Adams Approves Extra Wastewater Treatment Plant Funds

By Brian RhodesiBerkshires Staff
Print Story | Email Story

ADAMS, Mass. — Town meeting members at Tuesday's special town meeting approved an additional $2.37 million in funding for improvements to the wastewater treatment plant. 

 

Members supported the funds 95-4, in addition to approving the three other warrant articles with little discussion. Town meeting gave the OK to just more than $5 million for the plant in 2021. 

 

Town Administrator Jay Green explained the only bid for the project came in over this amount, necessitating the extra borrowing. 

 

"The estimate was a little over $5 million, then a year later, in the bidding process, same scope, with inflation it went up to $6.5 million. That's approximately $1.4 million over estimate," he said. "The state requires that you add a 5 percent contingencies, so that's [another] $325,000 ... when you take the construction service cost of $597,000 and you take the one bid that we got a year after it was estimated at $1.4 million, that comes up to $2.3 million that you have in front of you tonight." 

 

The total cost of the project is an estimated $7.42 million. Construction is already ongoing, as the project went out to bid earlier in the year.

 

Green said the plant can handle between 10 and 12 million gallons of wastewater flow a day, while the town only currently creates about 2.5 million. He said this should allow the town to operate the plant while keeping up with needed maintenance. 

 

"These upgrades are structural. They're electrical. We're handling things that weren't done in the 2005 upgrade. They're doing some things that, what needed to be done in 2005, now are being done," Green said. "Whether we see it, I don't think so. But this creates redundancy and allows for much better preventative maintenance. 

 

Selectman Joseph Nowak asked if the bond would prevent the town from getting any future grant funding for the project. Green said he was unsure but felt the town was getting the best deal possible. He also noted that the Adams expects to receive $378,713 in ARPA loan forgiveness and $499,901 in disadvantaged community loan forgiveness toward the project. 

 

"That's why I say that $7.4 million is the total project cost. That's what the contractor gets, part of that goes to Tighe & Bond, the engineering firm. Our debt service will not be based on $7.4 million," Green said. 

 

The Board of Selectmen approved the borrowing for the project at a meeting earlier this month

 

Article 2 appropriates $15,000 from Cemetery, Parks and Grounds' Master Plan account to its capital account. The funds, appropriated in 2016, were leftover for a project that is now complete.

 

Article 3 releases free cash from two projects that had leftover funds. The first, for a water meter replacement, totals $9,583.04 and the second, for equipment in the assessor's office, totals $8,696.74.

 

Article 4 authorizes the Board of Selectmen to accept an easement to install drainage lines from lower Linden Street to Commercial Street. The area has been prone to flooding with the current drainage system, and the easement will come at no cost to the town.

 

The new drainage system has already been designed and engineered by Hill Engineers.

 

At the end of the meeting, town meeting member Bruce Shepley thanked the Board of Selectmen and town staff for their work.

 

"I would just like, on behalf of myself, to say thank you very much. It's encouraging. We're seeing an influx of good things happening here in Adams," he said.


Tags: special town meeting,   wastewater,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Adams Man Gets 20 Years for Child Sex Assault

PITTSFIELD, Mass. — An Adams man has been sentenced to 15 to 20 years in state prison for sexually assaulting a child. 
 
Michael Hiser, 39, was found guilty by a Superior Court jury on June 11 of single counts of aggravated indecent assault and battery on a child under 14, indecent assault and battery on a child under 14 and indecent exposure; two counts of posing or exhibiting a child in the nude, and three counts of photographing an unsuspecting nude child.
 
He was sentenced on Tuesday to prison for the aggravated indecent assault, with further sentencing of eight to 10 years for the indecent assault, four to five for the photographing and 2 1/2 for indecent exposure, all to be served concurrently. Hiser was also sentenced to five years probation on the posing or exhibiting charge, with conditions not to contact or go near the victim and no unsupervised contact with minors. He will have to register with the Sex Offender Registry Board and take sex offender treatment. 
 
Investigators found that from approximately 2020 to 2022, Hiser would sneak into the victim's room at night to inappropriately photogram and touch them inappropriately. Additionally, he would follow the victim around the house and photograph them with inappropriate intent. An additional incident involved the defendant acting in a sexual manner in the presence of the minor and the investigators found multiple explicit images of the victim on Hiser's phone.
 
"Cases of child abuse and child sexual abuse shake the foundation of our community," said Berkshire District Attorney Timothy Shugrue. "Today justice has been served on behalf of a child who survived unimaginable abuse. While the guilty verdict and lengthy sentence do not take away any of the horrific crimes the defendant committed, I hope today provides an opportunity for both the child and their family to move forward."
 
Chief of the Child Abuse Unit Andrew Giarolo represented the commonwealth and Associate Director of Victim Witness Advocates Kristen Rapkowicz served as the victim witness advocate on behalf of the DA's Office. The Adams Police Department with assistance from a Williamstown Police Department's Berkshire Law Enforcement Task Force digital evidence unit officer led the investigation.
View Full Story

More Adams Stories