Pittsfield Street improvements Oct. 3 to 7

Print Story | Email Story
PITTSFIELD, Mass. — Please be advised of the following work that will take place Oct. 3 to 7, as part of the city of Pittsfield’s 2022 Street Improvement Project.
 
Monday, Oct. 3: curbing on Federico Drive.
 
Tuesday, Oct. 4: finish pave on Valentine Road.
 
Wednesday, Oct. 5: finish pave on New West Street, Federico Drive, and Southern Avenue.
 
Thursday, Oct. 6 and Friday, Oct. 7: paving Tamarack Road (one-way traffic from Bousquet to Barker Road).
 
On-street parking is prohibited during this work between the hours of 6 a.m. and 6 p.m. The schedule is subject to change based on weather conditions. The city of Pittsfield thanks you for your patience during this time.

Tags: street improvements,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Dalton Planning Board OKs Gravel Company Permit

By Sabrina DammsiBerkshires Staff
DALTON, Mass. — The Planning Board approved the renewal of Nichols Sand and Gravel's special permit for earth removal. 
 
The company, located at 190 Cleveland Road, operates a gravel pit there. 
 
The hours of operation will remain 7 to 4 p.m. The commission approved owner Paul Nichols' request to allow trucks to depart the property in either direction. 
 
Nichols has to apply for renewal of the special permit every year. The previous permit required the truck to exit the property to the right.
 
It makes more sense to go left if truck drivers have to go to the Pittsfield area, Nichols said. He has talked to the residents in the area and they are agreeable to the change. 
 
Former residents requested this stipulation nearly 16 years ago to reduce the number of trucks using the residential street to avoid disturbing the quality of life and neighborhood. 
 
There weren't any residents present during the meeting who expressed concerns regarding this change.
 
View Full Story