image description
Conservation Commissioners get a tour of the dredging being done to remove sediment ahead of the Bel Air Dam's removal.
image description
Flooding behind 200-year-old dam concerned the Conservation Commission.
image description
Sediment is being transported off-site to Seneca landfill in New York. The majority of the sediment has been removed, according to construction updates, and should be completed by mid-May.
image description
A cut was made in the dam and pumps installed to lower the water level in the dam's impoundment.
image description
Commissioner get an update on the progress and efforts to reduce flooding.

Flooding Leads Pittsfield ConCom to Bel Air Dam Deconstruction Site

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

PITTSFIELD, Mass. — The Bel Air Dam project team toured the site on Monday with the Conservation Commission to review conditions following a flooding incident

Work has been on hold for two weeks after melting snow and a release of water from Pontoosuc Lake led to water overtopping of the almost 200-year-old, abandoned dam. The project team says deconstruction is still on track to end in December. 

"They have plenty of time to finish the work, so they don't expect that they're going to need extra time, but we're all waiting," reported Robert Lowell, the Department of Conservation and Recreation's deputy chief engineer. 

"… it's unfortunate, but the high-water conditions in the spring, we did have in the contract that the site might flood, so there was supposed to be a contingency for it, and we're now dealing with the complications of that." 

DCR's Office of Dam Safety is leading the $20 million removal of the classified "high hazard" dam, funded by American Rescue Plan Act dollars. It has been an area of concern for more than a decade. 

The dam on Pontoosuc Brook dates to 1832 and was used for nearly a hundred years to power a long-gone woolen mill. It's being targeted for removal, using American Rescue Plan Act funds, because the stacked stone structure poses a significant danger to homes and businesses downstream. Excavation of sediment began last fall by contractor SumCo Eco-Contracting of Wakefield. 

Earlier this month, community members noticed flooding at the site bordering Wahconah Street; water levels were down by the next week. Conservation commissioners called for the site visit with concerns about the effects of the water release and how it is being remedied.  

The group got a look at the large project area near the dam and asked questions. Chair James Conant explained that community members wanted to know the cause of the flooding. 

Jane Winn, former executive director of the Berkshire Environmental Action Team, said this was specifically brought up at the Conservation Commission hearing to ensure this sort of thing didn't happen. 

"I just wanted it on record that this is twice in a row for SumCo in Pittsfield, and I find that unacceptable," she said about the environmental restoration and construction company. 



Contractors put a cut in the water flow for a controlled release and installed two turbidity curtains downstream of the dam. Two 24-inch pipe pumps on site can be used if needed. 

Pontoosuc Lake's water level management is not handled by Pittsfield, and an inquiry has been made about the lake's levels. The lake's spillway is operated by the state Department of Conservation and Recreation, which did some "response actions" to the rising water levels from snowmelt around the weekend of March 11. 

Lowell said, "We could have been better prepared for it." 

Jennifer Doyle-Breen, of AECOM*, which developed the ecological restoration proposal, added that despite the release, the water level at Pontoosuc has remained "pretty high." 


"When I was recently up at the dam, the water was flowing over the top of the dam. There's nothing DCR can do about that once the water gets up that high," she said. 

"There was a lot of snow, and we had a couple of really warm days. I do think that contributed to the situation here." 
 

*Architecture, Engineering, Construction, Operations, and Management
 


 


Tags: conservation commission,   dam removal,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

PCTV Celebrates 40th Anniversary with Community

By Breanna SteeleiBerkshires Staff

PITTSFIELD, Mass. – Many fans, workers, past workers, and city officials gathered at the Berkshire Hills Country Club Friday night to celebrate Pittsfield Community Television turning 40.

The room was alive with people eating, laughing, taking photos in a photo booth and watching snippets from PCTV's past archived programs throughout the decades curated by Operations Manager Dave Cachet.

President of the Board of Directors Sue Doucette acknowledged everyone in attendance and thanked the volunteers who help or have helped bring PCTV to the screen.

She reflected on how much technology has changed since 1986 and on PCTV's role in covering parades, debates and election-night precinct results 

"You heard it and saw it yourself, and you can interpret it your way. Not everybody has this, but we in Berkshire County do, and we need to be forever grateful to the people that have come before us and made this possible. So, for me personally, I love the staff at PCTV and the board members. I never begrudge going to a meeting. I like these people," she said.

Executive Director Shawn Serre said he feels as though this is their "Eras Tour," referencing Taylor Swift's record-breaking concert series. He reminisced about PCTV's eras.

"The first of our eras is the founders' era, that time when this was just an idea tossed around among colleagues with various skills and with an interest in creating a local source of television, but with no funding, no equipment, no facility, no staff, no volunteers other than themselves," he said.

He said the next era starts with PCTV's move to Fourth Street. At this point, they named their first executive director Garrett McCarey and built their first facility at 163 Fourth Street. They made community connections, programs, and learned the ropes, he said, adding that they "pushed the boundaries of what public access could accomplish".

He said the next era is their Federico era, led by former Executive Director Bernard Avalle and changing technology.

"Under his leadership, we moved our entire facility from the old building to a custom-built studio and offices. We expanded from one cable channel to three. We went from analog to digital to high definition," Cachet said. " We went from videotapes to DVDs to video servers and files. We had as many as seven staff members and grew the program. We designed and purchased a mobile production truck. We covered so many meetings, so many meetings. Viewers would look to us with trust on election nights, onn the Fourth of July, at sports events, and at special events. We have become a part of the fabric of life in Pittsfield."

And finally, the multi-platform era.

"Otherwise known as everything, everywhere, all at once. That's what it feels like. It's when we expanded our reach by saving WTBR FM from the wrecking ball and operating it. When we greatly expanded our PCTV sports program of live broadcasts from just about anywhere, we couldn't have imagined being able to do that early on," he said. "It's when, in the depths of the pandemic, we not only continued our regular broadcast and never stopped, but we also launched PCTV Select to provide high-quality video streams, live streams, and video on demand worldwide. When we started Park Square Productions to provide high-quality production services to clients and contribute to our mission."

He said their next era is still being shaped and will need the community to help.

"The next era, well, that one has to be shaped by you, by all of us actually, because after 40 years, we realize the only constant is change, and we know that while cable TV is at the moment still our sugar daddy, it won't be around forever," Cachet said. "But we know how important the kinds of services that we provide are, and the demand to not disappear." 

Rep. Tricia Farley Bouvier said local journalism is important and will save democracy. She presented PCTV a citation from the state House of Representatives signed by her and the Speaker of the House.

View Full Story

More Pittsfield Stories