image description
Initial estimates for a new fire station in Williamstown came in at just under $18 million.

Williamstown Fire Station Cost Pegged at $18M

By Stephen DravisiBerkshires Staff
Print Story | Email Story
WILLIAMSTOWN, Mass. — The initial estimate for a new fire station came in at just below $18 million, the fire district's Building Committee learned on Wednesday.
 
But there are a number of unknowns at this stage of the design process, and the committee noted at least one opportunity Wednesday to trim the budget by choosing a gas-fired HVAC system over an electric-powered variable refrigerant flow system.
 
With the more energy-efficient electric VRF system included, estimator Miyakoda Consulting of Raynham pegged the building cost at $17,909,261 for a cost of $658.07 per square foot, assuming a summer 2023 construction start.
 
If the district ultimately goes with a gas-fired HVAC unit, the upfront cost of construction could come down by about $500,000, according to Miyakoda's estimate. But, Building Committee member Don Dubendorf noted, the life-cycle costs of operating the station would change depending on the mechanical system.
 
Ken Romeo of Colliers Engineering and Design, the district's owner's project manager, said he could come up with a life-cycle cost comparison in two or three weeks for the Building Committee to consider.
 
It will be at least six weeks before the committee has more info on one of the biggest unknowns embedded in that $18 million estimate.
 
EDM's Tim Eagles and Chris Wante, who briefed the Building Committee on Wednesday, said much of a 13 percent "design contingency" in the initial estimate was due to the lack of complete geotechnical studies for the Main Street (Route 2) property where the district hopes to build a new station.
 
"The biggest uncertainty is the site and soil conditions," Wante said. "Once we get the final geotech report, it will help us know what kind of site prep we need. Are there materials out there that are unknown in terms of unsuitability?"
 
In part due to the unknown cost of site work, Miyakoda built in a $1.7 million design contingency.
 
"A design contingency is the estimator's way of saying, 'We don't have all the design information yet,'" Eagles said. "Thirteen percent is a pretty healthy number."
 
Miyakoda was hired by EDM to estimate the cost of the project. The Prudential Committee, which governs the fire district and appointed the Building Committee, is considering, on Romeo's advice, hiring a second estimator to provide another opinion on projected costs at future stages of the design process.
 
The current design of the building calls for about 27,215 square feet in two stories with an elevator and six bays for fire trucks with four "drive through" bays with access in the front and rear so trucks don't need to back into the station as they do at the district's current cramped and out-of-date facility on Water Street.
 
Romeo pointed out to the committee that the estimate it saw on Wednesday referred only to the building itself and the pavement around the structure. It did not include elements like a new radio tower and solar panels, which the district is planning in an effort to make the new station a net-zero building and eligible for green building certification through one of the industry's certifying agencies.
 
Wednesday's meeting at the Water Street station was the first time any of the Building Committee members saw the numbers, but members did query the architects on some of the assumptions behind them as well as what other costs might fall outside the building estimate.
 
One so-called "soft cost" that was not factored into Miyakoda's estimate was building permitting.
 
Dubendorf asked whether the fire district had a commitment from the town about its intention on the permitting question. He recalled that the issue was a point of contention the last time a municipal entity apart from town government did a building project in town.
 
"I don't want to let that slip," Dubendorf said. "We should have a conversation with [Town Manager Robert Menicocci]. It became a public controversy with the school, and we don't want to let that happen again."
 
In addition to all the detail questions, Dubendorf also asked Romeo and the project's three architects – Wante, Eagles and Bob Mitchell of Voorheesville, N.Y.,'s Mitchell Associates – for their impression of the bottom line in the estimate.
 
"This does not surprise us," Eagles said.
 
"I don't think it's going to get better," Mitchell said. "This is the new reality of building."

Tags: fire station,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

2025 Year in Sports: Mount Greylock Girls Track Was County's Top Story

By Stephen DravisiBerkshires Staff
Mount Greylock Regional School did not need an on-campus track to be a powerhouse.
 
But it did not hurt.
 
In the same spring that it held its first meets on its new eight-lane track, Mount Greylock won its second straight Division 6 State Championship to become the story of the year in high school athletics in Berkshire County.
 
"It meant so much this year to be able to come and compete on our own track and have people come here – especially having Western Mass here, it's such a big meet,"Mounties standout Katherine Goss said at the regional meet in late May. "It's nice to win on our own track.”
 
A week later at the other end of the commonwealth, Goss placed second in the triple jump and 100-meter hurdles and third in the 400 hurdles to help the Mounties finish nearly five points ahead of the field.
 
Her teammates Josephine Bay, Cornelia Swabey, Brenna Lopez and Vera de Jong ran circles around the competition with a nine-second win in the 4-by-800 relay. And the Mounties placed second in the 4-by-400 relay while picking up a third-place showing from Nora Lopez in the javelin.
 
Mount Greylock's girls won a third straight Western Mass Championship on the day the school's boys team claimed a fourth straight title. At states, the Mounties finished fifth in Division 6.
 
View Full Story

More Williamstown Stories