Pittsfield Sees COVID Spike in Sewage Testing, Another Death

By Brittany PolitoiBerkshires Staff
Print Story | Email Story

PITTSFIELD, Mass. — Sewage testing is showing a post-holiday COVID-19 spike.

On Tuesday, the city's virus concentration in sewage rose to 3 million copies per liter, compared to 1.3 million copies per liter on Christmas. 

Director of Public Health Andy Cambi has indicated that the sewage concentration is the most accurate indicator of the virus' presence in the community because the other metrics don't include at-home tests.

There was also another death that occurred in late December, bringing the city's total to 92.

Hospitalizations have remained low, as there were fewer than 10 COVID patients at Berkshire Medical Center earlier in the week.


Pittsfield saw 32.5 cases per 100,000 people on Tuesday and the positivity rate was 12.1 percent.  There are about 76 estimated actively contagious cases, a metric that has gone down from over 100 at the beginning of the year.

The city remains in the red incidence rate for having more than 10 average cases per 100,000 population and a positivity rate above 5 percent. It has essentially been in this category since last year with some reprieve in the spring that put the city in the lesser "yellow zone."

Before Thanksgiving, there was a low of around 470,000 copies per liter, a percent positivity rate of 5.4 percent, and 13.6 cases per 100,000.

For Berkshire County, there is a 7-day average of 33 cases. The state's 7-day average is nearly 1,600.


Tags: COVID-19,   


More Coronavirus Updates

Keep up to date on the latest COVID-19 news:


If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield ConCom OKs Stairs at Pontoosuc Lake

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass.— Shoreline access stairs are coming to the south side of Pontoosuc Lake. 

Last week, the Conservation Commission approved an amendment to the Order of Conditions for work at Pontoosuc Lake Park.  There will be two stair sets on the south shoreline, and additional bank stabilization. 

In 2025, the park's south side saw new stairs from the parking lot, a boardwalk, and other improvements.  Later phases of the project will enhance the north side of the park for swimming, and remedy a concrete barrier wall that is partially underwater. 

"Generally, what we're looking to do at Pontoosuc Lake Park is install some stair sets in two locations to help folks access from up above the bank, over the bank, and into the water," Parks, Open Space, and Natural Resources Manager James McGrath explained during the July 23 meeting. 

"We're sensitive to some of the issues that are currently existing on the bank, and we're also sensitive to some of the needs for lake recreation out there."

Stairs for water access will be placed on the shoreline at the beginning of the boardwalk, where it is highly eroded, and the second staircase will be at the extreme western end of the project area, which has around 100 feet of highly eroded bank. 

Additional brush layering will also stabilize the bank. 

An area near the boat ramp where live stakes were vandalized will see them replanted after the ConCom found some of the bank erosion was worse than believed on a site visit last year. 

The city originally proposed not replanting the area where live stakes were removed. 

View Full Story

More Pittsfield Stories