Adams Approves Extra Wastewater Treatment Plant Funds

By Brian RhodesiBerkshires Staff
Print Story | Email Story

ADAMS, Mass. — Town meeting members at Tuesday's special town meeting approved an additional $2.37 million in funding for improvements to the wastewater treatment plant. 

 

Members supported the funds 95-4, in addition to approving the three other warrant articles with little discussion. Town meeting gave the OK to just more than $5 million for the plant in 2021. 

 

Town Administrator Jay Green explained the only bid for the project came in over this amount, necessitating the extra borrowing. 

 

"The estimate was a little over $5 million, then a year later, in the bidding process, same scope, with inflation it went up to $6.5 million. That's approximately $1.4 million over estimate," he said. "The state requires that you add a 5 percent contingencies, so that's [another] $325,000 ... when you take the construction service cost of $597,000 and you take the one bid that we got a year after it was estimated at $1.4 million, that comes up to $2.3 million that you have in front of you tonight." 

 

The total cost of the project is an estimated $7.42 million. Construction is already ongoing, as the project went out to bid earlier in the year.

 

Green said the plant can handle between 10 and 12 million gallons of wastewater flow a day, while the town only currently creates about 2.5 million. He said this should allow the town to operate the plant while keeping up with needed maintenance. 

 

"These upgrades are structural. They're electrical. We're handling things that weren't done in the 2005 upgrade. They're doing some things that, what needed to be done in 2005, now are being done," Green said. "Whether we see it, I don't think so. But this creates redundancy and allows for much better preventative maintenance. 

 

Selectman Joseph Nowak asked if the bond would prevent the town from getting any future grant funding for the project. Green said he was unsure but felt the town was getting the best deal possible. He also noted that the Adams expects to receive $378,713 in ARPA loan forgiveness and $499,901 in disadvantaged community loan forgiveness toward the project. 

 

"That's why I say that $7.4 million is the total project cost. That's what the contractor gets, part of that goes to Tighe & Bond, the engineering firm. Our debt service will not be based on $7.4 million," Green said. 

 

The Board of Selectmen approved the borrowing for the project at a meeting earlier this month

 

Article 2 appropriates $15,000 from Cemetery, Parks and Grounds' Master Plan account to its capital account. The funds, appropriated in 2016, were leftover for a project that is now complete.

 

Article 3 releases free cash from two projects that had leftover funds. The first, for a water meter replacement, totals $9,583.04 and the second, for equipment in the assessor's office, totals $8,696.74.

 

Article 4 authorizes the Board of Selectmen to accept an easement to install drainage lines from lower Linden Street to Commercial Street. The area has been prone to flooding with the current drainage system, and the easement will come at no cost to the town.

 

The new drainage system has already been designed and engineered by Hill Engineers.

 

At the end of the meeting, town meeting member Bruce Shepley thanked the Board of Selectmen and town staff for their work.

 

"I would just like, on behalf of myself, to say thank you very much. It's encouraging. We're seeing an influx of good things happening here in Adams," he said.


Tags: special town meeting,   wastewater,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Letter: Progress Means Moving on Paper Mill Cleanup

Letter to the Editor

To the Editor:

Our town is facing a clear choice: move a long-abandoned industrial site toward cleanup and productive use or allow it to remain a deteriorating symbol of inaction.

The Community Development team has applied for a $4 million EPA grant to remediate the former Curtis Mill property, a site that has sat idle for more than two decades. The purpose of this funding is straightforward: address environmental concerns and prepare the property for safe commercial redevelopment that can contribute to our tax base and economic vitality.

Yet opposition has emerged based on arguments that miss the point of what this project is designed to do. We are hearing that basement vats should be preserved, that demolition might create dust, and that the plan is somehow "unimaginative" because it prioritizes cleanup and feasibility over wishful reuse of a contaminated, aging structure.

These objections ignore both the environmental realities of the site and the strict federal requirements tied to this grant funding. Given the condition of most of the site's existing buildings, our engineering firm determined it was not cost-effective to renovate. Without cleanup, no private interest will risk investment in this site now or in the future.

This is not a blank check renovation project. It is an environmental remediation effort governed by safety standards, engineering assessments, and financial constraints. Adding speculative preservation ideas or delaying action risks derailing the very funding that makes cleanup possible in the first place. Without this grant, the likely outcome is not a charming restoration, it is continued vacancy, ongoing deterioration, and zero economic benefit.

For more than 20 years, the property has remained unused. Now, when real funding is within reach to finally address the problem, we should be rallying behind a practical path forward not creating obstacles based on narrow or unrealistic preferences.

I encourage residents to review the proposal materials and understand what is truly at stake. The Adams Board of Selectmen and Community Development staff have done the hard work to put our town in position for this opportunity. That effort deserves support.

Progress sometimes requires letting go of what a building used to be so that the community can gain what it needs to become.

View Full Story

More Adams Stories