Electrical Improvements Advance at Pittsfield Municipal Airport

By Sabrina DammsiBerkshires Staff
Print Story | Email Story
PITTSFIELD, Mass. — In 2025, the Pittsfield Municipal Airport constructed a new 400-foot taxi lane but by February 2026, one piece was still missing: electricity.
 
Without power connected to the new taxi lane, the airport was unable to begin generating the revenue anticipated from the project, Airport Manager Anita Akor-Yeboah said during a city council meeting in February. 
 
During the recemt Airport Commission meeting, it was announced that the closeout for the design portion of the project was submitted to the agencies on Aug. 21 and hopefully by the end of the week the airport will be sending the closeout for the construction phase portion of that project. 
 
In February, the city approved the appropriation of $445,000 from certified free cash for electrical improvements. According to the meeting minutes, the Federal Aviation Administration and state Department of Transportation the amount will be reimbursed when complete.
 
At the time of the appropriation, the Pittsfield Municipal Airport sent a letter to Mayor Peter Marchetti explaining that the project will include, but is not limited to, removing  existing utility poles and overhead wire, installing electrical handholes, pullboxes, conduits and wire, relocating existing area lights, and pavement patching. 
 
The $445,000 electrical improvement project, which includes a 10 percent contingency over the $403,204 construction bid, is expected to be funded 95 percent by the Federal Aviation Administration, 2.5 percent by MassDOT Aeronautics and 2.5 percent by the city.
 
In August, the FAAA awarded the city with $256,085.26 under the Airport Infrastructure Grants program for Phase 3 electrical improvements to a new 400-foot taxi lane serving a non-exclusive hangar development area at Pittsfield Municipal Airport.

Tags: pittsfield airport,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield Considers CPA Funds for Pontoosuc Lake Park Improvements

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — The city will pursue Community Preservation Act funding for the second phase of renovations to Pontoosuc Lake Park. 

Last Tuesday, the Parks Commission endorsed seeking $100,000, about 10 percent of the estimated project cost, in CPA funds. Pontoosuc's public park has two sides; the south end off Hancock Road had the first round of work.

Park, Open Space and Natural Resource Program Manager James McGrath presented near-final designs, and commissioners suggested a CPA application for financial support, as this is an open space and recreation project. 

"The park isn't radically changed. It keeps its sort of openness," McGrath explained, adding that the design provides accessibility, gathering space, established shade from the sun, and a "nice entry into the lake." 

"… In a nutshell, that's the plan as it stands now. I'll call this 75 percent because I think the final plan will still need to evolve and work with you all to make certain we get this right."

The design proposes a sidewalk that keeps visitors out of the parking lot as they enter, a widened pathway to the lake, with an arm extending to the sandy shore, and floating swim platforms in the water, among other new elements. 

Pittsfield had two options for the failing concrete wall on the north side: replace it or remove it. The plan removes the wall and carves out a beach area, reminiscent of what was across the channel decades ago. 

During public comment, resident Larry Ward pressed for the design to include sanitary facilities, among other concerns. The city is still considering how changing and bathroom facilities will look, currently planning a three-sided wood enclosure with two accessible portable toilets.