The town would have to determine which circuit to tie into if it moves forward with a photovoltaic array. This shows the 18C BERKSHIRE circuit. This shows the 19A DOREEN circuit.
DALTON, MASS. — The Green Committee is working to obtain information from Eversource to inform the possibility of developing solar polar photovoltaic arrays in town.
The committee approved using $250 during its meeting last week for a pre-application to Eversource. This application will provide data that will inform how to develop a solar PV array in town.
The efforts to develop PV arrays is supported by the state Department of Energy Resources' Green Communities initiative and has been part of the town's master plan since 2016.
One of the master plan's goals in the infrastructure section is to improve the town's energy efficiency.
To minimize the tax impact of this goal, one of the objectives is to "support the development of solar farms on town property to reduce the cost of electricity for the town."
Upon submitting a pre-application, Eversource is required to send back a range of data within 10 business days otherwise it's free.
The town needs to determine how much it can load the two circuits available. There are two lines that come into Dalton — 18C BERKSHIRE and 19A DOREEN.
According to a Eversource representative, the company cannot provide that information without submitting the pre-application.
Eversource's DC Hosting Capacity map does not have all the information needed to inform future projects and is inaccurate because it represents people who submitted applications but may not have a live PV array, Green Committee member Todd Logan said later.
The Green Committee will use the Senior Center as a mock location for a 375-kilowatt solar array in its pre-application because the two circuits border the center. The 18C BERKSHIRE circuit is located on High Street and 19A DOREEN on Glennon Avenue. Dalton would have to determine which circuit to connect to.
Since the Green Committee is not proposing building a solar array on the land in front of the Senior Center, this gives the town "the opportunity to figure out which circuit would be best suited for an income generating and power generating PV array," Logan said.
The pre-application will provide data, including the substation transformer rating, the substation's circuit voltage and name, the phase available near the site, and the distance from the phase service if it's a single phase.
It also includes standards for the interconnection of distributed generation, including information on aggregate connected facilities that have not yet been interconnected, the interconnecting customer's network types and nearby feeders, and potential system constraints that may impact the proposed facility, among other things.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Pittsfield Sewer Lining Replacement Projects
PITTSFIELD, Mass.—; The City's Department of Public Services and Utilities sewer lining replacement project continues the week of Dec. 8.
The sewer lining will be replaced in several locations as outlined in the schedule below. This work includes lining aging sewer pipes to help prevent future breaks within the sewer line. There should be minimal to no impact on residential sewer lines during this work.
Dec. 8-10: Danforth Avenue (7:00 a.m. to 9:00 p.m.)
Dec. 11: Wahconah Street, between North Street and Seymour Street & Park Street between
Wahconah Street and Seymour Street (Overnight work-6:00 p.m. and 5:00 a.m.)
During this time, Wahconah Street, from North Street to Seymour Street, and Park Street, from Wahconah Street to Seymour Street, will be closed to traffic. Residents and emergency vehicles will be allowed to enter and exit the street if necessary. For more information about this project, please contact the Water Department at (413) 499-9339.
At least half a foot of snow was dumped on Pittsfield during Tuesday's storm, and plowing went fairly smoothly, according to the DPW commissioner. click for more
The Berkshire Mall owners have offered the town a $1.25 million loan to dissolve the Baker Hill Road District, while the road district wants to take the property by eminent domain and says Target is on board. click for more
The City Council unanimously approved a total of $1 million in Pittsfield Economic Development Funds to expand the Berkshire Innovation Center and add a new company. click for more
The plan was last updated in 2009, and Pittsfield has engaged VHB engineering firm for a yearlong process of bringing it to the 2020s and beyond.
click for more