Adams Approves Extra Wastewater Treatment Plant Funds

By Brian RhodesiBerkshires Staff
Print Story | Email Story

ADAMS, Mass. — Town meeting members at Tuesday's special town meeting approved an additional $2.37 million in funding for improvements to the wastewater treatment plant. 

 

Members supported the funds 95-4, in addition to approving the three other warrant articles with little discussion. Town meeting gave the OK to just more than $5 million for the plant in 2021. 

 

Town Administrator Jay Green explained the only bid for the project came in over this amount, necessitating the extra borrowing. 

 

"The estimate was a little over $5 million, then a year later, in the bidding process, same scope, with inflation it went up to $6.5 million. That's approximately $1.4 million over estimate," he said. "The state requires that you add a 5 percent contingencies, so that's [another] $325,000 ... when you take the construction service cost of $597,000 and you take the one bid that we got a year after it was estimated at $1.4 million, that comes up to $2.3 million that you have in front of you tonight." 

 

The total cost of the project is an estimated $7.42 million. Construction is already ongoing, as the project went out to bid earlier in the year.

 

Green said the plant can handle between 10 and 12 million gallons of wastewater flow a day, while the town only currently creates about 2.5 million. He said this should allow the town to operate the plant while keeping up with needed maintenance. 

 

"These upgrades are structural. They're electrical. We're handling things that weren't done in the 2005 upgrade. They're doing some things that, what needed to be done in 2005, now are being done," Green said. "Whether we see it, I don't think so. But this creates redundancy and allows for much better preventative maintenance. 

 

Selectman Joseph Nowak asked if the bond would prevent the town from getting any future grant funding for the project. Green said he was unsure but felt the town was getting the best deal possible. He also noted that the Adams expects to receive $378,713 in ARPA loan forgiveness and $499,901 in disadvantaged community loan forgiveness toward the project. 

 

"That's why I say that $7.4 million is the total project cost. That's what the contractor gets, part of that goes to Tighe & Bond, the engineering firm. Our debt service will not be based on $7.4 million," Green said. 

 

The Board of Selectmen approved the borrowing for the project at a meeting earlier this month

 

Article 2 appropriates $15,000 from Cemetery, Parks and Grounds' Master Plan account to its capital account. The funds, appropriated in 2016, were leftover for a project that is now complete.

 

Article 3 releases free cash from two projects that had leftover funds. The first, for a water meter replacement, totals $9,583.04 and the second, for equipment in the assessor's office, totals $8,696.74.

 

Article 4 authorizes the Board of Selectmen to accept an easement to install drainage lines from lower Linden Street to Commercial Street. The area has been prone to flooding with the current drainage system, and the easement will come at no cost to the town.

 

The new drainage system has already been designed and engineered by Hill Engineers.

 

At the end of the meeting, town meeting member Bruce Shepley thanked the Board of Selectmen and town staff for their work.

 

"I would just like, on behalf of myself, to say thank you very much. It's encouraging. We're seeing an influx of good things happening here in Adams," he said.


Tags: special town meeting,   wastewater,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Business Success, Storm Clouds Highlighted at 1Berkshire Annual Meeting

By Stephen DravisiBerkshires Staff

Cheshire native JD Chesloff of the Massachusetts Business Roundtable delivers the keynote address on Thursday.
 
ADAMS, Mass. — One of the county's biggest employers and one of its newest small businesses were touted on Thursday at 1Berkshire's annual meeting at the Adams Theater.
 
The vice president of maritime and strategic systems strategy and business development at General Dynamics shared news of a major expansion at the Pittsfield plant.
 
"We plan to hire over 200 employees in Pittsfield over the next 12 to 14 months," Chris Montferret said. "Business is booming. And of those 200 employees, over 200 will be engineers."
 
Currently, General Dynamics employs more than 1,600 people in Pittsfield, up from a low of 500 in 1997, Montferret said, reminding the 1Berkshire membership of the importance of growth for an anchor like his firm.
 
"As you all know as employers, the multiplier of economic development when you bring a full-time employee in is amazing for the entire community," Montferret said.
 
1Berkshire is dedicated to advancing the local economy by advocating for and serving local businesses while helping attract visitors to the region.
 
The development organization's president and CEO used the annual meeting to talk about 1Berkshire's economic development team, which averages more than 100 consultations per year with local entrepreneurs — over 40 percent with businesses owned by women, members of minority groups or immigrants.
View Full Story

More Adams Stories