hold up.
"The second lowest bidder is saying that Ferguson didn't submit their paperwork correctly. The difference in price is $550,000 more. If we disqualify Ferguson, we'd be paying $550,000 more than we are for Ferguson," the city's Purchasing Agent Colleen Hunter-Mullett said.
If the appeal does hold up, then Benzinger said there are plans in place to cover the additional cost. The Ferguson bid is what was included in the GMP.
"The whole project budget the MSBA has approved and you have authorized is $120,799,929 and the difference between the two are fees associated with the design, FF&E which the city will have to purchase eventually, moving expenses, [owner's project manager] expenses," Benzinger said.
Under a pre-construction contract, Gilbane was already authorized to execute contracts for site work, concrete, structural steel, plumbing, windows, and masonry, Benzinger said. Monday's authorization allows Gilbane to executive contracts for the rest of construction.
"Everything was competitively bid," Benzinger said.
Also not included in the price was $950,000 for additional soil work. A mix of contaminated soils and unsuitable soils were found on the property because it was both swamp in some areas and a dumping ground for construction debris in other areas. That additional work to mitigate the contamination — and ship the soils to an approved landfill — cost $950,000. That is coming out of the city's contingency budget, which was $4.3 million to start.
The site work is "significantly complete" now. Concrete foundation work is 80 percent done, structural steel will start on Oct. 11 and precast concrete work for the structure will start on Oct. 17.
Receiving and approving that GMP is the first significant milestone in the construction process. The new school is expected to be open in 2018. While the GMP is a milestone, school officials say the construction budget had already been set twice before.
"The MSBA itself really sets a number to draw a line in the sand to say this project is going to serve this many students in this type of school. In our instance, it is a comprehensive school so it has vocational programs included. They lay out a number that their board approves and this body approves, and the City Council approved it," McCandless said.
"This project may not exceed that cost. It may not exceed that cost in anyway shape or form."
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
BVNA Nurses Raise Funds for Berkshire Bounty
PITTSFIELD, Mass. — The Massachusetts Nursing Association members of the Berkshire Visiting Nurses Association raised $650 to help with food insecurity in Berkshire County.
The nurses and health-care professionals of BVNA have given back to the community every holiday season for the last three years. The first year, they adopted a large family, raised money, bought, wrapped and delivered the gifts for the family. Last year, they sold raffle tickets and the money raised went to the charitable cause of the winner.
This year, with food insecurity as a rising issue, they chose to give to Berkshire Bounty in Great Barrington.
They sold raffle tickets for a drawing to win one of two items: A lottery ticket tree or a gift certificate tree, each worth $100. They will be giving the organization the donation this month.
Berkshire Bounty seeks to improve food security in the county through food donations from retailers and local farms; supplemental purchases of healthy foods; distribution to food sites and home deliveries; and collaborating with partners to address emergencies and improve the food system.
The Select Board signed the sale on the last of what had been known as the Bardin property Monday even as a handful of residents demanded the right to speak against the action. click for more
Police Chief Thomas Dawley will retire next month after 24 years with the Pittsfield Police Department, and the mayor will appoint his successor.
click for more
Last weekend, LaBeau raced in the Mount Zion Snocross National race in Ironwood, Mich., the first of eight races in the national circuit series.
click for more
Brown hopes to one day work in a lab, feeding their strong interest in scientific research and making a positive difference in the world.
click for more
Prior to the ribbon-cutting, public officials and community resource personnel were able to tour the two new permanent supported housing projects — West Housatonic Apartments and The First Street Apartments and Housing Resource Center.
click for more