Pittsfield Announces Street Improvement Project Schedule

Print Story | Email Story

PITTSFIELD, Mass. — The City of Pittsfield has announced scheduled street improvements from April 28 through May 2.

From April 28 to April 30, structure lowering will occur on Daniels Avenue, Newell Street, and Meadow Lane. Milling is scheduled for Daniels Avenue on April 29, followed by the first course of paving on April 30. Milling will take place on Newell Street and Meadow Lane from May 1 to May 2.

On-street parking will be prohibited on these streets between 6 a.m. and 6 p.m. during the work periods.

Berkshire Gas will continue underground utility work at the intersection of East Street and Silver Lake Boulevard. On April 28 and April 29, traffic will be reduced to one lane in both directions at this intersection from 7:00 p.m. to 5:00 a.m.

Motorists are advised to exercise caution when traveling in these areas. The schedule is subject to change due to weather conditions.

 

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield ConCom OKs Stairs at Pontoosuc Lake

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass.— Shoreline access stairs are coming to the south side of Pontoosuc Lake. 

Last week, the Conservation Commission approved an amendment to the Order of Conditions for work at Pontoosuc Lake Park.  There will be two stair sets on the south shoreline, and additional bank stabilization. 

In 2025, the park's south side saw new stairs from the parking lot, a boardwalk, and other improvements.  Later phases of the project will enhance the north side of the park for swimming, and remedy a concrete barrier wall that is partially underwater. 

"Generally, what we're looking to do at Pontoosuc Lake Park is install some stair sets in two locations to help folks access from up above the bank, over the bank, and into the water," Parks, Open Space, and Natural Resources Manager James McGrath explained during the July 23 meeting. 

"We're sensitive to some of the issues that are currently existing on the bank, and we're also sensitive to some of the needs for lake recreation out there."

Stairs for water access will be placed on the shoreline at the beginning of the boardwalk, where it is highly eroded, and the second staircase will be at the extreme western end of the project area, which has around 100 feet of highly eroded bank. 

Additional brush layering will also stabilize the bank. 

An area near the boat ramp where live stakes were vandalized will see them replanted after the ConCom found some of the bank erosion was worse than believed on a site visit last year. 

The city originally proposed not replanting the area where live stakes were removed. 

View Full Story

More Pittsfield Stories