Adams Approves Extra Wastewater Treatment Plant Funds

By Brian RhodesiBerkshires Staff
Print Story | Email Story

ADAMS, Mass. — Town meeting members at Tuesday's special town meeting approved an additional $2.37 million in funding for improvements to the wastewater treatment plant. 

 

Members supported the funds 95-4, in addition to approving the three other warrant articles with little discussion. Town meeting gave the OK to just more than $5 million for the plant in 2021. 

 

Town Administrator Jay Green explained the only bid for the project came in over this amount, necessitating the extra borrowing. 

 

"The estimate was a little over $5 million, then a year later, in the bidding process, same scope, with inflation it went up to $6.5 million. That's approximately $1.4 million over estimate," he said. "The state requires that you add a 5 percent contingencies, so that's [another] $325,000 ... when you take the construction service cost of $597,000 and you take the one bid that we got a year after it was estimated at $1.4 million, that comes up to $2.3 million that you have in front of you tonight." 

 

The total cost of the project is an estimated $7.42 million. Construction is already ongoing, as the project went out to bid earlier in the year.

 

Green said the plant can handle between 10 and 12 million gallons of wastewater flow a day, while the town only currently creates about 2.5 million. He said this should allow the town to operate the plant while keeping up with needed maintenance. 

 

"These upgrades are structural. They're electrical. We're handling things that weren't done in the 2005 upgrade. They're doing some things that, what needed to be done in 2005, now are being done," Green said. "Whether we see it, I don't think so. But this creates redundancy and allows for much better preventative maintenance. 

 

Selectman Joseph Nowak asked if the bond would prevent the town from getting any future grant funding for the project. Green said he was unsure but felt the town was getting the best deal possible. He also noted that the Adams expects to receive $378,713 in ARPA loan forgiveness and $499,901 in disadvantaged community loan forgiveness toward the project. 

 

"That's why I say that $7.4 million is the total project cost. That's what the contractor gets, part of that goes to Tighe & Bond, the engineering firm. Our debt service will not be based on $7.4 million," Green said. 

 

The Board of Selectmen approved the borrowing for the project at a meeting earlier this month. 

 

Article 2 appropriates $15,000 from Cemetery, Parks and Grounds' Master Plan account to its capital account. The funds, appropriated in 2016, were leftover for a project that is now complete.

 

Article 3 releases free cash from two projects that had leftover funds. The first, for a water meter replacement, totals $9,583.04 and the second, for equipment in the assessor's office, totals $8,696.74.

 

Article 4 authorizes the Board of Selectmen to accept an easement to install drainage lines from lower Linden Street to Commercial Street. The area has been prone to flooding with the current drainage system, and the easement will come at no cost to the town.

 

The new drainage system has already been designed and engineered by Hill Engineers.

 

At the end of the meeting, town meeting member Bruce Shepley thanked the Board of Selectmen and town staff for their work.

 

"I would just like, on behalf of myself, to say thank you very much. It's encouraging. We're seeing an influx of good things happening here in Adams," he said.


Tags: special town meeting,   wastewater,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Hoosac Valley Train Car Catches Fire

Staff ReportsiBerkshires
ADAMS, Mass. — A malfunctioning heating pad is the suspected cause for a fire at one of the Hoosac Valley Service's train cars. 
 
The fire broke out about 4:30 p.m. on Saturday, and posts to Facebook show heavy flames and smokes on the side of the historic Budd Car 41. 
 
"We got dispatched to a train on fire, and when we got here, that's exactly what it was. It was a train on fire," said Fire Chief David Lennon. "We did have flames showing. We did have information from dispatch that there were no people on board. It was locked."
 
The incident is still under investigation but he said the best guess was the heating pad to keep the lines warm malfunctioned and the drip pads underneath ignited. 
 
Melanie Seiden, executive director of the Berkshire Scenic Railway Museum, said the weekend rides had been completed for the day and only some staff were still at the Adams Station. 
 
The rides are approximately an hour and the last one is usually completed around 4 p.m. The last two weekends have been fall foliage rides and a Halloween one is scheduled for next weekend. 
 
Seiden said car will be taken out of service and that scheduled rides will go on. 
 
View Full Story

More Adams Stories