Conservation Commissioners get a tour of the dredging being done to remove sediment ahead of the Bel Air Dam's removal.
image description
Flooding behind 200-year-old dam concerned the Conservation Commission.
image description
Sediment is being transported off-site to Seneca landfill in New York. The majority of the sediment has been removed, according to construction updates, and should be completed by mid-May.
image description
A cut was made in the dam and pumps installed to lower the water level in the dam's impoundment.
image description
Commissioner get an update on the progress and efforts to reduce flooding.

Flooding Leads Pittsfield ConCom to Bel Air Dam Deconstruction Site

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

PITTSFIELD, Mass. — The Bel Air Dam project team toured the site on Monday with the Conservation Commission to review conditions following a flooding incident

Work has been on hold for two weeks after melting snow and a release of water from Pontoosuc Lake led to water overtopping of the almost 200-year-old, abandoned dam. The project team says deconstruction is still on track to end in December. 

"They have plenty of time to finish the work, so they don't expect that they're going to need extra time, but we're all waiting," reported Robert Lowell, the Department of Conservation and Recreation's deputy chief engineer. 

"… it's unfortunate, but the high-water conditions in the spring, we did have in the contract that the site might flood, so there was supposed to be a contingency for it, and we're now dealing with the complications of that." 

DCR's Office of Dam Safety is leading the $20 million removal of the classified "high hazard" dam, funded by American Rescue Plan Act dollars. It has been an area of concern for more than a decade. 

The dam on Pontoosuc Brook dates to 1832 and was used for nearly a hundred years to power a long-gone woolen mill. It's being targeted for removal, using American Rescue Plan Act funds, because the stacked stone structure poses a significant danger to homes and businesses downstream. Excavation of sediment began last fall by contractor SumCo Eco-Contracting of Wakefield. 

Earlier this month, community members noticed flooding at the site bordering Wahconah Street; water levels were down by the next week. Conservation commissioners called for the site visit with concerns about the effects of the water release and how it is being remedied.  

The group got a look at the large project area near the dam and asked questions. Chair James Conant explained that community members wanted to know the cause of the flooding. 

Jane Winn, former executive director of the Berkshire Environmental Action Team, said this was specifically brought up at the Conservation Commission hearing to ensure this sort of thing didn't happen. 

"I just wanted it on record that this is twice in a row for SumCo in Pittsfield, and I find that unacceptable," she said about the environmental restoration and construction company. 



Contractors put a cut in the water flow for a controlled release and installed two turbidity curtains downstream of the dam. Two 24-inch pipe pumps on site can be used if needed. 

Pontoosuc Lake's water level management is not handled by Pittsfield, and an inquiry has been made about the lake's levels. The lake's spillway is operated by the state Department of Conservation and Recreation, which did some "response actions" to the rising water levels from snowmelt around the weekend of March 11. 

Lowell said, "We could have been better prepared for it." 

Jennifer Doyle-Breen, of AECOM*, which developed the ecological restoration proposal, added that despite the release, the water level at Pontoosuc has remained "pretty high." 


"When I was recently up at the dam, the water was flowing over the top of the dam. There's nothing DCR can do about that once the water gets up that high," she said. 

"There was a lot of snow, and we had a couple of really warm days. I do think that contributed to the situation here." 
 

*Architecture, Engineering, Construction, Operations, and Management
 


 


Tags: conservation commission,   dam removal,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Companion Corner: Loki at Berkshire Humane Society

By Breanna SteeleiBerkshires Staff

PITTSFIELD, Mass. — There's a sweet and playful dog at the Berkshire Humane Society waiting for his new family.

iBerkshire's Companion Corner is a weekly series spotlighting an animal in our local shelters that is ready to find a home.

Loki is a little less than a year old and is a terrier/pit mix who has been at the shelter for about a month.

Canine caregiver and adoption counselor Simone Olivieri told us about Loki. 

"He is very friendly, very social. He loves every single human. He's good with other dogs. He's just a lovely, lovely puppy who has a few things that he could still work on. He is young and learning."

Loki was brought in because his former home didn't have enough time for him and wanted him to be able to have a family who could give him the attention he deserves.

"He was brought in just because they didn't have time to continue working with a puppy," she said. "So nothing, nothing too serious, really, just he needs someone who can give him a lot of time, because he really does need that time, that attention as he grows and matures and works on this training."

He is still young so he has a bit to learn and has been hard at work learning new things including potty training and playing with other dogs.

"He can get a little bit mouthy, so sometimes, when he gets excited with his toys, he mouths on your hands a little bit. So that's something that we're working on showing him just more appropriate uses of his mouth when he's tugging," Olivieri  said. "Also, he can be a little bit reactive when he is out on walks and he can see other dogs, he tends to want to bark, and it's all just out of excitement and wanting to go see the other dog. So these are a couple things that we are working on with him here at the shelter, and he's been doing really, really well." 

Loki loves to play and go outside and will need a family who will want to take him on lots of walks. He can do well with a dog his size with introduction but should not go to a home with cats. They also say children 10 and older because Loki can be a little jumpy.

"He is very active, and he loves to go on hikes and walks and a lot of playtime. So someone who can devote a lot of that time to him, because he just wants to adventure," she said. "He wants to do everything. And also he could work on some training. Someone who would also devote some time to doing some training classes and really working with him on some reactivity and some mouthiness."

Loki is a great friend to play with other dogs and also loves to tug on stuffed animals and play fetch. While you may have to train him, he loves to learn and will be a great student and snuggle buddy.

"He loves to play with other dogs. He's a very social boy. He adapts his play style really well to other dogs. He loves to go for walks. He loves to play tug. He loves his stuffies here. He likes to play fetch. He loves to learn. He really likes to train. He really likes to be with you. He gives really good eye contact, good engagement. He loves learning new things. And more than just learning, he loves doing it with people. He just likes spending time with people. He also really likes to cuddle. Once his daily exercise needs are met. He's like a really good snuggle buddy."

Loki loves to meet anyone and everyone and is excited for his new family.

View Full Story

More Pittsfield Stories