WILLIAMSTOWN, Mass. — The Mount Greylock School Building Committee last week voted to authorize a quarter-million dollar change order that, as written, did not sit well with several members of the committee.
At issue was an undisclosed modification to the $65 million addition/renovation project related to building security. Taking advantage of an exception to the commonwealth's Open Meeting Law, the committee held a one-hour executive session at the start of its June 1 meeting.
It then voted in public on the monetary impact of the issue it discussed behind closed doors. And although the committee did not reveal exactly what the issue was, at least one member had concerns about the process that got the committee to the point of making the change, and another member pushed for language in the motion that would have required the project to choose "the lower cost proposal" if all other factors were equal.
Instead, the committee voted 8-3-1 to approve a motion to accept "a change order with a cost not to exceed $252,000, subject to the vetting of the bids by our construction manager."
Thomas Bartels, an architect and an at-large member of the School Building Committee from Williamstown, and Richard Cohen, an at-large member from Lanesborough, both raised issues with the change order in open session.
Bartels pushed for adding language specifying a preference for the "low bid" in a motion introduced by Hugh Daley, who represents the Williamstown Board of Selectmen on the School Building Committee.
Daley declined to accept the "low bid" language as a friendly amendment.
"I agree 100 percent that the construction manager will make sure they're both quoting the same scope of work," Daley said in a meeting telecast on Williamstown's community access television station, WilliNet. "I guess I would leave it to the CM to maximize the value of those dollars and say that part of that vetting may yield that the lowest bid may not represent the highest value bid. I don't like saying it has to be the lowest-bid dollar value no matter what.
"The CM will vet the bids and deliver to the project the highest total value bid to the project -- not the highest cost but the highest total value. It may be schedule. Maybe one [bidder] can get it faster."
Bartels challenged that notion.
"I don't like this," he said. "I think our architect will review the proposals and determine that they're providing the same quality and the same quantity. What is the fuzzy 'value' thing being introduced here?"
Bartels, Cohen and Chairman Mark Schiek voted against the motion to approve the change order.
Before the vote, Cohen raised concerns about what he characterized as the "rushed" process that led to the vote.
"It's my understanding that the reason we have a change order is that the requirements for these security measures were not included at the time we put out the bids for the project as a whole," Cohen said. "And the reason for that may be that the transition from the previous superintendent to the current [interim] superintendent did not go smoothly or that the previous superintendent did not submit the requirements in time to be placed in the original bidding process.
"I'm not suggesting the full $252,000 is an additional cost but that some amount of that $252,000 is an additional cost. I think it's important that we put that in the public record."
Cohen further said that the June 1 vote and past issues with the commonwealth's procurement process "make us vulnerable to litigation and delays. ... It also means that we're not fulfilling our ethical and fiduciary obligations."
Schiek responded that the School Building Committee had a consulted its legal counsel to make sure it was complying with the procurement law.
"After the fact," Cohen shot back. "After I requested [a legal opinion]."
Schiek said that was correct and did not continue the back-and-forth.
In response to questions raised by Bartels, the district's owner's project manager explained that the $252,000 is covered under the project's budget.
Trip Elmore of Newburyport's Dore & Whittier Architects had less sanguine news about the prospect of the junior-senior high school's gymnasium coming online in the fall as previously expected.
As the OPM explained it to the committee on Thursday, the issue is not the renovation of the gym, per se, but the fact that the mechanical service to the gym goes through other parts of the project that will not be completed until the spring.
"We've run into significant coordination issues because we have an existing system in the building that we're going to abandon in April, and we'll have a new system that won't be available until March-ish next year," Elmore said.
The smoke and fire alarm systems, permanent power and and communications systems would need to be set up on a temporary basis while the rest of the project is completed in order to start using the gym in the fall. The addition and renovation work is slated to be finished in April in order to allow the school to move classrooms into the new three-story academic wing over April vacation and begin demolition on the current academic areas in spring 2018.
"Whatever we do [to bring the gym online earlier] is going to be thrown away four or five months later," Elmore said. "We're trying to get the cost comparison -- of doing what you're doing now or opening the gym whatever the cost. We will have a rough order of magnitude in the next two weeks."
