image description
Conservation Commissioners get a tour of the dredging being done to remove sediment ahead of the Bel Air Dam's removal.
image description
Flooding behind 200-year-old dam concerned the Conservation Commission.
image description
Sediment is being transported off-site to Seneca landfill in New York. The majority of the sediment has been removed, according to construction updates, and should be completed by mid-May.
image description
A cut was made in the dam and pumps installed to lower the water level in the dam's impoundment.
image description
Commissioner get an update on the progress and efforts to reduce flooding.

Flooding Leads Pittsfield ConCom to Bel Air Dam Deconstruction Site

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

PITTSFIELD, Mass. — The Bel Air Dam project team toured the site on Monday with the Conservation Commission to review conditions following a flooding incident

Work has been on hold for two weeks after melting snow and a release of water from Pontoosuc Lake led to water overtopping of the almost 200-year-old, abandoned dam. The project team says deconstruction is still on track to end in December. 

"They have plenty of time to finish the work, so they don't expect that they're going to need extra time, but we're all waiting," reported Robert Lowell, the Department of Conservation and Recreation's deputy chief engineer. 

"… it's unfortunate, but the high-water conditions in the spring, we did have in the contract that the site might flood, so there was supposed to be a contingency for it, and we're now dealing with the complications of that." 

DCR's Office of Dam Safety is leading the $20 million removal of the classified "high hazard" dam, funded by American Rescue Plan Act dollars. It has been an area of concern for more than a decade. 

The dam on Pontoosuc Brook dates to 1832 and was used for nearly a hundred years to power a long-gone woolen mill. It's being targeted for removal, using American Rescue Plan Act funds, because the stacked stone structure poses a significant danger to homes and businesses downstream. Excavation of sediment began last fall by contractor SumCo Eco-Contracting of Wakefield. 

Earlier this month, community members noticed flooding at the site bordering Wahconah Street; water levels were down by the next week. Conservation commissioners called for the site visit with concerns about the effects of the water release and how it is being remedied.  

The group got a look at the large project area near the dam and asked questions. Chair James Conant explained that community members wanted to know the cause of the flooding. 

Jane Winn, former executive director of the Berkshire Environmental Action Team, said this was specifically brought up at the Conservation Commission hearing to ensure this sort of thing didn't happen. 

"I just wanted it on record that this is twice in a row for SumCo in Pittsfield, and I find that unacceptable," she said about the environmental restoration and construction company. 



Contractors put a cut in the water flow for a controlled release and installed two turbidity curtains downstream of the dam. Two 24-inch pipe pumps on site can be used if needed. 

Pontoosuc Lake's water level management is not handled by Pittsfield, and an inquiry has been made about the lake's levels. The lake's spillway is operated by the state Department of Conservation and Recreation, which did some "response actions" to the rising water levels from snowmelt around the weekend of March 11. 

Lowell said, "We could have been better prepared for it." 

Jennifer Doyle-Breen, of AECOM*, which developed the ecological restoration proposal, added that despite the release, the water level at Pontoosuc has remained "pretty high." 


"When I was recently up at the dam, the water was flowing over the top of the dam. There's nothing DCR can do about that once the water gets up that high," she said. 

"There was a lot of snow, and we had a couple of really warm days. I do think that contributed to the situation here." 
 

*Architecture, Engineering, Construction, Operations, and Management
 


 


Tags: conservation commission,   dam removal,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

PHS Community Challenges FY27 Budget Cuts

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — The School Committee received an early look Wednesday at the proposed fiscal year 2027 facility budgets, and the Pittsfield High community argued that $653,000 would be too much of a burden for the school to bear. 

On Wednesday, during a meeting that adjourned past 10 p.m., school officials saw a more detailed overview of the spending proposal for Pittsfield's 14 schools and administration building.  

They accepted the presentation, recognizing that this is just the beginning of the budget process, as the decision on whether to close Morningside Community School still looms. The FY27 budget calendar plans the School Committee's vote in mid-April.

Under this plan, Pittsfield High School, with a proposed FY27 budget of around $8.1 million, would see a reduction of seven teachers (plus one teacher of deportment) and an assistant principal of teaching and learning, and a guidance counselor repurposed across the district.  

The administration said that after "right-sizing" the classrooms, there were initially 14 teacher reductions proposed for PHS. 

"While I truly appreciate the intentionality that has gone into developing the equity-based budget model, I am incredibly concerned that the things that make our PHS community strong are the very things now at risk," PHS teacher Kristen Negrini said. "Because when our school is facing a reduction of $653,000, 16 percent of total reductions, that impact is not just a number on a spreadsheet. It is the experience of our students." 

She said cuts to the high school budget is more than half of the districtwide $1.1 million in proposed instructional cuts. 

Student representative Elizabeth Klepetar said the "Home Under the Dome" is a family and community.  There is reportedly anxiety in the student body about losing their favorite teacher or activities, and Klepetar believes the cuts would be "catastrophic," from what she has seen. 

"Keep us in mind. Use student and faculty voice. Come to PHS and see what our everyday life looks like. If you spend time at PHS, you would see our teamwork and adaptability to our already vulnerable school," she said. 

View Full Story