image description
Water was released from Pontoosuc Lake, causing some flooding around the Bel Air Dam, which is coming down.

State Issues Project Update After Flooding at Pittsfield's Bel Air Dam

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

PITTSFIELD, Mass. — The state says recent flooding near the Bel Air Dam is being managed, and was caused by a release of water from Pontoosuc Lake. 

The City of Pittsfield shared an update from the Massachusetts Department of Conservation and Recreation on Tuesday, having received inquiries this week about flooding near the almost 200-year-old, abandoned dam that is scheduled to be removed. 

DCR and the contractor, SumCo, said they are aware that there was flooding on the site last week, and that it was because of a release of water from Pontoosuc Lake. 

Water levels appear to be decreasing in the new week. River flows and water levels will continue to be monitored, and the state has enacted a couple of preventative measures. 

Removal of the dam structure began this month. 

"As of Monday March 16, we have not observed any large sediment plumes discharging from Bel Air Dam, or substantial sediment in the water discharging through the cut in the dam," DCR reported on Monday. 

"Two preparations were made in advance of construction activities that are now helping to manage water levels and reduce sediment movement: 1) an intentional cut in the Bel Air dam allows a controlled release of water, and 2) two turbidity curtains installed downstream of the dam are minimizing the transport of sediments and are being monitored and maintained as needed." 


Water levels have decreased from the high levels observed last week, and SumCo is setting up large pumps to try to maintain or lower the current water level in the Bel Air impoundment throughout Monday and Tuesday's rain. 

DCR's Office of Dam Safety is leading the $20 million removal of the classified "high hazard" dam, funded by American Rescue Plan Act dollars. It has been an area of concern for more than a decade, with the city and DCR conducting inspections, maintenance, and repairs. 

In 2020, it was identified as a high-priority project. It aims to improve the area's safety while also restoring the wetland and wildlife habitat through a combination of planting, sediment control, and removal of invasive species. 

The 26.5-by-200-foot structure was built in 1832 and was used to generate power for a woolen mill into the 1920s.

The city took it by eminent domain because the site owner is deceased. Construction teams have been working to excavate sediment from since last summer, and DCR reported that the majority of the sediment has been excavated. Sediment excavation is expected to be complete by mid-May.  

Testing over the last five years has identified accumulated sediment with elevated levels of metals and pH, among others. The project involves removing 35,000 cubic yards of substrate in order to reconnect and contour the river channel. A cap will then be placed over those grades, per the Massachusetts Contingency Plan.

On March 12, DCR shared that periodic truck traffic will continue entering and leaving the site from and to Wahconah Street to load and transport sediment off-site, currently to the Seneca landfill in New York State.
 


Tags: dam,   flooding,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

State Housing Secretary Tours Downtown Pittsfield Developments

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — The state's new secretary of the Executive Office of Housing and Livable Communities on Monday saw how local developers are transforming historic buildings into downtown housing units. 

Secretary Juana Matias, appointed to the role in February, toured the former St. Joseph's High School on Maplewood Avenue and the near-complete Wright Building Block on North Street.   

Matias observed local leaders working collaboratively to dismantle bottlenecks in housing production, something she said the administration wants to see across all 351 municipalities.  

"This is a perfect model of the partnerships we want to see, and we love coming to the ground and seeing how people are leveraging public taxpayer dollars to help address the issue of our time, which is housing production," she said after the tours. 

Developer David Carver, of Scarafoni Associates & CT Management Group, is seeking support from the state Housing Development Incentive Program to transform St. Joe's into apartments, and Allegrone Companies has secured millions from the program towards the Wright Building renovation

They first visited the shuttered school that functioned as a shelter during the onset of the COVID-19 pandemic, greeted by broken windows and leaving with Carver's vision. 

The plan is to transform the school with good bones into 19 apartments, 20 percent designated affordable, and 30 percent of the building for commercial use.  Units are expected to cost between $1,700 and $1,900 per month; 14 one-bedroom units and five two-bedroom units are planned. 

The project team is in talks with the nearby Berkshire Family YMCA to expand their childcare activities to the building's lower level.  Residents and the daycare would use different entrances. 

View Full Story

More Pittsfield Stories