image description
Paving began last week on the Ashuwillticook Rail Trail's extension into Pittsfield was paved week and the project is said to be about 80 percent completed.

Pittsfield Ashuwillticook Rail Trail Extension 80 Percent Complete

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

PITTSFIELD, Mass. — Paving began last week on the Ashuwillticook Rail Trail's extension into Pittsfield.  It was paved in the week and the project is said to be about 80 percent completed.

The state has given a formal completion date of May 2022.

"The project is well underway, final paving actually happened earlier this week on the trail, so we are nearing completion," Park, Open Space, and Natural Resource Program Manager James McGrath told the Conservation Commission on Thursday.

"The completion date that has been established by the state is in May of 2022. But substantial components of the project have been completed."

The 1.56-mile extension will run south from the vicinity of the mall Connector Road to Crane Avenue. The trail will be a 10-feet wide, paved, shared-use path that is part of the trail system that currently runs nearly 13 miles through Lanesborough to Lime Street in Adams.

The Pittsfield leg travels along Route 8 for several hundred feet and then around the boundaries of Unistress Construction yard. It then goes back up to the former Housatonic Railroad rail bed and at that point stays on the old rail bed straight down to Crane Avenue.

It comes out at John's Building Supply at 1 Crane Ave. and there are plans for a new parking lot and restrooms constructed on the southern side of the street.  

McGrath approached the Conservation Commission representing the Department of Public Services to request a three-year extension of the Order of Conditions for activities associated with the bike trail.


He confirmed there are replication areas and plantings that have ongoing monitoring.

The panel unanimously voted to extend the Order of Conditions to Oct. 31, 2024.

This trail extension project is the result of many years of planning for a bike and pedestrian trail in Pittsfield that uses the former Housatonic Railroad corridor. The construction of this leg began in late 2020. 

It is the northern section of an overall city plan that continues the trail south through Pittsfield to Lenox and eventually through the rest of Berkshire County. A leg in Williamstown is currently under construction and a trail through North Adams is still in the planning stages.

The extension has been in the works for almost a decade. In 2012, the city had made a pitch for construction funding but did not secure it.

The state then followed shortly after with a $2.5 million allocation through the Congestion Mitigation and Air Quality Improvement program for it.

The construction bid price for the new extension was $2,249,421.85 and was awarded to Maximilian Industries of Pittsfield in the fall of 2020.


Tags: Ashuwillticook Rail Trail,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Rip City 14U Team Wins N.Y. Tournament

iBerkshires.com Sports
CORTLAND, N.Y. -- Ryker Williams went 3-for-3 with four runs batted in Sunday to lead the Rip City 14-and-under travel baseball team to a 17-3 win over the DP Canes in the championship game of the Perfect Game tournament on Sunday.
 
Rip City went 1-1 in pool play on Saturday before winning the tournament semi-final, 9-0, over the Northeast Pride Prestige on Sunday behind a combined two-hitter from pitchers Andrew Scalise and Lador Lawson.
 
Roman Raifstanger went 2-for-3 with a triple and a double against Northeast.
 
"In the championship, our guys came out on fire and put up a quick nine runs in the top of the 1st and never looked back," Rip City coach Rick Paris said. "It was a great team effort. The hustle and effort was absolutely fun to watch. These boys are growing by leaps and bounds from where the were at in the summer."
View Full Story

More Pittsfield Stories