image description
Police Chief Robert Derksen pointed out deficiencies with the building during Thursday's tour, including its size, lack of privacy, mold presence, the lack of insulation and the lack of proper air conditioning.
image description
The station's locker room, as well as its break area and storage space.
image description
The station's interview room.

Lanesborough Police Station Committee Tours Current Police Building

By Brian RhodesiBerkshires Staff
Print Story | Email Story

LANESBOROUGH, Mass. — After establishing goals for the estimated $3.8 million new police building project at its first meeting on Tuesday, the newly-formed Police Station Committee conducted a tour of the current police building to examine its many issues. 

 

Police Chief Robert Derksen pointed out several deficiencies with the structure, including its size, lack of privacy, mold presence, and the lack of insulation and proper air conditioning. Many of these issues, he said, are due to the age of the structure. 

 

"It's been a lot of things over the years. I think it's from around 1827," he said. "It was a school; it was an ambulance garage." 

 

The estimated $3.8 million price for the new station came in February from Jacunski & Humes Architects, which has created two previous plans for the structure. The committee will be meeting with Humes to discuss the proposed designs at next week's meeting. 

 

Board of Selectmen Chair John Goerlach was present for the walkthrough and the discussion by the committee that followed. He said state Rep. John Barrett III recently visited the station. 

 

"He's going to try and work on a grant," Goerlach said. 

 

Committee Chair Kristen Tool said seeing the current station was helpful and is confident they can find grant funding for the new building. 

 

"[The new station] is going to meet the needs of the community," she said. "This building not only does not meet the needs of the community, it's not safe for community members to go in there. It does not meet the needs of our officers."

 

Committee member Bill Calderwood suggested several ways to lower the new station's $3.8 million estimated cost. He said some cost-saving measures are needed if the committee wants to decrease the price. 

 

"You can't just cross out one line item. You got to get 5 percent of this one and 4 percent of that one and 10 percent out of this one. You got to make some concessions," he said. 

 

The committee expects construction to begin within the next 18 months if it keeps pace with its goals. Town Administrator Joshua Lang said the committee must conduct a request for proposals for a project manager. 

 

Derksen acknowledged that cost limits what is possible with the new station but said if the cost was not an issue, he would opt for a training room in the new station. He previously spoke to the Finance Committee about new state training regulations for officers and said hosting training would benefit the town. 

 

Former Police Chief Tim Sorrell said there is no similar training facility anywhere in the county. 

 

"There is no dedicated training room in the county for anything," Sorrell said. "We've been so desperate we've used Berkshire Hills, we use the armory . . . you're scraping to find locations." 

 

The committee also discussed the need for a temporary station while construction of the new station is ongoing, proposing several potential solutions. Derksen said he is willing to consider any option.

 

"I'm open to everything," he said. "I would love to be able to rent a place in town if I have to be in a temporary location." 

 

The committee will discuss potential locations for a temporary facility again at its meeting next week. The committee will hold a joint meeting with the Board of Selectmen on Monday.


Tags: police station,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

PEDA Site 9 Preparation, Member Retirement

By Breanna SteeleiBerkshires Staff

PITTSFIELD, Mass. — The redevelopment of Site 9 for mixed-use in the William Stanley Business Park is set to take off. 

Edward Weagle, principal geologist at Roux Associates, gave an update on the yearlong work to the Pittsfield Economic Development Authority last week.

"It's been a real pleasure for me to work on a project like this," he said. "This is kind of like a project of a career of a lifetime for me, and I'm very pleased to see that we're just at the finish line right now. My understanding is that all the documents are in front of the commissioner, waiting for her to sign off."

Mill Town Capital is planning to develop a mixed-use building that includes housing on the site. Roux, headquartered in Islandia, N.Y., was hired assist with obtaining grant financing, regulatory permitting, and regulatory approvals to aid in preparing the 16.5-acre site for redevelopment. Approximately 25,000 cubic yards of concrete slabs, foundations, and pavements were removed from the former GE site. 

Once the documents are signed off, PEDA can begin the work of transferring 4.7 acres to Mill Town. Weagle said the closing on this project will make it easier to work on the other parcels and that he's looking forward to working on Sites 7 and 8.

PEDA received a $500,000 Site Readiness Program grant last year from MassDevelopment for Sites 7 and Site 8. The approximately 3-acre sites are across Woodlawn Avenue from Site 9 and border Kellogg Street. 

In other news, the state Department of Transportation has rented the east side of the parking lot for CDL (Commercial Driver's License) training. This is an annual lease that began in September and will bring in $37,200 in revenue.

Lastly, the meeting concluded with congratulations to Maurice "Mick" Callahan Jr. on his retirement.

Callahan is a former chair and a founding member of PEDA, dating back to when the board was established in the 1990s. He has also served on a number of civic and community boards and has volunteered for many organizations in the Berkshires. He is the president of M. Callahan Inc. 

"The one thing that's been a common denominator back is that you've always put others before yourself. You've served others well. You've been a mentor to two generations of Denmarks, and I'm sure many generations of other families and people within this city," said board Chair Jonathan Denmark. "We can never say thank you enough, but thank you for your services, for the creation of this board, your service to the city of Pittsfield, and to all the communities that you've represented and enjoy retirement." 

"It wasn't always easy to be in the position that you were in Mick, but you handled it with so much grace, always respecting this community, bringing pride to our community," member Linda Clairmont said. "I could not have accomplished many of the things I did, especially here for this business part, without you all of the Economic Development discussions that we had really informed my thinking, and I'm so grateful."

Callahan left the team with a message as this was his final meeting, but said he is always reachable if needed.

"I also have to say that a lot of great people sat around this table and other tables before the current board, and the time that I had with Pam [Green] and Mike [Filpi] sticking around, the leadership of this mayor [board member Linda Tyer], and it really, it was always great synergy," he said.

"So don't be afraid to embrace change. And you know, you got a business model. It's been around long time. Shake it up. Take a good look at it, figure out where it needs to go, and you're lucky to have leadership that you have here."

View Full Story

More Pittsfield Stories