Adams Approves Extra Wastewater Treatment Plant Funds

By Brian RhodesiBerkshires Staff
Print Story | Email Story

ADAMS, Mass. — Town meeting members at Tuesday's special town meeting approved an additional $2.37 million in funding for improvements to the wastewater treatment plant. 

 

Members supported the funds 95-4, in addition to approving the three other warrant articles with little discussion. Town meeting gave the OK to just more than $5 million for the plant in 2021. 

 

Town Administrator Jay Green explained the only bid for the project came in over this amount, necessitating the extra borrowing. 

 

"The estimate was a little over $5 million, then a year later, in the bidding process, same scope, with inflation it went up to $6.5 million. That's approximately $1.4 million over estimate," he said. "The state requires that you add a 5 percent contingencies, so that's [another] $325,000 ... when you take the construction service cost of $597,000 and you take the one bid that we got a year after it was estimated at $1.4 million, that comes up to $2.3 million that you have in front of you tonight." 

 

The total cost of the project is an estimated $7.42 million. Construction is already ongoing, as the project went out to bid earlier in the year.

 

Green said the plant can handle between 10 and 12 million gallons of wastewater flow a day, while the town only currently creates about 2.5 million. He said this should allow the town to operate the plant while keeping up with needed maintenance. 

 

"These upgrades are structural. They're electrical. We're handling things that weren't done in the 2005 upgrade. They're doing some things that, what needed to be done in 2005, now are being done," Green said. "Whether we see it, I don't think so. But this creates redundancy and allows for much better preventative maintenance. 

 

Selectman Joseph Nowak asked if the bond would prevent the town from getting any future grant funding for the project. Green said he was unsure but felt the town was getting the best deal possible. He also noted that the Adams expects to receive $378,713 in ARPA loan forgiveness and $499,901 in disadvantaged community loan forgiveness toward the project. 

 

"That's why I say that $7.4 million is the total project cost. That's what the contractor gets, part of that goes to Tighe & Bond, the engineering firm. Our debt service will not be based on $7.4 million," Green said. 

 

The Board of Selectmen approved the borrowing for the project at a meeting earlier this month. 

 

Article 2 appropriates $15,000 from Cemetery, Parks and Grounds' Master Plan account to its capital account. The funds, appropriated in 2016, were leftover for a project that is now complete.

 

Article 3 releases free cash from two projects that had leftover funds. The first, for a water meter replacement, totals $9,583.04 and the second, for equipment in the assessor's office, totals $8,696.74.

 

Article 4 authorizes the Board of Selectmen to accept an easement to install drainage lines from lower Linden Street to Commercial Street. The area has been prone to flooding with the current drainage system, and the easement will come at no cost to the town.

 

The new drainage system has already been designed and engineered by Hill Engineers.

 

At the end of the meeting, town meeting member Bruce Shepley thanked the Board of Selectmen and town staff for their work.

 

"I would just like, on behalf of myself, to say thank you very much. It's encouraging. We're seeing an influx of good things happening here in Adams," he said.


Tags: special town meeting,   wastewater,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

After More Than a Century, Heating Failure Puts Adams Turners' Future at Risk

By Sabrina DammsiBerkshires Staff
ADAMS, Mass. — For more than a century, generations have gathered for dances, community gatherings and bowling at Turn Hall, but that longtime tradition is now in jeopardy after the building's aging heating system failed.
 
The Adams community is known for rallying behind local people and organizations in times of need, and now Adams Turners is asking for that same support said Gail Burda, the group's financial secretary.  
 
The boiler, referred to as "the Beast" by board members, is as old as the building itself, which was constructed in 1902. It started out burning coal, was later switched to oil and then to gas President Virginia Fuller said. 
 
For several years, the nonprofit social club, a 501(c)7, has struggled with the aging system, with members periodically checking on it throughout the day during the winter to ensure it was still operating, she said. 
 
Now, "the Beast" has reached the end of its life but the Adams Turners don't have the funding to replace it, prompting them to establish a GoFundMe. 
 
At the time of writing, the GoFundMe has raised $1,750 and members have donated more than $2,500 toward the $30,000 needed to secure an additional $25,000 grant and $25,000 loan from American Turners, the national organization under which the club operates.
 
The nonprofit hopes to hire a contractor to install a multi-zone hydronic system, a project estimated to cost $81,443. The work would include new heating systems for the apartment, bar area, gym and bowling alley, along with new baseboards, gas lines, permits and other necessary fittings.
 
View Full Story

More Adams Stories