The School Building Committee's next scheduled meeting is July 13.
In other business on Thursday, Principal Mary MacDonald told the committee that the vendor selected to supply lockers to the project cannot deliver them in the charcoal gray color favored by the project's design working group.
"They would do it for more funding and an extra four weeks," MacDonald said. "We were were looking at alternate colors, particularly the grays, and given the gray trim and linoleum tile and wainscoting, the grays from this company are pretty bleak. It looks like you're either in a submarine or in prison.
"So we're not going to go with the gray. The color that has risen the top is called steel blue. It's a very deep blue, similar to the charcoal gray we were looking at."
Meanwhile, Bartels reported to the committee looking at the possible amphitheater and parking lot are close to bringing recommendations to the full committee.
"I think we're zeroing in on good solutions for both," Bartels said. "There are two solutions beyond the original one for the amphitheater. There's a Plan B and C that are more natural.
"For the parking lot, there was an in-depth discussion. ... I think we're pretty close to resolving that and coming up with a good-looking parking lot that meets our requirements."
Earlier this spring, the committee voted to order designs for the two site projects from its architect so it could decide at a later date whether to add either or both back into the scope of the project.
That vote elicited criticism from the Lanesborough Board of Selectmen. On Thursday, Schiek read into the record a letter from the town of Lanesborough asking the school district to pay for the parking lot and amphitheater out of a $5 million capital gift from Williams College rather than using taxpayer funds.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
National Grid Hosts Customer Assistance Events In The Berkshires
WALTHAM, Mass. — National Grid will hold a series of in-person Customer Assistance Events this December.
As colder weather sets in, these events are designed to help customers manage winter energy bills and explore cost-saving programs.
In Berkshire County:
Dec. 4 – Town Library, Williamstown, 4:00pm – 8:00pm, 1095 Main Street, Williamstown
Dec. 5 – National Grid Great Barrington Office, 11:00am – 2:00pm, 927 South Main Street, Great Barrington
Many of these events will continue to take place at local senior centers, making it convenient for older residents to access personalized assistance. Attendees at any location will have direct access to National Grid Customer Service Specialists, who can provide personalized guidance on payment options and energy solutions to meet each household's needs.
"As December begins, customers still have opportunities to find support and manage energy costs," said Bill Malee, chief customer officer, National Grid. "We're proud to host many of these events at local senior centers, ensuring customers have easy access to the support they need. Our in-person events are a great way for customers to connect with our team, learn about flexible payment options, and discover energy-saving programs that can help make a real difference this season."
Customers attending in-person events will have the opportunity to meet with representatives from National Grid, who will be on-site to assist with billing issues and provide information on:
Enrolling in National Grid's new Payment Assistance Bundle
Enrolling in Budget Billing
Enrolling in the Energy Discount Rate (for qualifying customers)
Scheduling home energy assessments and sharing information on other energy efficiency opportunities for homes or businesses
These events are part of National Grid's broader commitment to affordability and reliability. Customers can also access support by calling 1-800-233-5325.
National Grid customers can now sign up for a new Payment Assistance Bundle. The bundle combines three solutions to make it easier for managing energy costs and paying down past due amounts over a 12-month period.
Deferred Payment Agreement: Spread out past-due balance into future monthly payments.
Automatic Monthly Payments: Automatically deduct payments from your bank account each month and avoid missing due dates.
Budget Plan: Break down annual energy costs into balanced monthly payments, making it easier to budget and plan expenses.
Customers interested in enrolling in the Payment Assistance Bundle can do so online by visiting ngrid.com/hereforyou, at an in-person event, or by calling 1-800-233-5325.
From couture to canines and from crochet to carols, Williamstown Holiday Walk has you covered if you want to get into the spirit of the season this weekend. click for more
The Williamstown Chamber of Commerce reflected on this past year's success and the launch of a new coupon sales promotion at its annual meeting last week at Greylock Works.
click for more
Our Friday Front Porch is a weekly feature spotlighting attractive homes for sale in Berkshire County. This week, we are showcasing 1030 Simonds Road.
click for more