image description
Conservation Commissioners get a tour of the dredging being done to remove sediment ahead of the Bel Air Dam's removal.
image description
Flooding behind 200-year-old dam concerned the Conservation Commission.
image description
Sediment is being transported off-site to Seneca landfill in New York. The majority of the sediment has been removed, according to construction updates, and should be completed by mid-May.
image description
A cut was made in the dam and pumps installed to lower the water level in the dam's impoundment.
image description
Commissioner get an update on the progress and efforts to reduce flooding.

Flooding Leads Pittsfield ConCom to Bel Air Dam Deconstruction Site

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

PITTSFIELD, Mass. — The Bel Air Dam project team toured the site on Monday with the Conservation Commission to review conditions following a flooding incident. 

Work has been on hold for two weeks after melting snow and a release of water from Pontoosuc Lake led to water overtopping of the almost 200-year-old, abandoned dam. The project team says deconstruction is still on track to end in December. 

"They have plenty of time to finish the work, so they don't expect that they're going to need extra time, but we're all waiting," reported Robert Lowell, the Department of Conservation and Recreation's deputy chief engineer. 

"… it's unfortunate, but the high-water conditions in the spring, we did have in the contract that the site might flood, so there was supposed to be a contingency for it, and we're now dealing with the complications of that." 

DCR's Office of Dam Safety is leading the $20 million removal of the classified "high hazard" dam, funded by American Rescue Plan Act dollars. It has been an area of concern for more than a decade. 

The dam on Pontoosuc Brook dates to 1832 and was used for nearly a hundred years to power a long-gone woolen mill. It's being targeted for removal, using American Rescue Plan Act funds, because the stacked stone structure poses a significant danger to homes and businesses downstream. Excavation of sediment began last fall by contractor SumCo Eco-Contracting of Wakefield. 

Earlier this month, community members noticed flooding at the site bordering Wahconah Street; water levels were down by the next week. Conservation commissioners called for the site visit with concerns about the effects of the water release and how it is being remedied.  

The group got a look at the large project area near the dam and asked questions. Chair James Conant explained that community members wanted to know the cause of the flooding. 

Jane Winn, former executive director of the Berkshire Environmental Action Team, said this was specifically brought up at the Conservation Commission hearing to ensure this sort of thing didn't happen. 

"I just wanted it on record that this is twice in a row for SumCo in Pittsfield, and I find that unacceptable," she said about the environmental restoration and construction company. 



Contractors put a cut in the water flow for a controlled release and installed two turbidity curtains downstream of the dam. Two 24-inch pipe pumps on site can be used if needed. 

Pontoosuc Lake's water level management is not handled by Pittsfield, and an inquiry has been made about the lake's levels. The lake's spillway is operated by the state Department of Conservation and Recreation, which did some "response actions" to the rising water levels from snowmelt around the weekend of March 11. 

Lowell said, "We could have been better prepared for it." 

Jennifer Doyle-Breen, of AECOM*, which developed the ecological restoration proposal, added that despite the release, the water level at Pontoosuc has remained "pretty high." 


"When I was recently up at the dam, the water was flowing over the top of the dam. There's nothing DCR can do about that once the water gets up that high," she said. 

"There was a lot of snow, and we had a couple of really warm days. I do think that contributed to the situation here." 
 

*Architecture, Engineering, Construction, Operations, and Management
 


 


Tags: conservation commission,   dam removal,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Rutledge Defense Seeks Dismissal of Rape Charges Over Statute of Limitations

By Sabrina DammsiBerkshires Staff
PITTSFIELD, Mass. — The Superior Court courtroom was filled on Thursday as proceedings resumed on the high-profile case against former Miss Hall's School teacher Matthew Rutledge, with the court hearing arguments on his motion to dismiss.
 
 
On Thursday, Rutledge, represented by attorney Ryan Schiff, appeared before Judge Michael Callahan to seek dismissal of all three counts, arguing that prosecutors were attempting to circumvent the statute of limitations and had failed to disclose what Schiff characterized as "highly exculpatory evidence."
 
More than 100 attendees filled the pews, some wearing orange carnations to show solidarity with the accusers, Melissa Fares and Hilary Simon. 
 
As Rutledge attempted to leave the courtroom following Judge Callahan's departure, several attendees voiced their outrage, shouting "Shame," "You can't hide behind the bad law," and "We know what you did."  
 
Judge Callahan re-entered the courtroom to condemn these outbursts and directed court officers to record their names and bar them from attending future proceedings on this case.
 
The nearly hour-long hearing centered on competing interpretations of the language and legislative intent behind Massachusetts' statute of limitations, particularly whether Rutledge's temporary absences from the state could extend the time prosecutors have to bring charges.
 
View Full Story

More Pittsfield Stories