image description
The lettering on the front of the building was installed on Monday.
image description
image description
image description
image description
image description
image description
image description
image description
image description

Construction Wrapping Up at New Taconic High School

By Andy McKeeveriBerkshires Staff
Print Story | Email Story

A new handicapped accessible walkway from the school to the track was paved.
PITTSFIELD, Mass. — For all intents and purposes, the new Taconic High School building is done.
 
A temporary certificate of occupancy has been granted and administrative staff has been working out of the new $120.8 million building.
 
The teacher's supplies sit in boxes in each room and next week they'll start unpacking and setting up the classrooms. The staff members had been asked to pack up before they left for the summer and a moving company transported the boxes from the old classrooms to the new.
 
The building has been under construction for two years, kicking off in the spring of 2016, and this October a ribbon cutting ceremony is planned.
 
However, there is still some work being done on site. The auditorium and the shops are still considered construction zones. In the auditorium, the final bit of wiring is being done along with a back wall being installed. Soon, seats and aisle carpet will be laid. 
 
Electricians have been putting in extra days in this final month before school starts to finish up in the shops and the work left in some classes. In a week or so, the plants for the green roofs are expected to be placed.
 
There is still furniture and equipment expected to arrive later this week and into next week. The heating and cooling system is expected to be commissioned soon and health and building inspectors are expected to give their approval on the culinary kitchen.
 
Once the final pieces of the project are done in time for the students to arrive in late August, there will still be some punch list items and cleaning to be done. 
 
Meanwhile, deconstruction of the original Taconic has already begun. A fence surrounds the building and inside asbestos abatement and some internal demolition underway. Once that building is demolished, workers will install playing fields in that space. 
 
At the new Taconic, the landscaping around the building and parking lots are just about complete. That includes a new walkway to the track. In a separate project, the track and fencing are expected to be repairs and a community effort including donated labor and material from the construction companies working on the project is going to install new dugouts for the baseball field.
 
The new 246,520 square feet building, set to accommodate 920 students, broke ground in 2016. The site had been a small parking lot and rocky terrain. It has since been transformed into a new school. Skanska USA, architects Drummey Rosane Anderson Inc., and Gilbane Construction have been overseeing the work.
 
iBerkshires has been regularly following the project. Check out our photos from a number of tours of the site below. The newest photos are first and then the rest are chronological. 


Tags: school project,   Taconic High,   Taconic school project,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Dalton Board Signs Off on Land Sale Over Residents' Objections

By Sabrina DammsiBerkshires Staff

Residents demanded the right to speak but the agenda did not include public comment. Amy Musante holds a sign saying the town now as '$20,000 less for a police station.'
DALTON, Mass. — The Select Board signed the sale on the last of what had been known as the Bardin property Monday even as a handful of residents demanded the right to speak against the action. 
 
The quitclaim deed transfers the nine acres to Thomas and Esther Balardini, who purchased the two other parcels in Dalton. They were the third-highest bidders at $31,500. Despite this, the board awarded them the land in an effort to keep the property intact.
 
"It's going to be an ongoing battle but one I think that has to be fought [because of] the disregard for the taxpayers," said Dicken Crane, the high bidder at $51,510.
 
"If it was personal I would let it go, but this affects everyone and backing down is not in my nature." 
 
Crane had appealed to the board to accept his bid during two previous meetings. He and others opposed to accepting the lower bid say it cost the town $20,000. After the meeting, Crane said he will be filing a lawsuit and has a citizen's petition for the next town meeting with over 100 signatures. 
 
Three members of the board — Chair Robert Bishop Jr., John Boyle, and Marc Strout — attended the 10-minute meeting. Members Anthony Pagliarulo and Daniel Esko previously expressed their disapproval of the sale to the Balardinis. 
 
Pagliarulo voted against the sale but did sign the purchase-and-sale agreement earlier this month. His reasoning was the explanation by the town attorney during an executive session that, unlike procurement, where the board is required to accept the lowest bid for services, it does have some discretion when it comes to accepting bids in this instance.
 
View Full Story

More Pittsfield Stories