Pittsfield Street Improvement Project Schedule
![]() |
PITTSFIELD, Mass. – Please be advised of the following work that will take place July 11-15, as part of the city of Pittsfield’s 2022 Street Improvement Project.
Monday, July 11 and Tuesday, July 12: milling on Bushey Road, Alfred Drive, Pembroke Avenue, and Longview Terrace.
Wednesday, July 13 and Thursday, July 14: first application of blacktop on the locations above.
Friday, July 15: sidewalk paving on Donovan Street, curbing on Howard Street.
Except for Donovan Street, all other on-street parking is prohibited during this work between the hours of 6 a.m.-6 p.m. Please note there may be impacts to traffic.
The schedule is subject to change based on weather conditions. The city of Pittsfield thanks you for your patience during this time.