image description
Initial estimates for a new fire station in Williamstown came in at just under $18 million.

Williamstown Fire Station Cost Pegged at $18M

By Stephen DravisiBerkshires Staff
Print Story | Email Story
WILLIAMSTOWN, Mass. — The initial estimate for a new fire station came in at just below $18 million, the fire district's Building Committee learned on Wednesday.
 
But there are a number of unknowns at this stage of the design process, and the committee noted at least one opportunity Wednesday to trim the budget by choosing a gas-fired HVAC system over an electric-powered variable refrigerant flow system.
 
With the more energy-efficient electric VRF system included, estimator Miyakoda Consulting of Raynham pegged the building cost at $17,909,261 for a cost of $658.07 per square foot, assuming a summer 2023 construction start.
 
If the district ultimately goes with a gas-fired HVAC unit, the upfront cost of construction could come down by about $500,000, according to Miyakoda's estimate. But, Building Committee member Don Dubendorf noted, the life-cycle costs of operating the station would change depending on the mechanical system.
 
Ken Romeo of Colliers Engineering and Design, the district's owner's project manager, said he could come up with a life-cycle cost comparison in two or three weeks for the Building Committee to consider.
 
It will be at least six weeks before the committee has more info on one of the biggest unknowns embedded in that $18 million estimate.
 
EDM's Tim Eagles and Chris Wante, who briefed the Building Committee on Wednesday, said much of a 13 percent "design contingency" in the initial estimate was due to the lack of complete geotechnical studies for the Main Street (Route 2) property where the district hopes to build a new station.
 
"The biggest uncertainty is the site and soil conditions," Wante said. "Once we get the final geotech report, it will help us know what kind of site prep we need. Are there materials out there that are unknown in terms of unsuitability?"
 
In part due to the unknown cost of site work, Miyakoda built in a $1.7 million design contingency.
 
"A design contingency is the estimator's way of saying, 'We don't have all the design information yet,'" Eagles said. "Thirteen percent is a pretty healthy number."
 
Miyakoda was hired by EDM to estimate the cost of the project. The Prudential Committee, which governs the fire district and appointed the Building Committee, is considering, on Romeo's advice, hiring a second estimator to provide another opinion on projected costs at future stages of the design process.
 
The current design of the building calls for about 27,215 square feet in two stories with an elevator and six bays for fire trucks with four "drive through" bays with access in the front and rear so trucks don't need to back into the station as they do at the district's current cramped and out-of-date facility on Water Street.
 
Romeo pointed out to the committee that the estimate it saw on Wednesday referred only to the building itself and the pavement around the structure. It did not include elements like a new radio tower and solar panels, which the district is planning in an effort to make the new station a net-zero building and eligible for green building certification through one of the industry's certifying agencies.
 
Wednesday's meeting at the Water Street station was the first time any of the Building Committee members saw the numbers, but members did query the architects on some of the assumptions behind them as well as what other costs might fall outside the building estimate.
 
One so-called "soft cost" that was not factored into Miyakoda's estimate was building permitting.
 
Dubendorf asked whether the fire district had a commitment from the town about its intention on the permitting question. He recalled that the issue was a point of contention the last time a municipal entity apart from town government did a building project in town.
 
"I don't want to let that slip," Dubendorf said. "We should have a conversation with [Town Manager Robert Menicocci]. It became a public controversy with the school, and we don't want to let that happen again."
 
In addition to all the detail questions, Dubendorf also asked Romeo and the project's three architects – Wante, Eagles and Bob Mitchell of Voorheesville, N.Y.,'s Mitchell Associates – for their impression of the bottom line in the estimate.
 
"This does not surprise us," Eagles said.
 
"I don't think it's going to get better," Mitchell said. "This is the new reality of building."

Tags: fire station,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Williamstown Fire District Dedicates New Station

By Stephen DravisiBerkshires Staff

Chief Jeffrey Dias recognizes firefighter Alexandra Riggs, who will graduate from Williams College next week. See more photos here.
WILLIAMSTOWN, Mass. — The Massachusetts fire marshal came to town Saturday to congratulate the local Fire District and the taxpayers of Williamstown for the "amazing" station they have built on Main Street.
 
"I travel around the state, and I've seen hundreds of firehouses around the state — some great, some not so great," Fire Marshal Jon Davine told a crowd gathered outside the station for its dedication. "And I think we saw what the previous station here was in Williamstown. I'll tell you, especially in Western Massachusetts, we have a really big problem with deteriorating firehouses throughout Western Mass. These buildings are collapsing around our firefighters.
 
"And, as the marshal, it's my job to advocate for the departments for more funding. We've been working with our state reps and local reps and the fire chiefs association, trying to come up with different funding streams, so that we can help these departments build new stations, do better, safer stations, so that they have the equipment and the building they deserve to do their job safely."
 
The chair of the Prudential Committee, which governs the Fire District, and the chief of the department both thanked Williamstown residents for the 2023 special district meeting vote that paved the way for the station that went into operation earlier this year.
 
"It's an honor and a privilege to join you today as we celebrate this grand opening of the new firehouse," Chief Jeffrey Dias said. "This facility is so much more than a building that houses fire trucks. It stands as a symbol of our community's commitment to safety, preparedness and public service. It's a place where our members will maintain our equipment. They will learn about our craft. They'll share meals and, yes, from time to time, they're going to share sorrow.
 
"This isn't a fire station. This is a firehouse. And people have heard me say this a million times already. And it houses the very best second family that one could imagine."
 
Dias was joined at the podium set up in the parking lot for the noon ceremony by Prudential Committee Chair David Moresi, state Rep. John Barrett III and the the Rev. William F. Cyr, who gave an invocation.
 
View Full Story

More Williamstown Stories