image description
Mayor Linda Tyer had asked the council to approved the request on Tuesday.

Pittsfield Council Wants More Details on $74M Wastewater Project

By Andy McKeeveriBerkshires Staff
Print Story | Email Story
PITTSFIELD, Mass. — The City Council doesn't want to rush into making a $74 million decision.
 
Mayor Linda Tyer put forth a petition calling for the borrowing of $74 million for a massive project with the wastewater system. The city is under an administrative order from the U.S. Environmental Protection Agency holding the system to higher standards of phosphorus, aluminum treatment, and nitrogen removal. The project has been in design for about a year, coming after years of ultimately losing appeals in federal court.
 
"We did appeal several times and we lost every appeal so we are on the ropes here," Tyer told the City Council.
 
The mayor had asked the council to waive its own Rule 27, which requires a request for such a cost to go to the Finance Committee. Tyer said if it wasn't approved Tuesday night, the city could miss the construction deadline and be fined for non-compliance.
 
The City Council, however, wouldn't bite. Councilors said they didn't know enough about the project, had many questions, had no public input, and questioned the timeliness and threat of fines.
 
"Just there, $74 million is almost twice the amount of our share of the new Taconic and how long did we talk about that?" Ward 4 Councilor Christopher Connell said, warning his colleagues that the project will significantly raise the water and wastewater fees.
 
"This needs to go to Finance. It needs to go to Public Works. This is not a snap judgment. Do your job for the people you represent."
 
Councilor at Large Melissa Mazzeo said the public hasn't had a chance to hear the details and she has a number of questions. She retrieved a copy of the EPA administrative order requiring the city to make the upgrades and questioned inconsistencies between what she read there and what had been presented to the City Council about the project in the past.
 
"There are timelines but these timelines are not as set in stone as everyone is kind of alluding to," Mazzeo said.
 
Several councilors said the EPA mandated the city have "final design" completed by Aug. 1, 2017. They questioned if the city had hit that target and why was it only now coming before the council.
 
"We're not comfortable moving forward with qualifying vendors or going to bid until we have the funding plan in place," Tyer said.
 
Commissioner of Public Services and Utilities David Turocy said the city in August submitted a 60 percent design, which he said filled the requirements. Turocy said the final design had only just recently been completed.
 
Director of Finance Matthew Kerwood sketched out a timeline of the contract procurement. That timeline would have awarded the contract for the construction at the end of June, putting the city on track to hit the Aug. 1, 2018 deadline to start construction.
 
"That would give you a month and a half to get everything situated, contract signed, and all the legal work on the procurement side," Kerwood said. "There is a substantial amount of back-end work that goes into a project of this magnitude."
 
But Councilors Kevin Morandi and Donna Todd Rivers feel that the time crunch isn't the council's fault. The request and presentation, and design could have been made earlier to allow for the full subcommittee process to play out, they said. Mazzeo later said the city is currently out of compliance with the EPA's order.
 
"If they wanted us to vote on this, they could have moved a little quicker," Morandi said.
 
Both Kerwood and Tyer both said a council delay makes it more difficult administratively, but that they will do their best to continue to hit the EPA's deadlines.
 
"We will do our best to respect your desires and we will do our best to accelerate if we have to," Tyer said.
 
The project isn't quite a brand-new project but the councilors hadn't seen anything regarding it in about a year. Last March, the City Council authorized borrowing to complete the design and were given a presentation from consultant Klienfelder. 
 
"We presented a request for funding for the design work, which was approved and completed. Now we are moving to the construction phase and that is what this is for," Tyer said.
 
The expenses date back to the city's attempt to renew its National Pollutant Discharge Elimination System permit in 2005. The U.S. Environmental Protection Agency oversees those permits in an effort to keep waterways clean and had issued a permit in 2008 requiring significantly higher standards of phosphorus, aluminum treatment, and nitrogen removal.
 
"I'd hate to hold anything up," Councilor Earl Persip said, but, "I'm not comfortable taking a vote without any more information."
 
The council sent the request to the Finance Committee for thorough vetting after rejecting to waive Rule 27.

Tags: council rules,   municipal borrowing,   public works,   wastewater,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Companion Corner: Cali and Kyzer at The Berkshire Humane Society

By Breanna SteeleiBerkshires Staff

PITTSFIELD, Mass. — There's a bonded dog pair awaiting a new family at the Berkshire Humane Society.

Kyzer and Cali are both poodles. Kyzer is the male and is 7 years old, a quite a bit bigger than his sister Cali, who is a miniature of Kyzer and 8 years old.

Canine adoption counselor Rhonda Cyr introduced us to the two.

"They came from a household that couldn't hold on to them, and it sounds like they may have been abandoned by their previous owner with somebody else, and so they came to us looking for a new home," she said.

The two love to be around you and snuggle. But both are very happy dogs.

"Kyzer is 7 years old, and his personality is that he kind of wants to be in everything. He's very loving, very snuggly, as you can tell. And Callie here, she's 8 years old, and she is kind of like the life of the party," said Cyr. "She wants to tell you everything about her day, and she's a little bit of a little ham."

The two are considered seniors and really like soft treats as Cali just had a few teeth removed and Kyzer has a tooth procedure coming up.

"Currently, they really like soft treats, because they are both on the senior side of things. So they have had some dental work, so they are really in need of something softer. They are not big chewers at this age, really, their main focus right now is just really socializing and cuddling," Cyr said.

The two would love a quiet home with someone who wants to snuggle. They shouldn't go to a home with bigger dogs but if you have a dog, you can bring them in for a visitation with the poodles to see if they will get along. Cats will be fine and the preference is for older and more responsible children so that the pups don't get hurt, as they are senior citizens.

"The perfect home for them would be a quiet home that's not too active. Like I said, they're very social, so they could handle some visitors," she said. "They're very friendly, but I don't think that they would really enjoy any other dogs in the home."

Poodles need to be regularly groomed, and the prospective adopter will have to keep an eye on their health. Kyzer has a heart murmur that needs to be monitored. This doesn't mean he is in bad health, as he could live a perfectly normal life, but he will need to be checked by a veterinary specialist routinely.

"Ideally, he would go to a home that could provide further health care with a specialist in cardiac care. And you know, he could very well live out the rest of his life comfortably and happy," Cyr said. "We just don't have all that information at the moment, but I think that you know the way he's going right now. He's got a good spirit, and he seems to be pretty happy."

The shelter is hoping the to get them a home for the holidays.

"We would love to get them a home in time for the holidays. They've been here since the eighth of November, and they're really, really looking as much as the staff loves them here, we're really looking to get them into a home and somewhere nice and cozy so they can spend the rest of their life together," she said.

View Full Story

More Pittsfield Stories